Enter Material
Requirement Plan will be usefull for planning group of materials with some name i.e we can Give the
Naming for group of Materials and can give schedule.
Click the Scheduling View to Split the Monthly Demand to Day Wise
Here I am Spliting
Here you can check the MRP results for each material if not satisfied you can come out with out saving
the results, if satisfied you can save the results.
If we run MRP at plant level(MD01) the above screen will not come, the results automatically will get
save.
Select the material and click the Selected Results so that can be seen the results
You can save the results..
After saving the results new screen will come that screen will give information of how many materials
planned and material list with running time. Click Back Button…or press F3
Go to stock Requirement List..MD04
Like based on MRP controller or Vendor etc…so results will come based on the selection screen.
February Month Not Splitted
Will get pop up screen where you can see Planned order number , quantity , dates and sone push
buttons called Prod.Ord(Production Order), Partial Prod Ord etc…
Click Prod.Ord
Click enter..Enter..
Press Enter…
ENTER
Press enter..
Press enter…