Descripcion Unidad Cantidad V.

Unitario 5
Preliminares
Localizacion m2 64.2 $2,140.00 $137,388.00
Valla informativa und 1 $1,149,000.00 $1,149,000.00
Campamento und 1 $1,800,000.00 $1,800,000.00
Demolicion de cunetas existente m3 4 $61,050.00 $244,200.00
Manejo de aguas Gl 1 $1,200,000.00 $1,200,000.00
Señalizacion Preventiva Gl 1 $1,414,000.00 $1,414,000.00

Excavacion manual material comun m3 32.1 $25,300.00 $812,130.00


Solado de 2500 Psi m3 5 $596,800.00 $2,984,000.00
Acero de refuerzo kg 6465 $5,999.00 $38,783,535.00
Concreto 3000 psi m3 92 $866,100.00 $79,681,200.00
Relleno material Seleccionado m3 70 $59,250.00 $4,147,500.00
Transporte de material m3 1750 $1,200.00 $2,100,000.00
Baranda Metalica de proteccion de
3" y 2" ml 20 $277,000.00 $5,540,000.00
Señalizacion vertical informativa y pre und 4 $391,400.00 $1,565,600.00
Resane en concreto de canal Existentem3 1 $866,100.00 $866,100.00
Retiro de material de excavacion m3 36.9 $25,450.00 $939,105.00
Limpieza general gl 1 $272,463.00 $272,463.00
28.875 2.73 4.935
Cemento Arena Triturado $14,869,500.00
676.2 53.613 80.661
84

7 0.555 0.835
Materiales
Cemento 713 20000 $14,260,000.00
Arena 8.12828571 9 $300,000.00 $2,700,000.00
Triturado 12.3472857 13 $700,000.00 $9,100,000.00
Refuerzo 6465 2300 $14,869,500.00
Relleno 12 $350,000.00 $4,200,000.00