BBU3900 V200

Installation Guide

Issue: 08
Part Number: 31504449
Date: 2009-09-30

HUAWEI TECHNOLOGIES Co., Ltd.


Content

Safety Information ………………………………… 2


Installation Tools ………………………………… 3
Installation Scenarios …………………………… 4
Procedure ………………………………………… 6
BBU Hardware …………………………………… 7
Installing the BBU in the APM30 ……………… 8
Installing the BBU in the APM30H(Ver.A)…… 16
Installing the BBU in the APM30(+24V) ……… 18
Installing the BBU in the TMC ………………… 20
Installing the BBU in the TMC11H(Ver.A) …… 22
Installing the BBU in the APM30H(Ver.B)…… 23
Installing the BBU in the TMC11H(Ver.B) …… 27
Installing the BBU in the TMC11H
(Ver.B, +24V)……………………………………… 29
Installing the BBU in the 19-Inch Cabinet …… 31
Installing the BBU on the Wall ………………… 38
Installing the BBU in the OMB Cabinet ……… 42
BBU Hardware Installation Checklist………… 47
Powering On the BBU…………………………… 47
Appendix…………………………………………… 48
Change History …………………………………… 54

1
Safety Information
■ Abide by All Safety Requirements
To ensure personal and equipment safety, abide by safety precautions described in the label on
equipment or in the manual when you install, operate, or maintain the equipment.
The "Safety Warning", "Caution", and "Note" in the manual are not the contents of safety requirements.
They are provided as the supplement to the safety precautions. When operating Huawei products or
equipment, strictly follow all precautions and special safety instructions required by Huawei.
The "Safety Warning" in the manual is only based on the knowledge of Huawei. Huawei will not assume
any responsibility for the loss incurred by operations violating the universal safety rules or standards for
designing, producing, or using the equipment.
■ Abide by the Local Laws and Regulations
When operating the equipment, abide by the local laws and regulations.
■ Requirements for Personnel
The installation and maintenance personnel of Huawei equipment must be strictly trained. They are not
allowed to install, operate, or maintain the equipment until they have mastered the correct operation
method and got familiar with the safety requirements.
■ Symbol Description

If you ignore the warning, serious incidents such as casualties or equipment


damage may be incurred.

If you ignore the warning, incidents such as injuries or equipment damage


may be incurred.

This information is of help to operation.

■ Personal Safety
•Directly contacting or indirectly contacting high voltage power supply through wet objects is lethally dangerous.
•Incorrect high voltage operations will cause incidents such as fire or a shock hazard.
•Never perform any high voltage AC operations or perform operations on a tower or a mast during a
thunderstorm. It can be lethally dangerous.
•Any equipment must be grounded before it is connected to the power supply. Ungrounded equipment can be
lethally dangerous.
•Never perform any hot-line operation.
•Strong RF signals are harmful to human health. Ensure that the transmit antennas are shut down before an
antenna installation or maintenance operation on a tower or mast installed with multiple transmit antennas.
•During an operation involving optical cables, keep your eyes far away from optical output ports and do not
directly look at the optical output ports with bare eyes.
•Take measures to prevent dusts from entering your respiratory tract or eyes when drilling holes.
•Before connecting cables to storage batteries, disconnect the storage batteries from the power supply.
Otherwise, injuries may be incurred.
•When working aloft, take measures to prevent objects from falling.
Equipment Safety
•Before operating the equipment, check the electric continuity of the equipment that requires grounding to
ensure that it is reliably grounded.
•The static electricity produced by human body may damage the static-sensitive components, such as LSI on
boards. Take proper ESD prevention measures, for example, wear ESD wrist straps or gloves to prevent
boards, modules, and electronic components from being destroyed by static of the human body.
•When operating storage batteries, prevent battery short-circuiting and electrolyte overflow or leakage. The
electrolyte corrodes metal objects and the boards, producing rust and causing board short-circuiting.

2
Installation Tools

Torx screwdriver Phillips screwdriver flat-head screwdriver

Adjustable wrench Socket wrench Torque wrench

Power cable crimping pliers RJ-45 crimping pliers Wire cutter

Rubber hammer Hex key(8mm) Cable peeler

hammer drill(Ф8) Heat gun Level bar

Multimeter Long measuring tape Vacuum cleaner

3
Installation Scenarios

1. APM30 2. APM30H(Ver.A)

3. APM30(+24V) 4. TMC

5. TMC11H(Ver.A)

4
Installation Scenarios
6. APM30H(Ver.B) 7. TMC11H(Ver.B)

8. TMC11H(Ver.B, +24V) 9. In 19-inch cabinet

10. On the Wall 11. OMB

5
Procedure

6
BBU Hardware

1. Appearance of the BBU (Unit: mm)

2. Configuration Principles of the BBU Boards

Board Mandatory Full Installation Remarks


/Optional Configuration Slot
WMPT Mandatory 2 S6 and S7 Preferentially configured in S7.

WBBP Mandatory 4 S0 to S3 The WBBP is installed in S3 by default.


If extension CPRI ports are required, the
board is installed in S2.
If extension CPRI ports are not required,
the priority of the installation position of the
board is from s0 to S1, and then to S2.

UBFA Mandatory 1 FAN Configured in FAN slot.

UPEU Mandatory 2 PWR1 and Preferentially configured in PWR2.


PWR2

UEIU Optional 1 PWR1 Preferentially configured in PWR1.

UTRP Optional 4 S0/S1/S4/S5 The priority of the UTRP installation


position of the board is from S4 to S5, and
then to S0 and S1.

USCU Optional 1 S1 or S0 -

The UELP and UFLP need to be optionally configured in the BBU or SLPU on site according to the field
requirements.

7
Installing the BBU in the APM30
a Cable connections

c e
b d
f b a
e

Cable Installation Position

From... To ...
a BBU power cable LOAD3 on PDU PWR on BBU

b E1 transfer cable E1/T1 on WMPT INSIDE on UELP

c E1cable OUTSIDE on UELP Transmission equipment

d Monitoring cable TX/RX on APMI MON1on BBU

e External alarm cable EXT-ALM0 or EXT-ALM1 on UPEU Associated alarm device

f CPRI optical cable CPRI on WBBP CPRI on RRU

8
Installing the BBU in the APM30
b Cable connections of the BBU

Alarm Monitoring
Equipment Equipment

Transmission
equipment
c
b g e d
h
h b
a

f Power System

a BBU Power Cable e Alarm Cable


b E1 surge protection transfer cable f CPRI Optical cable
c E1 Cable g FE cable
d Monitoring Cable h FE surge protection transfer cable

9
Installing the BBU in the APM30
c Installing BBU
1. Install the mounting ears at both sides of
the BBU reversely.

PDU

BBU
M6 bolt

2. Slide the BBU case into the cabinet.

d Installing cables
1. Install power cable.
Connect the OT terminal of the power cable to
the LOAD3 terminal of the PDU, and then fix the
3V3 connector of the power cable to the UPEU
port on the BBU.
LOAD3

NEG(-)

RNT(+)

PWR

The power cable is to be made


depending on field requirements.

10
Installing the BBU in the APM30
d Installing the BBU cables
2. Install optical cables.

Connect the longer end of the optical cable to the CPRI port on the WBBP. Then, connect the other end to the
RRU.

Turn the puller on the optical module


outwards, insert the optical module into
CPRI ports.
Turn outwards the puller on the optical
module.

Optical module

Puller

Remove the dustproof caps from the


optical connectors.
Insert the optical connector at one end of the
CPRI optical cable into the optical module. lead
the CPRI optical cable out of the cabinet along
the left side of the cabinet.

Wrap the fiber tail with the winding pipe till the
first cable tie.
z Connect the fiber tails labeled 1A and 1B to
the CPRI_W port on the RRU.
z Connect the fiber tails labeled 2A and 2B to
one of the CPRI ports on the WBBP

Optical cable
connector

Winding pipe

11
Installing the BBU in the APM30
d Installing the BBU cables
3、Install the E1 transfer cable.
Fix one end of the E1 transfer cable to the INSIDE port on the UELP.
Fix the other end to the E1/T1 port on the WMPT.

4、Install the E1 cable.


Cabling the E1 cable.
Fix one end of the E1 cable to the
OUTSIDE port on the UELP.
Strip the jacket off the E1 cable near
the grounding point at the lower right
corner of the cabinet to expose the
shielding layer. E1 cable
Shielding layer of
the E1 cable
(25mm)

E1 transfer cable

grounding clip

Thread the FE cable through the grounding clip.


Then, tighten the screw on the grounding clip to INSIDE OUTSIDE
make the shielding layer of the FE cable in full
contact with the grounding clip. Finally, connect
the PGND cable on the grounding clip to the
grounding bolt of the APM30.
Shielding layer of
the FE cable

E1/T1

Ensure that both ends of the E1 cable are


disconnected. Then, weld connectors to the
bare wires at one end of the E1 cable all at
once.

12
Installing the BBU in the APM30
d Installing the BBU Cables

5. Install the FE transfer cable (FE


transmission mode).
Connect one end of the FE transfer cable to the
FE0 port near the INSIDE label on the UFLP and
the other end to the FE0 port on the WMPT.

6. Install the FE cable (FE transmission).


Connect one end of the FE cable to the FE0 port
near the OUTSIDE label on the UFLP. Then, lead
the other end out of the cabinet along the right side
of the cabinet.

FE transfer cable

Strip the jacket off the FE cable near FE cable


the grounding point at the lower right
corner of the cabinet to expose the
shielding layer

25mm INSIDE FE0

OUTSIDE FE0

FE0

Thread the FE cable through the grounding clip. Then, tighten the screw on the grounding
clip to make the shielding layer of the FE cable in full contact with the grounding clip.
Finally, connect the PGND cable on the grounding clip to the grounding bolt of the APM30.

Shielding layer
of the FE cable

13
Installing the BBU in the APM30
d Installing the BBU Cables
7. Install the monitoring signal cable between the APMI and the BBU.
Fix the RJ45 connector at one end of the cable to the MON1 port on the UPEU.

MON1

TX+ RX-

TX- RX+

Monitoring signal cable between the


APMI and the BBU

EXT-ALM1

External alarm
cable

8. Install the external alarm cable.


Connect one end of the alarm cable to the EXT-
ALM port on the UPEU, and the other end to the
associated alarm device.
The port on the external alarm device is added
depending on field requirements.

14
Installing the BBU in the APM30
d Installing the BBU Cables
9. Install the EMUA monitoring signal cable.
Cut off the RJ45 connector of the EMUA monitoring signal cable, and then connect the
four exposed bare wires to the RX+, RX-, TX+, and TX- ports on the APMI. For the
relationship between the ports and wires. Fix the DB9 connector to the corresponding
port on the EMUA.

EMUA monitoring signal cable

Pin on the RJ45 Pin on the DB9 Color Type Port on the APMI
Connector Male Connector
X1.1 X2.3 White Twisted pair TX+

X1.2 X2.7 Orange TX-

X1.4 X2.2 Blue Twisted pair RX+

X1.5 X2.6 White RX-

15
Installing the BBU in the APM30H(Ver.A)
a BBU Cable Connections

The procedure for installing the BBU case in the APM30H is the same as that in the APM30. For details, see
pages 8–15. The following figure shows the cable connections of the BBU. Page 17 shows how to install the
monitoring signal cable between the HEUA and the BBU in the APM30H.

b c e d

f b a

c
e

Cable Installation Position

One end is connected to... The other end is


connected to...
a BBU power cable LOAD3 terminal of the PDU PWR port on the BBU

b E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

c E1 cable OUTSIDE port on the UELP External transmission device

d Monitoring signal cable COM IN port on the HEUA MON1 port on the BBU

e External alarm cable EXT-ALM0 or EXT-ALM1 on UPEU Associated alarm device

f CPRI optical cable CPRI port on the WBBP CPRI port on the RRU

16
Installing the BBU in the APM30H(Ver.A)

b Installing the Monitoring Signal Cable between the HEUA and


the BBU

HEUA

COM IN

MON1

UPEU on the
BBU

17
Installing the BBU in the APM30(+24 V)
a BBU Cable Connections

The procedure for installing the BBU in the APM30 (+24 V) is the same as that in the APM30. For details, see
pages 8–15. The following figure shows the cable connections of the BBU. Page 19 shows how to install the
monitoring signal cable of the cabinet.

b c d

b a

e
f

Cable Installation Position

One end is connected to... The other end is


connected to...
a BBU power cable LOAD6 terminal of the DCDU PWR port on the BBU

b E1 surge protection E1/T1 port on the WMPT INSIDE port on the UELP
transfer cable

c E1 cable OUTSIDE port on the UELP External transmission device

d Monitoring signal cable Monitoring port on the cabinet EXT-ALM1 on the UPEU
for the cabinet

e External alarm cable EXT-ALM0 or EXT-ALM1 on UPEU Associated alarm device

f CPRI optical cable CPRI port on the WBBP CPRI port on the RRU

18
Installing the BBU in the APM30(+24 V)
b Installing the Monitoring Signal Cable of the Cabinet

Pin assignment of the monitoring signal cable of the cabinet


Pin on the RJ45 Pin on the RJ45 Wire Color Wire Type Monitoring
Connector Connector equipment

X1.1 X2.1 White/orange Twisted pair APMI

X1.2 X2.2 Orange

X1.3 X2.3 White/green Twisted pair DCDU-03C

X1.6 X2.6 Green

X1.5 X2.5 White/blue Twisted pair Door status sensor

X1.4 X2.4 Blue

X1.7 X2.7 White/brown Twisted pair DC/DC Power


System
X1.8 X2.8 Brown

19
Installing the BBU in the TMC
a BBU Cable Connections

The procedure for installing the BBU in the TMC is the same as that in the APM30. For details, see
pages 8–15.

b c d
a
e b

Cable Installation Position

From... To...
a BBU power cable LOAD6 terminal of the PDU PWR port on the BBU

b E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

c E1 cable OUTSIDE port on the UELP External transmission device

d Monitoring signal cable Wiring terminal of cabinet monitoring ALM1 port on the BBU

e CPRI optical cable CPRI port on the WBBP CPRI port on the RRU

20
Installing the BBU in the TMC
b Installing the BBU Cables

Wiring terminals for the surge


APMI
protection and alarm cables

c
Door status
sensor
d
b

Installing the TMC alarm cable:

a. Fix the RJ45 connector at one end of the alarm cable to the EXT_ALM1 port on the
BBU.
b. Connect the two bare terminals X1.4 (blue) and X1.5 (white) to the alarm wiring
terminals on the door status sensor.
c. Connect the two bare terminals X1.1 (white) and X1.2 (orange) to the OUT+ and
OUT- alarm wiring terminals on the APMI.
d. Connect the two bare terminals X1.3 (white) and X1.6 (green) to the alarm wiring
terminals on the DCDU.

The white and green bare wire terminals are not distinguished from different wiring terminals.

21
Installing the BBU in the TMC11H(Ver.A)
a Installing the BBU

The procedure for installing the BBU in the TMC11H is the same as that in the APM30. For details, see
pages 8–15.

d
a

b c d
a
e b

Cable Installation Position

From... To...
a BBU power cable LOAD6 terminal on the DCDU PWR port on the BBU

b E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

c E1 cable OUTSIDE port on the UELP External transmission device

d Monitoring signal cable Wiring terminal of cabinet monitoring MON1 port on the BBU

e CPRI optical cable CPRI port on the WBBP CPRI port on the RRU

22
Installing the BBU in the APM30H(Ver.B)
a Installing the BBU Case
1. Installing the BBU Case 2. Installing the SLPU Case
Slide the BBU close to the EPS01 to the 2 U Slide the SLPU close to the BBU to the 1 U
space along the guide rails, and then tighten space along the guide rails, and then tighten
the four M6 screws on the BBU panel. the four M6 screws on the SLPU panel.

M6X16 M6X16

EPS01

2N•m 2N•m

BBU
SLPU

M6
screws.

b BBU Cable Connections


Alarm Monitoring
Equipment Equipment

e d
Transmission
equipment

h b a c
f
Power System
b

h g
a BBU Power Cable e Alarm Cable
b E1 surge protection transfer cable f CPRI Optical cable
c E1 Cable g FE cable
d Monitoring Cable h FE surge protection transfer cable

23
Installing the BBU in the APM30H(Ver.B)
c Installing the BBU cables
1. Install power cable.
Connect the OT terminal at one end to the LOAD1 terminal of the EPS01, and then link the 3V3
connector at the other end to the -48V port on the BBU.
LOAD1

2. Install the CPRI optical cable .


The connectors labeled 2A and 2B are connected to the optical module on the port labeled
CPRI0 /1 /2 on the WBBP of the BBU, the connectors labeled 1A and 1B are connected to
the optical module on the port labeled CPRI_W on the RRU.
2.1. Turn the puller on the optical module outwards,
insert the optical module to the port CPRI 0 to
CPRI2.
2.2. Remove the dustproof caps from the optical
connectors. Optical module
Insert the optical connector at one end of the CPRI
Puller
optical cable into the optical module. lead the CPRI
optical cable out of the cabinet along the left side of
the cabinet.
2.3. Wrap the winding pipe at the fiber tails.
TX RX

Winding
pipe

z Connect the fiber tails labeled 1A and 1B to the


CPRI_W port on the RRU.
z Connect the fiber tails labeled 2A and 2B to one
of the CPRI0 to CPRI2 ports on the WMPT

24
Installing the BBU in the APM30H(Ver.B)
c Installing the BBU cables
3. Install the E1 transfer cable.
3.1. Fix one end of the E1 transfer cable to the INSIDE port on the UELP
3.2. Fix the other end to the E1/T1 port on the WMPT.

4. Install the E1 cable.


4.1. Cabling the E1 cable.
4.2. Fix one end of the E1 cable to the
OUTSIDE port on the UELP.

Ensure that both ends of the E1 cable are


disconnected. Then, weld connectors to the
bare wires at one end of the E1 cable all at
E1
once. E1 transfer cable
cable

5. Install the FE transfer cable (FE


transmission mode).
Connect one end of the FE transfer cable
to the FE0 port near the INSIDE label on
the UFLP and the other end to the FE0
port on the WMPT.

6. Install the FE cable (FE transmission).


Connect one end of the FE cable to the
FE0 port near the OUTSIDE label on the
UFLP. Then, lead the other end out of the
cabinet along the right side of the cabinet.
FE transfer cable

FE cable

25
Installing the BBU in the APM30H(Ver.B)
c Installing the BBU Cables
7. Install the monitoring signal cable between the CMUA and the BBU.

COM_IN

MON1

26
Installing the BBU in the TMC11H(Ver.B)
a Installing the BBU
Slide the BBU to the TMC11H along Slide the SLPU to the TMC11H along
guide rails, and then tighten the four guide rails, and then tighten the four M6
M6 screws on the BBU panel. screws on the SLPU panel.
M6X16 M6X16

DCDU
BBU

2N•m 2N•m

BBU
SLPU

b Installing BBU Cables


Installation the BBU power cable.

LOAD6

27
Installing the BBU in the TMC11H(Ver.B)
b Installing BBU Cables

z The procedure for installing BBU cables (except the power cable) in the TMC11H cabinet is the same as that in the
APM30H(Ver.B). For details, see the description on pages 23 to 26.
z For details on the BBU cable connections, see BBU Cable Connections on pages 23.

Cable Connector Type Connects to


CPRI optical cable DLC The connectors labeled 2A and 2B are connected to
the optical module on the port labeled CPRI0 to
CPRI2 on the WBBP.

DLC The connectors labeled 1A and 1B are connected to


the optical module on the port labeled CPRI_W on
the RRU.

E1 cable DB26 connector OUTSIDE port on the UELP

The connector needs to Port on the transmission device


be made on site according
to the field requirements.

E1 Surge Protection DB26 connector E1/T1 port on the WMPT


Transfer Cable
DB25 connector INSIDE port on the UELP

FE cable RJ45 connector FE0 port at the OUTSIDE side on the UFLP

RJ45 connector Port on the transmission device

FE Surge Protection RJ45 connector FE0 port at the INSIDE side on the UFLP
Transfer Cable
RJ45 connector FE0 port on the WMPT

Monitoring signal cable RJ45 connector MON1 port on the BBU


between the CMUA and
the BBU RJ45 connector COM_IN port on the CMUA

BBU power cable 3V3 connector -48V port on the UPEU

OT terminal LOAD6 port on the DCDU-03C

28
Installing the BBU in the TMC11H(Ver.B, +24V)
a Installing the BBU
Slide the BBU to the TMC11H Slide the SLPU to the TMC11H (+24V)
(+24V) along guide rails, and then along guide rails, and then tighten
tighten the four M6 screws on the the four M6 screws on the SLPU
BBU panel. panel. M6X16
M6X16

2N•m
2N•m

BBU
EPS48100D

SLPU
BBU

b Installing BBU Cables


Installing the monitoring signal cable for the PSU and the in-position signal
cable for the PSU

ALM PRESENT

EXT-ALM1 EXT-ALM0

29
Installing the BBU in the TMC11H(Ver.B, +24V)
b Installing BBU Cables

z The procedure for installing BBU cables (except the power cable) in the TMC11H(+24 V) cabinet is the same as that in
the APM30H(Ver.B). For details, see the description on pages 23 to 26.
z For details on the BBU cable connections, see BBU Cable Connections on pages 23.

Cable Connector Type Connects to


CPRI optical cable DLC The connectors labeled 2A and 2B are connected to the
optical module on the port labeled CPRI0 to CPRI2 on the
WBBP.

DLC The connectors labeled 1A and 1B are connected to the


optical module on the port labeled CPRI_W on the RRU.

E1 cable DB26 Connector E1/T1 port on the WMPT

The connector needs to Port on the transmission device


be made on site
according to the field
requirements.

E1 Surge Protection DB26 connector E1/T1 port on the WMPT


Transfer Cable
DB25 connector INSIDE port on the UELP

FE cable RJ45 connector FE0 port on the WMPT

RJ45 connector Port on the transmission device

FE Surge Protection RJ45 connector FE0 port at the INSIDE side on the UFLP
Transfer Cable
RJ45 connector FE0 port on the WMPT

Monitoring signal RJ45 connector MON1 port on the BBU


cable between the
RJ45 connector COM_IN port on the CMUA
CMUA and the BBU

Monitoring signal RJ-45 EXT-ALM0 port on the UPEU


cable for the PSU
RJ-45 ALM port on the EPS48100D

In-position signal RJ-45 EXT-ALM1 port on the UPEU


cable for the PSU
Cord end terminal PRESENT port on the EPS48100D

BBU power cable 3V3 -48V port on the UPEU

OT LOAD6 port on the DCDU-03

30
Installing the BBU in the 19-Inch Cabinet
a BBU Cable Connections

i a h

f g
d

c b
a
e

Cable Installation Position

From... To...
a BBU power cable LOAD6 terminal of the DCDU PWR port on the BBU

b E1 cable External transmission device E1/T1 port on the WMPT

c FE cable (optional) External transmission device FE0 port on the WMPT

d Monitoring signal cable External monitoring device MON/ALM on the BBU

e CPRI optical cable CPRI port on the RRU CPRI port on the BBU

f PPS signal cable PPS1 port on the WGRU RGPS port on the USCU
g GPS signal cable COM1 port on the WGRU RGPS port on the USCU

h WGRU power cable LOAD7~LOAD8 on the DCDU POWER port on the back of the
WGRU

i DCDU power cable External power device NEG(-) and RTN(+) on the DCDU

j GPS clock signal cable GPS antenna system ANT port on the back of the WGRU

31
Installing the BBU in the 19-Inch Cabinet
b Space Requirements

z 25 mm on the left of the BBU for ventilation


z 25 mm on the right of the BBU for ventilation
z 70 mm in front of the BBU for cabling
z A minimum of 800 mm in front of the panel for maintenance

c Installing the BBU Case


Slide the BBU case into the cabinet. Then, tighten the four M6 screws.

32
Installing the BBU in the 19-Inch Cabinet
d Installing the WGRU (optional)

Slide the WGRU case into the cabinet, and tighten the four M6 screws.

Front

Back

WGRU

z 25 mm on the left of the WGRU for ventilation


z 25 mm on the right of the WGRU for ventilation
z 70 mm in front of the WGRU for cabling
z A minimum of 800 mm in front of the panel for maintenance

e Installing the DCDU-03C


Slide the DCDU-03C case into the cabinet, and tighten the four M6 screws.

33
Installing the BBU in the 19-Inch Cabinet
f Installing BBU Cables

1. Install the PGND cable.

Grounding bolt
on the right side
of the BBU

Grounding
bar

2. Install the power cable.

LOAD6

PWR

3. Install the signal cable.

EXT-ALM0/1 MON0/1

34
Installing the BBU in the 19-Inch Cabinet
f Installing BBU Cables
4. Install the CPRI optical cable and the E1 cable.

Connect the longer end of the optical cable to CPRI0, CPRI1, or CPRI2 on the WBBP. Then, connect the other
end to the RRU.

E1/T1

Turn the puller on the optical module outwards, insert the optical module into CPRI
ports.
Turn outwards the puller on the optical module.

Optical module

Puller

Remove the dustproof caps from the optical connectors.


Insert the optical connector at one end of the CPRI optical cable into the optical
module. Lead the CPRI optical cable out of the cabinet along the left side of the
cabinet.

CPRI optical cable

Winding pipe

35
Installing the BBU in the 19-Inch Cabinet
g Installing the WGRU Cables
1. Install the PGND cable.
Back
Grounding bar

Grounding bolt on the


right side of the WGRU

The PGND cable is


connected to the closest
grounding bar.

2. Install the GPS clock signal cable.

Back The GPS clock signal cable is


routed upwards along the
column of the cabinet.

ANT

3. Install the power cable.

Back

POWER
LOAD8

The power cable is routed from the output terminal on the DCDU to the back,
avoiding the front panels of the DCDU and WGRU.

36
Installing the BBU in the 19-Inch Cabinet
g Installing the WGRU Cables

4. Install the signal cable.

The GPS signal is transmitted over the COM1 port and the PPS signal is transmitted over the PPS1 port.

Port Pin Port Silkscre Wire


en Color

WGRU-PPS1 Pin 1- USCU-RGPS 1S+ Orange


CLK1_PPS_TXD+ and white

WGRU-PPS1 Pin 2-CLK1_PPS_TXD- USCU-RGPS 1S- Orange

WGRU-COM1 Pin 1- USCU-RGPS TX+ Orange


COM1_COMRXD+ and white

WGRU-COM1 Pin 2- USCU-RGPS TX- Orange


COM1_COMRXD-

WGRU-COM1 Pin 3- USCU-RGPS RX+ Green and


COM1_COM_TXD+ white

WGRU-COM1 Pin 6- USCU-RGPS RX- Green


COM1_COM_TXD-

37
Installing the BBU on the Wall
a BBU Cable Connections

a
e
c f

b d

Cable Connector Type Connects to

a BBU PGND cable OT terminal (6mm²-M4) Grounding bolt on the BBU

OT terminal (6mm²-M8) Nearest grounding bar

b CPRI optical cable DLC The connectors labeled 2A and 2B are connected to the optical
module on the port labeled CPRI0 to CPRI2 on the WBBP.

DLC The connectors labeled 1A and 1B are connected to the optical


module on the port labeled CPRI_W on the RRU.

c E1 cable DB26 Connector E1/T1 port on the WMPT

The connector needs to Port on the transmission device


be made on site
according to the field
requirements.

d FE cable RJ45 connector FE0 port on the WMPT

RJ45 connector Port on the transmission device

e BBU alarm cable RJ-45 MON1 port on the BBU


(optional)
RJ-45 Port on the external monitoring device

f BBU power cable 3V3 -48V port on the UPEU

OT LOAD6 port on the DCDU-03

38
Installing the BBU on the Wall
a Space Requirements

A single BBU BBU+DCDU-03C

DCDU-03C
≥20mm
BBU

mm
≥50

mm
≥50 0m m
≥ ≥10
60
0m
m
≥800mm

The DCDU is installed near the BBU.

a
b Installing the BBU Case

Install the mounting ears for wall installation.

M6X12

Mounting ear on
the BBU case

2N•m

Mounting ear
for wall installation

39
Installing the BBU on the Wall
c Installing the BBU

Place the mounting ears for wall installation against the wall, and then use
the marking pen to mark the holes of the mounting ears for wall installation.

wall

BBU

a
d Install the expansion bolts.
a
e Installing the BBU Case

Bolt M6×60
Spring washer 6
Flat washer 6
Expansion tube

Flat washer

Spring washer
M6X60

45N•m

40
Installing the BBU on the Wall
f Installing the DCDU-03C Case

1. Installing the mounting 2. Place the mounting ears for wall


ears of the DCDU-03C. installation against the wall, and then
use the marker to mark the holes of the
mounting ears for wall installation.

Wall
M6X12

2N•m

3. Install the expansion bolt. 4. Install the DCDU-03 on the wall.

Bolt M6 x 60
Nut
Spring washer 6
Flat washer 6
Ф8 Expansion tube

55mm~60mm

M6X60

45N•m
20mm

41
Installing the BBU in the OMB Cabinet
a Installing the brackets on the metal pole and mounting plate
1. Install the brackets on the metal pole.
Use a level bar to adjust the levelness of the brackets to ensure that the front and back
brackets are on the same plane.

M10x110
Flat washer
Spring washer
Bolt

255-306 kgf·cm

2. Install the mounting plate.

M10X40

255~306kgf·cm

Flat Spring
washer washer Bolt

appearance of the mounting plate

42
Installing the BBU in the OMB Cabinet
b Installing the OMB Cabinet
Slide the BBU case into the OMB
cabinet gently. Then, tighten the four
M6 screws.

Ensure the FAN is in the bottom when installing the BBU.

c Installing the BBU Cables

1. Install the PGND cable of OMB cabinet.

Grounding bar

43
Installing the BBU in the OMB Cabinet
c Installing the BBU Cables
2. Install the input power cable.

NEG(-)

RNT (+)

LOAD6
3. Install the BBU power cable.

44
Installing the BBU in the OMB Cabinet
c Installing the BBU Cables

4. Install the E1 cable (E1 transmission).


OUTSIDE
a

E1/T1
d

INSIDE

b
c

PGND

Shielding layer
(25 mm) Shielding
layer

45
Installing the BBU in the OMB Cabinet
c Installing the BBU Cables
5. Install the FE cable (FE transmission).
c

a
c
b

6. Install the CPRI optical cable.

Connect the longer end of the optical cable to CPRI0, CPRI1, or CPRI2 on the WBBP. Then, connect the other
end to the RRU.
1. Insert the optical module into the CPRI0, CPRI1, or CPRI2 port.
2. Turn outwards the puller on the optical module.

Optical module

Puller

3. Remove the dustproof caps from the


optical connectors.
4. Insert the optical connector at one end
of the CPRI optical cable into the optical
module. lead the CPRI optical cable out of
the cabinet along the left side of the
cabinet.

46
参考信息
BBU Hardware Installation Checklist
SN Item
1 The position for each equipment conforms to the engineering design and meets the space requirement. Sufficient
space is reserved for equipment maintenance.

2 The BBU and auxiliary devices are properly installed. All screws are tighten.

3 The power cable and PGND cable are not short-circuited or reversely connected. The cables are intact.

4 No joint lies in the middle of the power cable or the PGND cable.

5 The lugs at both ends of the power cable or the PGND cable are securely soldered or crimped.

6 The bare wires and lug handles at the wiring terminals are tightly coated with insulation tapes or heat-shrinkable
tubes.

7 The operating grounding and protection grounding of the NodeB and the surge protection grounding of the
building share one group of grounding conductors.

8 The connectors of signal cables are intact and securely linked. The signal cables are not damaged or broken.

9 The distance between the bundled fiber tails and the BBU panel is more than 40 mm and less than 70 mm.

10 All labels, tags, and nameplates are correct, legible, and complete. All the labels at both ends of the cables,
jumpers and feeders should match.

Powering On the BBU


Start
a
a The input voltage of the BBU
stays within a normal range.
If +24 V DC power is used,
Does the input voltage the input voltage ranges
No
of the BBU stay within a from +21.6 V DC to +29 V
normal range? DC.
Rectify the fault If -48 V DC power is used,
the input voltage ranges
Yes from -38.4 V DC to -57 V
DC.
If 220 V AC power is used,
Power on the BBU Rectify the fault the input voltage rages
from 176 V AC to 290 V
AC.
b Power off the BBU b
Status of the LEDs on the BBU:
When the WMPT or WBBP runs
Is the status of the LEDs on No
properly,
the BBU normal?
RUN LED: ON for 1s and
OFF for 1s
ALM: OFF
Yes ACT: ON
When the UPEU runs properly,
RUN LED: ON
End

47
Appendix
a Checking the DIP Switches of the BBU

Wear an ESD wrist strap or a pair of ESD gloves when performing operations related to the boards, as shown
in the figure below.

ESD strap ESD gloves

b Removing the BBU Boards

48
Appendix
c Checking the DIP Switches of the UELP

The black part indicates the position of a DIP switch.

Settings of the DIP switches on the UELP

75-ohm E1 Mode

Other Modes

d Checking the DIP Switches of the WMPT


Settings of the DIP switches on the WMPT
T1 Mode

75-ohm E1 Mode 120-ohm E1 Mode

e Reinstalling the Boards

49
Appendix
f Pin Assignment of the BBU Signal Cables
75-ohm E1 cable

Pin on the DB26 Male Connector Wire Type Coaxial SN. Label

X1.1 Tip 1 RX1+

X1.2 Ring RX1-

X1.3 Tip 3 RX2+

X1.4 Ring RX2-

X1.5 Tip 5 RX3+

X1.6 Ring RX3-

X1.7 Tip 7 RX4+

X1.8 Ring RX4-

X1.19 Tip 2 TX1+

X1.20 Ring TX1-

X1.21 Tip 4 TX2+

X1.22 Ring TX2-

X1.23 Tip 6 TX3+

X1.24 Ring TX3-

X1.25 Tip 8 TX4+

X1.26 Ring TX4-

50
Appendix
f Pin Assignment of the BBU Signal Cables
120-ohm E1 cable

Pin on the DB26 Male Connector Wire Color Wire Type Label

X1.1 Blue RX1+


Twisted pair
X1.2 White RX1-

X1.3 Orange RX2+


Twisted pair
X1.4 White RX2-

X1.5 Green RX3+


Twisted pair
X1.6 White RX3-

X1.7 Brown RX4+


Twisted pair
X1.8 White RX4-

X1.19 Grey TX1+


Twisted pair
X1.20 White TX1-

X1.21 Blue TX2+


Twisted pair
X1.22 Red TX2-

X1.23 Orange TX3+


Twisted pair
X1.24 Red TX3-

X1.25 Green TX4+


Twisted pair
X1.26 Red TX4-

51
Appendix
f Pin Assignment of the BBU Signal Cables
FE cable

Pin on the RJ45 Wire Color Wire Type Pin on the RJ45
Connector Connector

X1.2 Orange Twisted pair X2.2

X1.1 White/orange X2.1

X1.6 Green Twisted pair X2.6

X1.3 White/green X2.3

X1.4 Blue Twisted pair X2.4

X1.5 White/blue X2.5

X1.8 Brown Twisted pair X2.8

X1.7 White/brown X2.7

Monitoring signal cable between the APMI and the BBU

Pin on the RJ45 Wire Pins on the X2, Wire Type Port on the APMI
Connector Color X3, X4, and X5

X1.1 White X2 Twisted pair TX+

X1.2 Orange X3 Twisted pair TX-

X1.4 Blue X4 Twisted pair RX+

X1.5 White X5 Twisted pair RX-

52
Appendix
f Pin Assignment of the BBU Signal Cables

EMUA monitoring signal cable

Pin on the RJ45 Pin on the DB9 Wire Wire Type Port on the APMI
Connector Male Connector Color

X1.1 X2.3 White Twisted TX+


pair

X1.2 X2.7 Orange Twisted TX-


pair

X1.4 X2.2 Blue Twisted RX+


pair

X1.5 X2.6 White Twisted RX-


pair

Alarm cable

Pin on the RJ45 Pin on the RJ45 Wire Color Wire Type
Connector Connector

X1.1 X2.1 White/orange Twisted pair

X1.2 X2.2 Orange

X1.3 X2.3 White/green Twisted pair

X1.6 X2.6 Green

X1.5 X2.5 White/blue Twisted pair

X1.4 X2.4 Blue

X1.7 X2.7 White/brown Twisted pair

X1.8 X2.8 Brown

53
Change History

08 (2009-09-30)
This is the eighth commercial release.
Compared with issue 07 (2009-08-30), the configuration principles of the
BBU boards are modified.
Compared with issue 07 (2009-08-30), the installation scenarios of
APM30H(Ver.B), TMC11H(Ver.B) and TMC11H(Ver.B, +24V) are added.
07 (2009-08-30)
This is the seventh commercial release.
Compared with issue 06 (2009-06-30), the installation of WGRU is added.
06 (2009-06-30)
This is the sixth commercial release.
Compared with issue 05 (2009-01-23), the configuration principles of the
BBU boards is modified.