Table No : 1

For M-20 Grade Concrete Material Required :


Grade Of Concrete Cement (Bags/m3) Fine Agg (m3) Coarse Agg (m3)
M-20/per Cubic mtr 6.8 0.357 0.714

For M-20 Material Required If total quantity is 20 m3

Cement 136
Fine Agg(m3) 7.14
Coarse Agg(m3) 14.28

Note : All Quantity are taken in Cubic meter, It will be change in Cubic feet by Multiply of 35.3147

Table No : 2
Cement Bags Calculations In Concreting

Formula : A = 1.52*1 m3/Sum of Ratio


Again A*28.8= Consumpations
For eg. :
1 m3 concrete for 1:1.5:3 (M-20 Grade)
1+1.5+3=5.5
A= 1.52*1/5.5=0.28
Now 0.28*28.8 = 7.59 Bags/m3

Table No : 3
How to Calculate Quantity of Cement Mortar in Plaster?
like if ratio is give 1:4, 1:6 etc.
e.g.
say, my area is 20 m2 and avg. thickness is (15mm = 0.015 m)
so....
20 x 0.015 = 0.3 m3
ratio = 1:4 so the ratio factor is 5
0.3/5 = 0.06
now mul. by the ratio
so 0.06 x 1 = 0.06 m3 for cement (one cement bag contain 0.035 m3 cement)
0.06 x 4 = 0.24 m3 for sand
Grade Of Concrete Cement (Bags/m3)
M10 3.4
M15 6.2
M20 6.8
M25 7.5
M30 8.5
M35 9
M40 10

Density of concrete 2400 kg/per cubicmeter


Note: For 1m3 wet concrete = 1.52 m3 dry concrete approximate
SP.Wt of concrete= 1440 kg/m3 (or) 1.44 t/m3
1 bag of cement = 50 Kg (0.035 m3)
1440/50=28.8