NOTE:-

MINIMUM CEMENT CONSUMPTION SHOULD BE AS PER THE CHART PROVIDED


FOR THE TENDER NAMED " CIVIL WORKS AT LONI TERMINAL" FOR ALL THE
JOBS INCLUDING CIVIL BUILDING STRUCTURES, RCC DRIVE WAY, DYKEWALL,
FIRE BREAK WALL ETC COMPLETE.

CEMENT CONSUMPTION FOR CONCRETE GRADES


NOTE : 30 Bags / CuM
SR.NO. DESCRIPTION NO. OF CEMENT BAGS

1 M10 ( 1:3:6 ) 4.4

2 M15 (1:2:4 ) 4.8

3 M20 (1:1.5:3 ) 5.5

4 M25 (1:1:2 ) 7.5

5 PCC M10 (1:3:6 ) 3


& (1:4:8 ) 2.3

CEMENT CONSUMPTION FOR CEMENT MORTAR


NOTE : 30 Bags / CuM
SR.NO. DESCRIPTION NO. OF CEMENT BAGS

1 (1:4) 6

2 (1:5) 5

3 (1:6) 4.3

CEMENT CONSUMPTION FOR PLASTER


NOTE : 30 Bags / CuM
SR.NO. DESCRIPTION NO. OF CEMENT BAGS

1 20 MM THICK (1:4 ) 18

2 12 MM THICK (1:4) 10.8

CEMENT CONSUMPTION FOR BRICK WORK / CuM


NOTE : 30 Bags / CuM
SR.NO. DESCRIPTION NO. OF CEMENT BAGS

1 ( 1:3 ) 2.5

2 (1:4 ) 2

3 (1:5 ) 1.65

4 (1:6 ) 1.4

ACTUAL CEMENT CONTENT REQUIRED MAY VARY AS PER APPROVED MIX


DESIGN BUT MINIMUM CONSUMPTION SHALL BE AS PER THE CHART.