The operation of the circuit.

The supply that comes from TNB (Tenaga Nasional Berhad) will flow through Cut Out Neutral Link and
then go through the Kilowatt-Hour Meter. Until this part, TNB will be responsible for any fault that
occur here. After that the supply will flow through the Switch Fuse 63A (63A). The switch fuse will
protect the electrical appliances if the overload happen reach the 63A. Next the supply will flow
through RCCB 63A(300mA). The RCCB will disconnect the circuit if the residual current pass the limit
of 300mA. After that the supply will go through each MCB for appropriate appliances. In this workshop
session the MCB 6A is used to protect the cable and conductor against the overload and short circuit
for the fluorescent lamp circuit. The load is connected to the neutral to complete the circuit for current
to flow.