SCHEDULE FINISHING CANOPY

PT. SAMSUNG PRINT & PACK INDONESIA


2015
TIME SCHEDULE, 20 WORK DAYS

No Uraian pekerjaan 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Mar-15
TGL 18 19 20 21 22 23 24 25 26
I Main Canopy
1 Install Frame Cladding
2 Close Cladding side Canopy
3 install & close Cladding Sopi sopi Front &Back

II Motor Parking Canopy


1 Install Frame for Roofing Small canopy
2 Install Install Roofing small canopy
3 Install Frame for Cladding
4 Install Cladding

Pelaksana Pekerjaan

TTD

RUDI FIYATNO