1 EXECUTIVE SUMMARY 1
2 DESCRIPTION OF SERVICE 1
3 TECHNOLOGY CONSIDERATIONS 2
4 SERVICE MARKETPLACE 2
5 MARKETING STRATEGY 2
6 ORGANIZATION AND STAFFING 3
7 PROJECT TIME TABLE 5
8 FINANCIAL PROJECTIONS 7
9 FINDINGS AND RECOMMENDATIONS 11
13
EXECUTIVE SUMMARY
Water is essential for every living thing on earth. However, the increasing number
of population demands more water sources for their daily activities that caused water
scarcity seriously felt especially by those living in mountainous places. Barangay Tabon,
a barangay of Dalaguete is one of the 250 communities of the entire country that has no
access to enough water supply due to its upland location. Nevertheless, with the
presence of fog the proponents were inspired to seek a solution to the problem through
the installation of a Fog Harvesting Facility.
The goal of the proposed project is to determine the feasibility of installing a fog
harvesting facility at Barangay Tabon, Dalaguete, Cebu. The business will run as a
cooperative named Cebu Fog Water Cooperative whose members are the households
of the barangay who are also the initial target market for this project. Five Board of
Directors together with the mandated committee would organize it. The initial funds
needed to start its operation will be ₱ 3,462,011.00. The land needed to construct the
fog harvesting facility and the small office will be the contribution by some members of
the cooperative. The service will be available for eight hours daily; however, the fog
harvesting facility will continue to collect water 24 hours daily. The water collected will
initially be stored in the water tanks where the galvanized iron water pipes are connected
to the automatic water machine located in every sitio. The automatic water machine will
dispense the water with the use of its timer equivalent to one gallon at ₱ 1.00. This price
is expected to remain constant for the first five years or as determined by the assembly.
Cebu Fog Water Cooperative (CFWC) is expected to earn a substantial income
averaging 12.4% of the investment in five years and its payback period discounted at
12% of 3.8 years. Water, being one of the necessities, yet a scarce resource plays a
vital role in the economic growth and development particularly to the residents in
mountain barangays to improve their way of living. In the light of the findings, the
implementation of this project will also benefit its members’ to develop the habit to save,
to earn interest on its share capital and patronage refund and to be self-sufficient in their
pursuit of economic prosperity. Its expansion would further benefit not just the residents
of Barangay Tabon, but most probably other mountainous barangays in Cebu and even
other provinces.
DESCRIPTION OF SERVICE
The said facility is entirely dependent on the fog harvesting technology that will
be constructed at Barangay Tabon, Dalaguete, Cebu having an altitude of 695 meters
above sea level. Fog harvesting involves the use of simple, flat, rectangular nets of
polypropylene Raschel mesh with an area of 40 square meter supported by a post at
both ends and installed perpendicular to the direction of the wind. The proponents based
the facility on the fact that one can accumulate water from fog particles. Fog is a mass of
water vapor condensed into water droplets as it passes through the mesh. It will then
form into water droplets that will drip down into the gutter through the PVC tubes leading
to the cistern for storage. It could potentially supply water for multiple uses in
mountainous areas at altitudes of approximately 400 meters to 1200 meters where fogs
are frequent. The proposed project does not only focus on implementing a water facility,
but also focused on distributing of water in line with the primary goal of making water
42
ORGANIZATIONAL CHART
GENERAL ASSEMBLY
Treasurer Secretary
Manager
Cashier Caretakers
57
Pre-feasib
Sourcing of Funds
Registration of Cooperative
MONTH 1 2 3 4
ACTIVITY
WEEK 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Purchase Materials
Site Preparations
Excavate Foundation for Post
Build Components (post drains,cables, etc.)
Raise Post
Install Mesh
Tension Mesh
Install and connect pipe networks to collector
97
FINANCIAL PROJECTIONS
The proposed water facility requires an estimated project cost of ₱ 4,407,011.00. It
consists of pre-operating expenses amounting to ₱ 50,966.00; property, plant, and equipment
amounting to ₱ 4,264,293; and working capital of ₱ 91, 752.00.The financial projection of the
proposed study is shown in the table below. The figures shown are account for the projected
financial statements and financial analysis of the study for the next five years.
Revenue Projections
2,760,000.00
2,740,000.00
2,720,000.00
2,700,000.00
2,680,000.00
2,660,000.00
2,640,000.00
2019 2020 2021 2022 2023
Revenue Projection
Expense Projections
1,900,000.00
1,890,000.00
1,880,000.00
1,870,000.00
1,860,000.00
1,850,000.00
1,840,000.00
1,830,000.00
1,820,000.00
2019 2020 2021 2022 2023
Expenses Projection
10
8
Net Surplus
Total Assets
9,000,000.00
8,000,000.00
7,000,000.00
6,000,000.00
5,000,000.00
4,000,000.00
3,000,000.00
2,000,000.00
1,000,000.00
-
2019 2020 2021 2022 2023
Total Assets
11
9
Total Liabilities
320,000.00
315,000.00
310,000.00
305,000.00
300,000.00
295,000.00
2019 2020 2021 2022 2023
Total Liabilities
FINANCIAL ANALYSIS
Net Profit Rate
Net Profit Ratio measures the capability of an entity to earn a profit in relation to its
sales. It is the percentage of net income to the net sales of the entity which indicates the share
of the entity of its net sales.
32%
31%
30%
29%
2019 2020 2021 2022 2023
Revenue Projection
The net profit or net surplus indicates an average of 31 percent of the revenue.
However, the net surplus will be deducted by the statutory funds required, after which the
remaining amount will be distributed to the members, a minimum of 30 percent as a patronage
refund and the balance as an interest on share capital.
Return on Investment
Return on investment measures the capability of an entity to earn a profit in relation to
its assets. The relative value of net income over the average assets indicates the
management's capability to use its capital effectively.
Return on Investments
16%
14%
12%
10%
8%
6%
4%
2%
0%
2019 2020 2021 2022 2023
Return on Investments
13
11
The decreasing return on investment indicates that the contributions are increasing
every year with a slight increase in income. The decreasing results indicate that the entity is not
able to utilize the annual increase in assets to gain more profit. Thus, the entity own idle assets
that must be invested; thereby, it must consider expansion to solve this matter and gain more
profit while helping people at the same time.
Discounted Payback Period
The payback period is the period for the net cash inflows from operations to compensate
with the initial investment financed by both the creditors and investors. It is a simple way to
evaluate the risk associated with a proposed project.
Based on the present value of 1 at 12% of net cash inflows, the entity can compensate
its capitalization from members at approximately 3 years and 10 months. This is a good
indicator and a solid proof that the proposed project is feasible and profitable since it can pay
back the assets it used for less than five years. This means that after 3.80 years, the entity is
now ready to expand its geographical scope.
FINDINGS AND RECOMMENDATION
Based on the data presented in the previous chapters, the summary of findings are in
this section. This section contains brief descriptions of every aspect tackled.
Technical
It involves the use of simple, flat, rectangular nets of Polypropylene Raschel
mesh supported by a post at both ends and installed perpendicular to the
direction of the wind
Since part of the project is the construction of the fog collectors, the tools, and
materials needed are the following: Raschel mesh, metal poles, ropes, PVC
pipes, PVC tubes, electric drill, welding machine, ladder, shovel, and digging bar.
12
14
The service flow involves the harvesting of the fogs, storing of the water, and its
distribution. The computation of service capacity considers the factors such as
the quantity discharge of the automatic machine that will be installed in every
sitio and the number of hours operation of the service capacity.
Marketing
The initial target market of the proposed project is the households at Barangay
Tabon, Dalaguete Cebu
Since there is a high demand for water and no direct competitors in the said
barangay, the entity will incur lesser costs in the advertising since the consumers
are themselves members of the cooperative. Thereby, their patronage is
expected.
The water distribution will be done through the automatic water machine installed
per sitio for an easy access to every household. Furthermore, the pricing of the
water is relatively very cheap compared to the cost of obtaining water from the
neighboring barangay for it is exclusive of its transportation cost.
Management
The employees’ compensation is on a per day bases. They would work for eight
hours a day on weekdays except for caretakers who will also work during
weekends, but on a routinary basis.
Legal and Taxation
The entity shall secure Barangay Clearance and Mayor's Business Permit
It will be exempted from national, city, provincial, municipal, and local taxes of
whatever name and nature as provided by the RA 9520 Sec. 60-61.
Financing
Financial
The net surplus of the proposed project for the five years of operations is ₱
859,321.00, ₱ 830,124.92, ₱ 822,489.49, ₱ 833,227.55, and ₱ 825,135.63,
respectively.
The return on investment for the five years are 0.15, 0.14, 0.12, 0.11, and 0.10,
respectively.
The payback period of the proposed project is 3.8 years in which the entity can
recover the capital invested
Will not only benefit the prospective implementors, but also the agricultural
industries, related industries, competitors and the government.
Three strengths of the proposed project such as no direct competitor at the target
market, not requiring large cost of advertisement, and the business is easy to
manage
2. It is highly recommended that the entity will expand to other upland barangays where
the occurrences of fogs are frequent such as Barangay Mantalongon in Dalaguete,
Barangay Busay in Cebu City and Barangay Magsaysay in Balamban. This can
contribute to having more money for further innovation of fog harvesting facility and
could help such barangays in providing an alternative source of water.
3. Due to time constraints, unavailability of materials and funding needed, the proponents
could not resolve some technical issues such as finding an alternative mesh that is
locally available or the occurrence of climate change. Therefore, there is a need for
further research and development for the perfection of the technical aspect of the
proposed project.
4. Since the proposed project gears towards translating early-stage technologies into
market-ready products, the implementers can avail the Department of Science and
Technology (DOST) Startup Research grant. The entity can use the fund to overcome
research and development roadblocks, strengthen intellectual property, the
establishment of initial market traction and refinement of the business model.