ID Task Name Duration Start Finish Predecessors Feb 25, '18 Mar 4, '18 Mar 11, '18

T F S S M T W T F S S M T W T F S S M T W
1 EARTHWORK EXCAVATION 5 days Fri 2/23/18 Thu 3/1/18
2 PCC 9 days Fri 3/2/18 Wed 3/14/18 1
3 FOUNDATION 12 days Thu 3/15/18 Fri 3/30/18 2
4 BASEMENT CONSTRUCTION 6 days Mon 4/2/18 Mon 4/9/18 3
5 BRICK WORK 15 days Tue 4/10/18 Mon 4/30/18 4
6 LINTEL 10 days Tue 5/1/18 Mon 5/14/18 5
7 ROOFING 10 days Tue 5/15/18 Mon 5/28/18 6
8 PARAPET 13 days Tue 5/29/18 Thu 6/14/18 7
9 PLASTRING 4 days Fri 6/15/18 Wed 6/20/18 8
10 FITTINGS 9 days Thu 6/21/18 Tue 7/3/18 9
11 PAINTING AND OTHERS 10 days Mon 7/9/18 Fri 7/20/18

Task Milestone External Tasks


Project: Project1
Split Summary External Milestone
Date: Sun 3/11/18
Progress Project Summary Deadline

Page 1
Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18 Apr 22, '18
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Milestone External Tasks


Project: Project1
Split Summary External Milestone
Date: Sun 3/11/18
Progress Project Summary Deadline

Page 2
Apr 29, '18 May 6, '18 May 13, '18 May 20, '18 May 27, '18 Jun 3, '18
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Milestone External Tasks


Project: Project1
Split Summary External Milestone
Date: Sun 3/11/18
Progress Project Summary Deadline

Page 3
Jun 10, '18 Jun 17, '18 Jun 24, '18 Jul 1, '18 Jul 8, '18 Jul 15, '18 Jul
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Milestone External Tasks


Project: Project1
Split Summary External Milestone
Date: Sun 3/11/18
Progress Project Summary Deadline

Page 4