Professional Documents
Culture Documents
A 12a Mekanikalfin
A 12a Mekanikalfin
A. MATERIAL
1. Gate leaf
- Plate SS 400 2765 27,033 74,746,951
- Plate SUS 304 164 25,033 4,105,454
- H Beams SS 400 3100 27,033 83,803,091
- Canal SS 400 2202 27,033 59,527,228
- Spring SUP 4 -
- Round bar S 45 C -
- Rubber seal 15 M NEOPRENE 36 175,000 6,300,000
- Bolt & Nuts SUS 304 16 25,033 400,532
2. Guide frame -
- Plate SS 400 1001 27,033 27,060,288
- Plate SUS 304 566 25,033 14,168,822
- H Beams SS 400 1380 38,300 52,854,000
- Canal SS 400 792 38,300 30,333,600
- Round bar SS 400 120 38,300 4,596,000
- Bolt & Nuts SUS 304 5 25,033 125,166
3. Guide frame
- Wire rope STEEL GALV 15 75,000 1,125,000
- Sackle STD Ø 45 30 9,000 360,000
- O Ring SS 400 10 12,500 125,000
4. Jig and Fixture 250 12,500 3,125,000
TOTAL 399,031,746
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 3 x 30 x3 270 130,000 35,100,000
- Fitter 1 x 4 x 30 x 2 240 90,000 21,600,000
- Welder 2 x 3 x 30 x 4 720 90,000 64,800,000
- Gas Cutting 2 x 3 x 30 x 2 360 90,000 32,400,000
- Helper 2 x 4 x 30 x 3 720 90,000 64,800,000
- Sandblasting & Painting 235 105,000 24,675,000
-
2. Mechanical -
- Foreman 1 x 1 x 30 x 5 150 130,000 19,500,000
- Fitter (Bor & Shaper) 2 x 1 x 30 x 3 180 90,000 16,200,000
- Helper 3 x 1 x 30 x 5 450 90,000 40,500,000
- Equipment and Tools Ls 11,000,000
C. CONSUMABLE Ls 13,500,000
E. ERECTION COST
- Foreman 1 x 1 x 30 x 3 90 130,000 11,700,000
12a-1-8
Item Description Material Unit (kg) Harga Satuan Jumlah
No. Rp. Rp.
TOTAL 587,764,310
TOTAL (A + B + C + D + E) 986,796,056
12a-1-9
Item Description Material Unit (kg) Harga Satuan Jumlah
No. Rp. Rp.
12a-1-10
Analisa Harga Satuan Pekerjaan : Hydromekanikal
TOTAL 3,457,092,301
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 7.0 x 30 x 3 630 130,000 81,900,000
- Fitter 2 x 7.0 x 30 x 4 1,680 90,000 151,200,000
- Welder 2 x 4 x 30 x 4 960 90,000 86,400,000
- Gas Cutting 2 x 4 x 30 x 4 480 90,000 43,200,000
- Helper 4 x 7.0 x 30 x 4 1,680 50,000 84,000,000
- Sandblasting & Painting 120 76,500 9,180,000
-
2. Mechanical -
- Foreman 1 x 2.0 x 30 x 1 60 130,000 7,800,000
- Fitter (Bor & Milling) 2 x 3.0 x 30 x 2 360 90,000 32,400,000
- Helper 4 x 3.0 x 30 x2 720 50,000 36,000,000
- Equipment and Tools Ls 13,000,000
C. CONSUMABLE Ls 29,000,000
12a-2-11
Item Description Material Unit (kg) Unit Price Amount
No. Rp. Rp.
E. ERECTION COST
- Foreman 1 x 2.0 x 30 x 10 600 130,000 78,000,000
- Fitter Mechanical 2 x 2.5 x 30 x 10 1,500 90,000 135,000,000
- Fitter electrical 1 x 2.0 x 30 x 10 600 90,000 54,000,000
- Welder 1 x 2.0 x 30 x 10 600 90,000 54,000,000
- Helper 8 x 2.5 x 30 x 10 6,000 50,000 300,000,000
- Equipm, Tools and Consumable Ls 41,100,000
TOTAL 1,471,385,850
TOTAL (A + B + C + D + E) 4,928,478,151
12a-2-12
Item Description Material Unit (kg) Unit Price Amount
No. Rp. Rp.
12a-2-13
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. Trash Rack Bar and Support Beam
- Plate SS 400 4156 25,033 104,038,209
- Steel pipe SGP 2070 15,500 32,085,000
- H Beams SS 400 8050 25,033 201,517,704
- Round bar SUS 304 6880 25,033 172,228,796
- Round bar SS 400 90 35,000 3,150,000
- Nuts SUS 304 211 25,033 5,282,017
TOTAL 570,131,898
12a-3-14
Analisa Harga Satuan Pekerjaan : Hydromekanikal
SERVICE GATE
A. MATERIAL
1. Gate leaf
- Plate SS 400 2758 25,033 69,041,718
- Plate SUS 304 1155 25,033 28,913,410
- H Beams SS 400 -
- Canal SS 400 -
- Round bar SUS 304 -
- Bearing Plate BC 3 96 45,000 4,320,000
- Rubber seal 11 M Rubber -
- Bolt & Nuts SUS 304 12 25,033 300,399
2. Frame Bonnet -
- Plate SS 400 15677 25,033 392,446,342
- Plate SUS 304 230 25,033 5,757,649
- H Beams SS 400 -
- Canal SS 400 -
- Round bar SS 400 -
- Bolt & Nuts HTB 180 25,033 4,505,986
- Plate BC 3 339 45,000 15,255,000
3. Actuator Hoist -
- ActuatorHoist Complete 638,000,000
and Accessories
4. Jig and Fixture 800 12,500 10,000,000
TOTAL 1,285,394,553
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 7.0 x 30 x 1 2,100 46,490 97,629,000
- Fitter 2 x 7.0 x 30 x 1 4,200 42,270 177,534,000
- Welder 2 x 4 x 30 x 10 2,400 65,360 156,864,000
- Gas Cutting 2 x 3.5 x 30 x 1 2,100 42,250 88,725,000
- Helper 5 x 7.0 x 30 x 1 10,500 11,500 120,750,000
- Sandblasting & Painting 56 76,500 4,284,000
-
2. Mechanical -
- Foreman 1 x 2 x 30 x 10 600 46,490 27,894,000
- Fitter (Bor & Shaper) 2 x 2 x 30 x 10 1,200 40,260 48,312,000
- Helper 4 x 2 x 30 x 10 2,400 11,500 27,600,000
- Equipment and Tools Ls 10,500,000
C. CONSUMABLE Ls 10,275,000
12a-4-15
Item Uraian Material Sat (kg) Harga Satuan Jumlah Harga
No. Rp. Rp.
E. ERECTION COST
- Foreman 1 x 1.5 x30 x 2 450 46,490 20,920,500
- Fitter Mechanical 2 x 1.5 x 30 x2 900 42,270 38,043,000
- Fitter electrical 1 x 30 x 2 300 42,270 12,681,000
- Welder 1 x 30 x 2 300 65,360 19,608,000
- Helper 6 x 1.5 x 30 x 2 2,700 12,500 33,750,000
- Equipment and Tools Ls 22,250,000
TOTAL 1,034,681,450
TOTAL (A + B + C + D + E) 2,320,076,003
12a-4-16
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. Gate leaf
- Plate SUS 304 1,238 75,000 92,850,000
- Plate < 25 SS 400 2,497 45,000 112,365,000
- Plate < 65 SS 400 -
- Steel pipe STPG 260 45,000 11,700,000
- Air valve STD 85 72,500,000
- Round bar SUS 304 -
- Bearing Plate BC 3 96 45,000 4,320,000
- Gate valve STD 62 29,500,000
- Bolt & Nuts HTB 6 75,000 450,000
2. Guide frame
- Plate SUS 304 90 75,000 6,750,000
- Plate < 25 SS 400 7,973 45,000 358,785,000
- Plate < 65 SS 400 5,075 45,000 228,375,000
- H Beams SS 400 -
- Canal SS 400 -
- Round bar SUS 304 -
- Bearing Plate BC 3 339 45,000 15,255,000
- Rubber seal Rubber -
- Bolt & Nuts HTB 276 75,000 20,700,000
3. Actuator hoist complete 1 set 468,000,000.00
with acessories
indicator and access.
4. Jig and Fixture 500 12,500 6,250,000
TOTAL 1,641,970,000
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 7.0 x 30 x 1 2,100 46,490 97,629,000
- Fitter 2 x 7.0 x 30 x 1 4,200 42,270 177,534,000
- Welder 2 x 4 x 30 x 10 2,400 65,360 156,864,000
- Gas Cutting 2 x 3.5 x 30 x 1 2,100 42,250 88,725,000
- Helper 5 x 7.0 x 30 x 1 10,500 11,500 120,750,000
- Sandblasting & Painting 56 76,500 4,284,000
-
2. Mechanical -
- Foreman 1 x 1 x 30 x 10 600 46,490 27,894,000
- Fitter (Bor & Shaper) 2 x 1 x 30 x 10 1,200 40,260 48,312,000
- Helper 3 x 2 x 30 x 10 1,800 11,500 20,700,000
- Equipment and Tools Ls 10,450,000
C. CONSUMABLE Ls 10,650,000
12a-5-17
Item Description Material Unit (kg) Harga Satuan Jumlah Harga
No. Rp. Rp.
E. ERECTION COST
- Foreman 1 x 1.5 x30 x 10 450 46,490 20,920,500
- Fitter Mechanical 2 x 1.5 x 30 x10 900 42,270 38,043,000
- Fitter electrical 1 x 30 x 10 300 42,270 12,681,000
- Welder 1 x 30 x 10 300 65,360 19,608,000
- Helper 6 x 1.5 x 30 x 1 2,700 12,500 33,750,000
- Equipment and Tools Ls 22,250,000
TOTAL 1,071,175,550
TOTAL (A + B + C + D + E) 2,713,145,550
12a-5-18
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. Sheel pipe and flange
- Plate SM 490 305,902.73 35,000 10,706,595,375
- Plate SS 400 6160 25,033 154,204,852
- H Beams SS 400 -
- Canal SS 400 -
- Round bar SUS 304 -
- Bearing Plate BC 3 -
- Rubber seal Rubber -
- Bolt & Nuts HTB 168 25,033 4,205,587
2. Jig and Fixture 550 12,500 6,875,000
TOTAL 12,502,662,936
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 2.5 x 30 x 1 750 46,490 34,867,500
- Fitter 2 x 3 x 30 x 10 1,800 42,270 76,086,000
- Welder 1 x 3 x 30 x 10 900 43,400 39,060,000
- Gas Cutting 1 x 3 x 30 x 10 900 42,250 38,025,000
- Helper 5 x 3 x 30 x 10 4,500 11,500 51,750,000
- Sandblasting & Painting 160 76,500 12,240,000
-
2. Mechanical -
- Foreman 1 x 1 x 30 x 10 300 46,490 13,947,000
- Fitter (Bor & Milling) 2 x 1 x 30 x 10 600 40,260 24,156,000
- Helper 2 x 2 x 30 x 10 1,200 11,500 13,800,000
- Equipment and Tools Ls 8,750,000
C. CONSUMABLE Ls 13,475,000
F. ERECTION COST
- Foreman 1 x 1.5 x30 x 10 450 46,490 20,920,500
- Fitter Mechanical 2 x 1.5 x 30 x10 900 42,270 38,043,000
- Fitter electrical 1 x 30 x 10 300 42,270 12,681,000
- Welder 1 x 30 x 10 300 65,360 19,608,000
- Helper 6 x 1.5 x 30 x 10 2,700 12,500 33,750,000
- Equipment and Tools Ls 15,350,000
12a-6-19
Item Description Material Unit (kg) Harga Satuan Jumlah Biaya
No. Rp. Rp.
TOTAL 988,950,359
TOTAL ( A + B + C + D + E) 13,491,613,295
12a-6-20
Item Description Material Unit (kg) Harga Satuan Jumlah Biaya
No. Rp. Rp.
12a-6-21
Ket
12a-6-22
Ket
28,736,131
12a-6-23
Ket
12a-6-24
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. Sheel pipe and flange
- Plate SM 490 1,800.00 35,000 63,000,000
- Plate SS 400 3,748.00 25,033 93,824,641
- H Beams SS 400 -
- Canal SS 400 -
- Round bar SUS 304 -
- Bearing Plate BC 3 -
- Rubber seal Rubber -
- Bolt & Nuts HTB -
2. Jig and Fixture 550 12,500 6,875,000
TOTAL 188,254,587
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 2.5 1 46,490 46,490
- Fitter 2 x 3 x 30 2 42,270 84,540
- Welder 1 x 3 x 30 2 43,400 86,800
- Gas Cutting 1 x 3 x 30 2 42,250 84,500
- Helper 5 x 3 x 30 4 11,500 46,000
- Sandblasting & Painting 1 76,500 76,500
-
2. Mechanical -
- Foreman 1 x 1 x 30 2 46,490 92,980
- Fitter (Bor & Milling) 2 x 1 x 30 4 40,260 161,040
- Helper 2 x 2 x 30 4 11,500 46,000
- Equipment and Tools Ls 8,750,000
C. CONSUMABLE Ls 1,375,000
F. ERECTION COST
- Foreman 1 46,490 46,490
- Fitter Mechanical 2 42,270 84,540
- Fitter electrical 2 42,270 84,540
- Welder 2 65,360 130,720
- Helper 6 12,500 75,000
- Equipment and Tools Ls 1,550,000
TOTAL 23,067,666
TOTAL ( A + B + C + D + E) 211,322,253
12a-6-25
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. Sheel pipe and flange
- Plate SM 490 -
- Plate SS 400 4,275.00 55,000 235,125,000
- H Beams SS 400 -
- Canal SS 400 -
- Round bar SUS 304 -
- Bearing Plate BC 3 -
- Rubber seal Rubber -
- Bolt & Nuts HTB -
2. Jig and Fixture 550 25,000 13,750,000
TOTAL 286,206,250
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 2.5 1 150,000 150,000
- Fitter 2 x 3 x 30 2 110,000 220,000
- Welder 1 x 3 x 30 2 110,000 220,000
- Gas Cutting 1 x 3 x 30 2 110,000 220,000
- Helper 5 x 3 x 30 4 75,000 300,000
- Sandblasting & Painting 1 76,500 76,500
-
2. Mechanical -
- Foreman 1 x 1 x 30 2 150,000 300,000
- Fitter (Bor & Milling) 2 x 1 x 30 4 110,000 440,000
- Helper 2 x 2 x 30 4 110,000 440,000
- Equipment and Tools Ls 8,750,000
C. CONSUMABLE Ls 1,375,000
F. ERECTION COST
- Foreman 1 150,000 150,000
- Fitter Mechanical 2 110,000 220,000
- Fitter electrical 2 110,000 220,000
- Welder 2 110,000 220,000
- Helper 6 75,000 450,000
- Equipment and Tools Ls 1,550,000
TOTAL 26,565,288
TOTAL ( A + B + C + D + E) 312,771,538
12a-6-26
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. Gate leaf
- Plate SS 400 1209 35,000 42,315,000
- Plate SUS 304 486 35,000 17,010,000
- H Beams SS 400 213 35,000 7,455,000
- Canal SS 400 172 35,000 6,020,000
- Round bar SUS 304 344 35,000 12,040,000
- Round bar S 45 C 234 35,000 8,190,000
- Rubber seal 11 M Rubber 22 175,000 3,850,000
- Bolt & Nuts SUS 304 9 35,000 315,000
2. Guide frame -
- Plate SS 400 100 35,000 3,500,000
- Plate SUS 304 610 35,000 21,350,000
- H Beams SS 400 519 35,000 18,165,000
- Canal SS 400 572 35,000 20,020,000
- Round bar SS 400 -
- Bolt & Nuts STD -
3. Hoist Equipment -
- Plate SS 400 308.6 35,000 10,801,000
- Round bar SUS 304 222 35,000 7,770,000
- Steel pipe SS 400 -
- Canal SS 400 174 35,000 6,090,000
- Round bar SS 400 -
- Bolt & Nuts SUS 304 -
- Bushing BC 3 -
-
- Actuator manual hoist 51,000,000
complete with accessories
TOTAL 271,274,650
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 45 x 5 225 130,000 29,250,000
- Fitter 2 x 2 x 30 x 5 690 90,000 62,100,000
- Welder 1 x 21 x 5 105 90,000 9,450,000
- Gas Cutting 1 x 20 x 5 100 90,000 9,000,000
- Helper 4 x 60 x 5 1,200 90,000 108,000,000
- Sandblasting & Painting 27 76,500 2,065,500
-
2. Mechanical -
- Foreman 1 x 15 x 3 45 130,000 5,850,000
- Fitter (Bor & Shaper) 2 x 20 x 3 120 90,000 10,800,000
- Helper 4 x 20 x 3 240 90,000 21,600,000
- Equipment and Tools Ls 5,750,000
12a-8-27
Item Uraian Material Unit (kg) Harga satuan Jumlah Harga
No. Rp. Rp.
C. CONSUMABLE Ls 5,000,000
E. ERECTION COST
- Foreman 1 x 18 x 3 54 130,000 7,020,000
- Fitter Mechanical 2 x 21 x 3 126 90,000 11,340,000
- Fitter electrical 1 x 10 x 3 30 90,000 2,700,000
- Welder 1 x 10 x 3 30 90,000 2,700,000
- Helper 3 x 30 x 3 270 90,000 24,300,000
- Equipment and Tools Ls 13,000,000
TOTAL 386,284,184
TOTAL (A + B + C + D + E) 657,558,834
12a-8-28
Item Uraian Material Unit (kg) Harga satuan Jumlah Harga
No. Rp. Rp.
12a-8-29
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. MONORAIL HOIST
- Plate SUS 304
- Plate < 25 SS 400 1,139 25,033
- Plate < 65 SS 400
- H Beams SS 400 2,248 25,033
- Canal SS 400 180 25,033
- Wheel S 45 C 164 47,500
- Round bar SUS 304 5 25,033
- Bearing Plate BC 3 2 45,000
- Rubber seal Rubber
- Bolt & Nuts HTB
2. Monorail hoist complete 1 set
dengan troley
SUB TOTAL
TOTAL
A. MATERIAL
1. MONORAIL HOIST
- Plate SUS 304
- Plate < 25 SS 400 830 16,500
- Plate < 65 SS 400 263 22,500
- H Beams SS 400 1,914 17,500
- Canal SS 400 180 17,500
- Wheel S 45 C 156 47,500
- Round bar SUS 304 5 53,500
- Bearing Plate BC 3 2 45,000
- Rubber seal Rubber
- Bolt & Nuts HTB
SUB TOTAL
TOTAL
12a-9-30
Item Description Material Unit (kg) Unit Price
No. Rp. Yen
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 1 x 30 x 10 300 46,490
- Fitter 2 x 1 x 30 x 10 600 42,270
- Welder 1 x 10 x 10 100 65,360
- Gas Cutting 1 x 70 x 10 70 42,250
- Helper 4 x 1 x 30 x 10 1,200 11,500
- Sandblasting & Painting 11 76,500
2. Mechanical
- Foreman 1 x 15 x 10 150 46,490
- Fitter (Bor & Milling) 1 x 15 x 10 150 40,260
- Helper 2 x 15 x 10 300 11,500
- Equipment and Tools Ls
12a-9-31
Item Description Material Unit (kg) Unit Price
No. Rp. Yen
C. CONSUMABLE Ls
E. ERECTION COST
- Foreman 1 x 10 x 10 100 46,490
- Fitter Mechanical 2 x 10 x10 200 42,270
- Fitter electrical 1 x 10 x 10 100 42,270
- Welder 1 x 10 x 10 100 65,360
- Helper 5 x 10 x 10 500 12,500
- Equipment and Tools Ls
SUB TOTAL
TOTAL
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 30 x 10 300 46,490
- Fitter 2 x 30 x 10 600 42,270
- Welder 1 x 10 x 10 100 65,360
- Gas Cutting 1 x 70 x 10 70 42,250
- Helper 4 x 30 x 10 1,200 11,500
- Sandblasting & Painting 11 76,500
2. Mechanical
- Foreman 1 x 15 x 10 150 46,490
- Fitter (Bor & Milling) 1 x 15 x 10 150 40,260
- Helper 2 x 15 x 10 300 11,500
- Equipment and Tools Ls
C. CONSUMABLE Ls
E. ERECTION COST
- Foreman 1 x 10 x 10 100 46,490
- Fitter Mechanical 2 x 10 x 10 200 42,270
- Fitter electrical 1 x 10 x 10 100 42,270
- Welder 1 x 10 x 10 100 65,360
- Helper 5 x 10 x 10 500 12,500
- Equipment and Tools Ls
SUB TOTAL
TOTAL
12a-9-32
Item Description Material Unit (kg) Unit Price
No. Rp. Yen
TOTAL (A + B + C + D + E)
A-12a-09-2 + A-12a-09-2
C. CONSUMABLE
1. Oxygen 6 85,000
2. Acetelyn 3 220,000
3. Welding rod Ø 5.0 mm 70 1 125,000
Ø 4.0 mm 70 1 125,000
4. Eye boor Ø 6 - 16 10 27,500
5. Grinding stone Ø 4 inchi 42 12,500
6. Gauging rod
7. Majun 20 1,500
8. Shearing paper No. 1,2 and 3 10 5,000
9. Others
9A MONORAIL HOIST
C. CONSUMABLE
12a-9-33
Item Description Material Unit (kg) Unit Price
No. Rp. Yen
1. Oxygen 6 85,000
2. Acetelyn 2 220,000
3. Welding rod Ø 5.0 mm 70 1 125,000
Ø 4.0 mm 70 1 125,000
4. Eye boor Ø 6 - 16 10 27,500
5. Grinding stone Ø 4 inchi 46 12,500
6. Gauging rod
7. Majun 20 1,500
8. Shearing paper No. 1,2 and 3 14 5,000
12a-9-34
Amount
Rp.
-
28,512,878
-
56,274,758
4,505,986
7,790,000
125,166
90,000
-
-
42,000,000
139,298,788
20,894,818
160,193,606
13,695,000
5,917,500
33,495,000
3,150,000
7,410,000
267,500
90,000
-
-
-
45,000,000
109,025,000
10,902,500
119,927,500
12a-9-35
Amount
Rp.
13,947,000
25,362,000
6,536,000
2,957,500
13,800,000
841,500
-
-
6,973,500
6,039,000
3,450,000
3,250,000
12a-9-36
Amount
Rp.
2,400,000
4,370,000
4,649,000
8,454,000
4,227,000
6,536,000
6,250,000
6,000,000
126,042,500
12,604,250
138,646,750
13,947,000
25,362,000
6,536,000
2,957,500
13,800,000
841,500
-
-
6,973,500
6,039,000
3,450,000
3,250,000
2,150,000
4,025,000
4,649,000
8,454,000
4,227,000
6,536,000
6,250,000
5,850,000
125,297,500
12,529,750
137,827,250
12a-9-37
Amount
Rp.
556,595,106
1,250,000
225,000
25,000
1,500,000
250,000
3,250,000
510,000
660,000
125,000
125,000
275,000
525,000
30,000
50,000
100,000
2,400,000
`
930,000
1,250,000
25,000
1,500,000
255,000
220,000
125,000
125,000
1,250,000
320,000
6,000,000
1,250,000
225,000
25,000
1,500,000
250,000
3,250,000
12a-9-38
Amount
Rp.
510,000
440,000
125,000
125,000
275,000
575,000
30,000
70,000
2,150,000
`
930,000
1,250,000
25,000
1,500,000
255,000
220,000
125,000
125,000
1,250,000
170,000
5,850,000
12a-9-39
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. MATERIAL
1. GATE LEAF
- Plate SUS 304
- Plate < 25 SS 400 30 16,500 495,000
- Plate < 65 SS 400 -
- H Beams SS 400 -
- Canal SS 400 -
- Steel Casting S 45 C 65 47,500 3,087,500
- Round bar SUS 304 2 53,500 107,000
- Bushing BC 3 2 45,000 90,000
- Rubber seal Rubber -
- Bolt & Nuts HTB -
99 -
2. GUIDE FRAME
- Round bar SUS 304 7 53,500 374,500
- Steel Casting S 45 C 182 47,500 8,645,000
- Bushing BC 3 26 45,000 1,170,000
- Plate SS 400 50 12,500 625,000
TOTAL 16,053,400
B. CONSTRUCTION COST
1. Fabrications
- Foreman 1 x 15 x 10 150 46,490 6,973,500
- Fitter 2 x 30 x 10 300 42,270 12,681,000
- Welder 1 x 5 x 10 50 65,360 3,268,000
- Gas Cutting 1 x 5 x 10 50 42,250 2,112,500
- Helper 4 x 30 x 10 600 11,500 6,900,000
- Sandblasting & Painting 2 76,500 153,000
-
2. Mechanical -
- Foreman 1 x 2 x 10 20 46,490 929,800
- Fitter (Bor & Milling) 2 x 2 x 10 40 40,260 1,610,400
- Helper 2 x 2 x 10 40 11,500 460,000
- Equipment and Tools Ls 1,675,000
C. CONSUMABLE Ls 1,100,000
E. ERECTION COST
- Foreman 1 x 3 x 10 30 46,490 1,394,700
- Fitter Mechanical 1 x 5 x 10 50 42,270 2,113,500
- Fitter electrical 1 x 1 x 10 10 42,270 422,700
- Welder 1 x 2 x 10 20 65,360 1,307,200
- Helper 5 x 2 x 10 100 12,500 1,250,000
12a-10-40
Item Description Material Unit (kg) Unit Price Amount
No. Rp. Yen Rp.
TOTAL 52,431,830
TOTAL (A + B + C + D + E) 68,485,230
12a-10-41
Item Description Material Unit (kg) Unit Price Amount
No. Rp. Yen Rp.
1,100,000
E. EQUIPM, TOOLS AND CONSUMABLE `
1. Welding machine 10 KW 1 x1 155,000 155,000
2. Gas cutting 1 1,250,000 1,250,000
3. Hammer 5 Kg 1 25,000 25,000
4. Grinding machine Ø 4 inchi
5. Hand Drilling machine Ø 9 - 16
6. Oxygen 1.50 85,000 127,500
7. Acetelyn 0.50 220,000 110,000
8. Welding rod 1 125,000 125,000
9. Grinding stone Ø 4 inchi 5 12,500 62,500
10. Chain block 1T 1 925,000 925,000
11. Others 120,000
2,900,000
12a-10-42
Analisa Harga Satuan Pekerjaan : Hydromekanikal
A. INTAKE, REGULATING,
GUARD GATES
1. Rubber seal 10 M 175,000 1,750,000
2. Bolt and Nuts (SUS 304) 40 Pcs 7,500 300,000
3. Bearing 2 Pcs 275,000 550,000
4. Bush (Oilless) 2 Pcs 1,250,000 2,500,000
5. Selenoit 2 Pcs 2,225,000 4,450,000
6. Flexible pipe of Hydraulic 30 M 225,000 6,750,000
7. Bronze Nut (Spindle) 2 Pcs 1,750,000 3,500,000
8. Limit Swict 2 Pcs 1,775,000 3,550,000
C. CONTROL, AND
EMERGENCY GATES
1. Rubber seal 17 M 175,000 2,975,000
2. Bolt and Nuts M 12 x 70 ls 20 Pcs 7,500 150,000
3. Oilles bush Ø 70/85x80 2 Pcs 550,000 1,100,000
D. TOOLS
1. Chain Block 2.0 t 4 Pcs 1,750,000 7,000,000
2. Wire rope Ø 20 10 M 75,000 750,000
3. Tool kit 1 set 5,500,000 5,500,000
4. Hammer 5.0 Kg 2 Pcs 25,000 50,000
5. Punch 10 mm in Dia 1 Pc 25,000 25,000
6. Schuitmatch. 12 inchi 1 Pc 175,000 175,000
7. Spesial tools M 12, 32, L et Ls 375,000 375,000
TOTAL 51,122,500
12a-11