Professional Documents
Culture Documents
Hilton CH 11 Select Solutions
Hilton CH 11 Select Solutions
11-16 The conceptual problem in applying fixed manufacturing overhead as a product cost is that this procedure treats
fixed overhead as though it were a variable cost. Fixed overhead is applied as a product cost by multiplying the
fixed overhead rate by the standard allowed amount of the cost driver used to apply fixed overhead. For example,
fixed overhead might be applied to Work-in-Process Inventory by multiplying the fixed-overhead rate by the standard
allowed machine hours. As the number of standard allowed machine hours increases, the amount of fixed overhead
applied increases proportionately. This situation is conceptually unappealing, because fixed overhead, although it is
a fixed cost, appears variable in the way that it is applied to work in process.
EXERCISE 11-26 (40 MINUTES)
2. Fixed-overhead variances:
Standard
Standard Fixed-
Allowed Overhead
Hours Rate
40,000 $6.00 per
hours hour*
Fixed-overhead Fixed-overhead
budget variance volume variance
$300,000
*Fixed overhead rate = $6.00 per hour = (25,000)(2hrs per unit)
†
Some accountants would designate a positive volume variance as "unfavorable."
EXERCISE 11-31 (45 MINUTES)
$ 25,000
Budgeted fixed overhead...........................................................................
$ 32,500 a
Actual fixed overhead ...............................................................................
12,500
Budgeted production in units......................................................................
12,000 c
Actual production in units ..........................................................................
4 hours
Standard machine hours per unit of output.................................................
$8.00
Standard variable-overhead rate per machine hour.....................................
$9.00 b
Actual variable-overhead rate per machine hour.........................................
3 d
Actual machine hours per unit of output......................................................
$ 36,000 U
Variable-overhead spending variance ........................................................
$ 96,000 F
Variable-overhead efficiency variance........................................................
$ 7,500 U
Fixed-overhead budget variance................................................................
$ 1,000 g U*
Fixed-overhead variance............................................................................
Total actual overhead................................................................................
$356,500
$409,000 e
Total budgeted overhead (flexible budget)..................................................
$425,000 f
Total budgeted overhead (static budget).....................................................
Total applied overhead...............................................................................
$408,000
Explanatory Notes:
Total applied overhead = total standard hours total standard overhead rate
$408,000 = X $8.50
X = 48,000 = total standard hrs.
total standard hrs.
Actual production = standard hrs. per unit
48,000
12,000units
= 4
overhad teproductin perunit
= ($8.50)(12,500)(4)
= $425,000
6. $294,150 c
9. $7,500 U d
10. $9,000 F e
11. $(126,000) (Negative) f (The negative sign means that applied fixed
overhead exceeded budgeted fixed overhead.)
19. $270,000 j
20. $756,000 k
b
Total standard overhead rate
= variable overhead rate + fixed overhead rate
= $7.50 + $21.00 = $28.50
c
Variable-overhead spending variance
= actual variable overhead – (actual direct-labor
hours standard variable overhead rate)
$16,650 U = actual variable overhead – (37,000 $7.50)
Actual variable overhead = $294,150
d
Variable-overhead efficiency variance
= SVR(AH – SH)
= $7.50(37,000 – 36,000)
= $7,500 U
e
Fixed-overhead budget variance
= actual fixed overhead – budgeted fixed overhead
= $621,000 – $630,000
= $9,000 F
f
Fixed-overhead volume variance
= budgeted fixed overhead – applied fixed overhead
= $630,000 – (36,000 $21)
= $126,000 F
36,000
6,000units
= 6
j
Applied variable overhead
= SH SVR
= 36,000 $7.50
= $270,000
k
Applied fixed overhead
= SH fixed overhead rate
= 36,000 $21
= $756,000
PROBLEM 11-47 (60 MINUTES)
budgeted machine hours 30,000
1. Standard machine hours per unit = budgeted production = 6,000
$540,000 $166,000
2. Actual cost of direct material per unit = 6,200units
$504,000 $156,000
3. Standard direct-material cost per machine = 30,000
hour
= $22 per machine
hour
$546,000 $468,000
$169.00per unit
4. Standard direct-labor cost per = 6,000units
unit
6. First, continue using the high-low method to determine total budgeted fixed
overhead as follows:
The key is to realize that fixed overhead includes not only insurance and
depreciation, but also the fixed component of the semivariable-overhead costs
(supervision and inspection). (Note that maintenance and supplies are true
variable costs.)
Now, we can compute the standard fixed-overhead rate per machine hour, as
follows:
$648,000
Standard fixed-overhead rate per machine hour = 30,000hours
8. Variable-overhead efficiency
variance
= (AH SVR) – (SH SVR)
= (32,000 $20.20) – (31,000* $20.20) = $20,200 Unfavorable
11. Flexible budget formula, using the high-low method of cost estimation:
$3,080,000 $2,928,000
Variable cost per machine hour = $76 per hour
32,000 30,000
Therefore, the total budgeted production cost for 6,050 units is:
The report is based on a static budget. Management should use a flexible budget
that compares the same level of activity, calculating variances between the actual
results and the flexible budget. Also, management might consider implementing an
activity-based costing system.
Costs over which the supervisors have no control, such as fixed production costs
and allocated overhead costs, are included in the report.
The report uses a single plant-wide rate to allocate fixed production costs. Square
footage may not drive the fixed production costs, and there may be a more
appropriate base such as number of units produced. It may be more appropriate to
use different cost drivers for each of the different product lines.
Be frustrated and confused by the conflicting signals of the report and what is
occurring in his department and in the market. This confusion about the
department's results and, consequently, the uncertainty of his job will lead to stress
which may negatively affect his performance.
Hold supervisors responsible for only those costs over which they have control by
using a contribution approach.
Flexible
Actual Budget Variance
Units............................................................. 3,000 3,000
Revenue........................................................ $483,000 $495,000 a $12,000 U
Variable production costs:..............................
Direct material........................................... $ 69,300 $ 72,000 b $ 2,700 F
Direct labor................................................ 54,900 54,000 c 900 U
Machine time............................................. 57,600 58,500 d 900 F
Manufacturing overhead............................. 123,000 126,000 e 3,000 F
Total variable costs.................................... $304,800 $310,500 $ 5,700 F
Contribution margin....................................... $178,200 $184,500 $ 6,300 U
a
($412,500 budget ÷ 2,500 budgeted units) 3,000 actual units
b
($ 60,000 budget ÷ 2,500 budgeted units) 3,000 actual units
c
($ 45,000 budget ÷ 2,500 budgeted units) 3,000 actual units
d
($ 48,750 budget ÷ 2,500 budgeted units) 3,000 actual units
e
($105,000 budget ÷ 2,500 budgeted units) 3,000 actual units
b. Steve Clark should be more motivated by the revised report since it clearly shows
that the variable cost variances for his product line were better than Sara McKinley
had thought, despite the fact that there is an unfavorable contribution margin
variance. Clark is not responsible for the revenue variance which resulted from a
decrease in the sales price.
1. Calculation of variances:
Direct-material price = PQ(AP – SP)
variance
= 15,000($2.20* – $2.00)
= $3,000 Unfavorable
*Each dollar number in the flexible budget column is equal to the static budget
number given in the problem multiplied by 1.125 (225,000/200,000). This reflects the
increase in the volume of sales from 200,000 units to 225,000 units.
4. The variance between the flexible budget contribution margin and the actual
contribution margin, from requirement (1) is $124,250 U.
This $124,250 unfavorable variance between the flexible budget and actual
contribution margin for the chocolate nut supreme cookie product line during
April is explained by the following variances:
Dividing the total actual labor cost by the actual labor time used, for
each type of labor, shows that the actual rate and the standard rate are
the same (i.e ., AR = SR ). Thus, this variance is zero.
CASE 11-55 (CONTINUED)
= $37,500 U
= SVR ( AH SH *)
625,000 3 225,000
= $32.40
60 60
= $27,000 F
g. Sales-price variance =
= $22,500 U
Summary of variances:
5. a. One problem may be that direct labor is not an appropriate cost driver
for Colonial Cookies, Inc. because it may not be the activity that drives
variable overhead. A good indication of this situation is shown in the
variance analysis. The direct-labor efficiency variance is favorable,
while the variable-overhead spending variable is unfavorable. Another
problem is that baking requires considerably more power than mixing
does; this difference could distort product costs.