ID Task Task Name Duration Start Finish Feb 11, '18 Feb 18, '18 Feb 25, '18

Duration Start Finish Feb 11, '18 Feb 18, '18 Feb 25, '18 Mar 4, '18 Mar 11, '18 Mar 18, '18 Mar 25, '18 Apr 1, '18 Apr 8, '18 Apr 15, '18
Mode T F M T S W S T F M T S W S T F M T S W S
1 Research 25 days Fri 2/16/18 Thu 3/22/18
2 Read Article on ICE for space 5 days Fri 2/16/18 Thu 2/22/18
3 Calculate horsepower by using GH2 and GOX 5 days Fri 2/23/18 Thu 3/1/18
4 Determine fuel necessary for a semi to drive from Dallas to El Paso
5 days Fri 3/2/18 Thu 3/8/18
5 Calculate solar power required to produce fuel from water 5 days Fri 3/9/18 Thu 3/15/18
6 determine how long it would take to produce fuel 5 days Fri 3/16/18 Thu 3/22/18
7 ICE Model 35 days Fri 2/16/18 Thu 4/5/18
8 Acquire funding 5 days Fri 2/16/18 Thu 2/22/18
9 order 5 days Fri 2/23/18 Thu 3/1/18
10 assemble 5 days Fri 3/2/18 Thu 3/8/18
11 design motor bracket 10 days Fri 3/9/18 Thu 3/22/18
12 fabricate bracket 5 days Fri 3/23/18 Thu 3/29/18
13 modify 5 days Fri 3/30/18 Thu 4/5/18
14 Arduino 40 days Fri 2/16/18 Thu 4/12/18
15 specify kit 5 days Fri 2/16/18 Thu 2/22/18
16 order 5 days Fri 2/23/18 Thu 3/1/18
17 learn code 10 days Fri 3/2/18 Thu 3/15/18
18 programming 10 days Fri 3/16/18 Thu 3/29/18
19 test 10 days Fri 3/30/18 Thu 4/12/18

Task Project Summary Manual Task Start-only Deadline

Project: Ritika's Project Split Inactive Task Duration-only Finish-only Progress


Date: Fri 2/16/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone