Bill of Materials

PERIMETER FENCING

Owners: Mr. Willy De Luna

Prepared By

Arch. Romlene B. Guiruela UAP


PRC No. 25311
BILL OF MATERIALS P76,280.00
1. Perimeter Fencing (CHB
WALL
Excavation of Wall Footing
Excavation of Column Footing
Excavation of Grade Beam
Laying of Footing
Reinforcements 10mm def bars
Concrete Pouring of Footing,
Grade Beam, and Tie Beams
CHB Laying (CHB #4)
Column Installation 10mm &
12mm def bars
Column Concrete Pouring
Plastering

2. Front Gate (Steel Gate) P64,125.00


Cutting of C purlins (1.5mm thk
2x6”)
Cutting of Tubular sch. 40
Welding of Gate Panels
Pre Painting treatment
Painting
Installation of Hinges