Area
1. Tiles - Pieces -Get the area of Concern
2. Plywood/Boards - Pieces -Unit Area
3. CHB's - Pieces
4. Paint - Gallons
Volume
1. Cement - Rags
2. Concrete - Cu. M.
3. Deformed Bars - Pieces
4. Sand & Gravel - Cu. M.
5. Board Feet
1. Quantity
2. Cost
3. Area-related
4. Volume-related
5. Weight
6. Length
7. Conversion
Area
1. Tiles
8m x 20m = 160sqm
Use 0.60m x 0.60m Tiles
=0.60 x 0.60 = 0.36sqm
QTY= 160sqm x 1pc/0.36sqm
If with 3% allowance
QTY= 160sqm x 1pc/0.36sqm x 1.03
4. Paint
= 20sqm = 1 Gal
= 25sqm = 1 Gal
= 30sqm = 1 Gal
= 35sqm = 1 Gal
= 40sqm = 1 Gal
Volume
1. Board Feet
Use 2"x2"x8FT KD @ 0.40 O.C. B.W.
8ft = 2.4m
[(20m/0.4)+1]x8 = 408m
[(8m/0.4)+1]x8 = 420m
Total Length = 828m
Unit Length = 2.4m (8ft)
Qty = 828 x 1 pc/2.4m = 345pcs
BDft = 2x2x8/12 x 345
=920 Bdft
2. Cement
TYPE BAGS
AA 12 Bags / Cu. m.
A 9 Bags / Cu. m.
C 6 Bags / Cu. m.
1 Bag = 42 kg
3. Concrete = 2400kg/cu. m
4. Deformed Bars
Length