Work Schedule (GF & FF Slabs)

Construction of Boys Hostel At IST ISLAMABAD.


Apr-18 May-18
Sr No Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 Ground Floor Slab Part


I
Concrete
2 First Floor Column Part
I
Steel Fixing
Form Work
Concrete 24 Cols
3 First Floor Slab Part I 10 10 4
Form Work 12 Days Stipping Period
Steel Fixing
Electrical Conduits
Concrete Pouring
4 Ground Floor Slab Part
II
Form Work
Steel Fixing
Electrical Cpnduits
Concrete Pouring
5 First Floor Columns
Part II
Steel Fixing
Form Work
Concrete Pouring
6 First Floor Slab Part II 10 10 10 11
Form Work 12 Days Stipping Period
Steel Fixing
Electrical Cpnduits
Concrete Pouring