You are on page 1of 9

Critical Chain Project

Management
Course progress
Initiating Planning Executing Controlling Closing
Integration
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder

We are in the planning process group and time management knowledge area
Overestimating activity times
• It is believed that those who estimate activity times usually
provide an overestimate
• Even thought there is a tendency to overestimate activity
durations, why do so many projects come in behind schedule?
Overestimating
• Even thought there is a tendency to overestimate activity
durations, why do so many projects come in behind schedule?
• Parkinson’s law: work fills the time available
• Self-protection: team members don’t report early finish
• Dropped baton: even if task finishes early, successor task not
ready to start
• Excessive multitasking
• Resource bottleneck
• Procrastination
Critical Chain Project Management (CCPM)
• CCPM suggests that one solution to time overrun is to use estimates
where there is only a 50% chance of completion before time (instead
of 80-90% chance of completion)
This appears to be counterintuitive. Why do this?
Critical Chain Project Management
• Why might underestimating work?
• Parkinson’s law does not apply
• No Procrastination
Critical Chain Project Management (CCPM)
• Used by companies such as

You might also like