You are on page 1of 4

A-75 2012 IEEE International Conference on Condition Monitoring and Diagnosis

23-27 September 2012, Bali, Indonesia

Application of Modern Testing and Diagnostic


Methods for High Voltage Power Cables
Edward Gulski Piotr Cichecki
onsite hv solutions AG onsite hv solutions Benelux BV
Luzerne, Switzerland Werkendam, the Netherlands
e.gulski@onsitehv.com p.cichecki@onsitehv.com

Steve Burks Chris Grodzinski


onsite hv solutions Americas Inc onsite hv solutions Americas Inc
Gormley, Canada Gormley, Canada
s.burks@onsitehv.com c.grodzinski@onsitehv.com

Abstract— Based on the international experiences as collected in


the last 2 years at different power grids, cable manufacturers and
normalisation work of international bodies, this contribution (a)
focuses on several fundamental and applied aspects of on-site
testing and diagnosis of new and service aged HV power cables.
Based on the above consideration and evaluation and supported
by field experiences, a concept of testing recommendation and
procedure will be discussed. In particular different important (b)
aspect of testing new connections as well as condition assessment
of service aged power cables will be mentioned in this paper. (d)

Keywords-on-site testing and diagnosis; partial discharges;


power cables; damped AC voltages; dissipation factor
(c)
I. INTRODUCTION
Figure 1 Examples of insulation defects in power cables: (a) termination
It is known, that an insulation failure of a HV power cable of 132 kV XLPE cable with un-sealed bottom resulting in contamination
can occur as a result of the normally operational voltage or and moisture ingress in side insulator, (b,c) cable movement due to
during a transient voltage due to lightning or switching surges, expansion of oil due to high temperatures. Directly resulting in cracks and
figure 1. The failure can occur if localized electrical stresses voids in joint insulation with final breakdown, (d) electrical treeing in 150
kV gas pressure cables resulting in long term insulation degradation and
are greater than the dielectric strength of dielectric materials in finally cable breakdown [15]
the area of the localized stress or the bulk dielectric material
degrades to the point where it cannot withstand the applied level of voltage stresses and all insulation which is aged and/or
voltage. Therefore together with type testing, the routine consists of insulation defects should have a lower level of
testing makes high voltage (HV) on-site testing including withstand voltage and should produce a breakdown during the
diagnostic measurements, e.g. partial discharges, part of designated test time.
reliability improvement of high voltage power cables. In It is known that the above described, so called non-
particular, the on-site tests are applied to prove two monitored voltage withstand testing methods only, can not
characteristics of a cable circuit. always be sufficient to identify all manufacturing and
1. Quality and cable system integrity; installation problems. Moreover it has to be considered that:

2. Availability /reliability of the cable circuit. 1. due to the applied test voltage stresses higher than the
operational stresses, the test may be destructive even if no
In general as on-site acceptance test for newly installed or failure has occurred,
repaired circuits one of the two approaches are in use:
2. Due to the fact that the duration of the over-voltage is
1. Destructive withstand tests by over-voltage stresses arbitrarily selected e.g. 1 hour it can not be excluded that
applied, e.g. for 1 hour to the test object, or after e.g. 1 hour and 10 minutes a failure will occur.
2. Alternatively a voltage test of 1xUo as applied for 24 hrs. It has been observed that after successful non-monitored
The first approach is based on the assumption that a healthy voltage withstand tests as described above, during initial
(defect-free and/or non-aged) insulation can withstand high operation up to several months of operation, failures have

978-1-4673-1018-5/12/$31.00 ©2012 IEEE 651


1HZLQVWDOOHG 5HSDLUHG 6HUYLFHDJHG
FDEOHV UHIXUELVKHGFDEOHV FDEOHV

'$&DFFHSWDQFH '$&PDLQWHQDQFH '$&GLDJQRVWLF


WHVW WHVW WHVW

'$&YROWDJH 3DUWLDOGLVFKDUJHV 3'


ZLWKVWDQGWHVW 'LVVLSDWLRQIDFWRU WDQδ
'LVVLSDWLRQIDFWRU WDQ δ

(YDOXDWLRQ
0RQLWRUHG

1RQPRQLWRUHG

FULWHULD Figure 3. Example of modern monitored on-site testing and


3DVV)DLO
diagnosis by partial discharges and dissipation factor measurements
Figure 2. Types of damped AC (DAC) on-site electrical tests which using sinusoidal damped AC voltages: maintenance test
can be performed on-site on power cables [15] of a 220 kV cable circuit

occurred [13, 14]. It has been found that insulation defects in IEC 60060-3: High Voltage test techniques – Part 3:
the cable insulation and cable accessories are responsible for Definitions and requirements for on-site testing;
these failures. Therefore to detect during the after-installation IEEE 400: Guide for Field Testing and Evaluation of the
or after-repair testing all weak spots in the cable insulation and Insulation of Shielded Power Cable Systems;
cable accessories monitored testing is becoming nowadays IEC 60840: Power cables with extruded insulation and the
more and more common practice, figure 2. It is known that accessories for rated voltages above 30 kV up to 150 kV Test
monitored testing consists of a voltage withstand test combined methods and requirements;
with a diagnostic test, e.g. partial discharge measurement. IEC 62067: Power cables with extruded insulation and the
Moreover with regard to diagnostic testing, where over- accessories for rated voltages above 150 kV, Test methods and
voltages (stresses higher than U0) may have very destructive requirements;
influence on the remaining service life of a particular cable IEEE 400.3: Guide for PD Testing of Shielded Power Cable
circuit makes the application of sensitive diagnostics at stresses Systems in a Field Environment;
up to U0 crucial. The practical realization of such tests becomes IEC 60270: Partial discharges measurements;
more attractive if modern on-site testing methods are available IEC 885-3: Test methods for partial discharges measurements
which are characterized by: on lengths of extruded power cable;
1. lightweight and high level of mobility of the test system, IEC 60141: Tests on oil-filled and gas-pressure cables and
their accessories.
2. test system compactness versus output voltage, It follows from figure 2 that the majority of the application
3. easy system assembling and low voltage erecting effort, of DAC so far are based on the combination of voltage
withstand test and advanced diagnostic measurements
4. low necessary power demand for testing long cable (e.g. partial discharges and dielectric losses). For voltage
lengths, withstand test, a predetermined number of DAC excitations is
applied, see figure 4-5. Due to shorter duration of the excitation
5. possibility of sensitive standardized PD detection and and decaying characteristic of the voltage, DAC test results
dissipation factor measurement. obtained can be different from those obtained by continuous
In this paper, the use of damped sinusoidal AC voltages AC withstand voltage testing.
(DAC) for monitored testing of power cables will be discussed To generate damped AC voltages with duration of a few
based on general consideration and practical examples. An tens of cycles of AC voltage at frequencies up to a few
example of a DAC test system is shown in figure 3. hundreds of Hz a test system has been developed [1, 2]. This
II. ON-SITE ENERGIZING AT DAMPED AC VOLTAGES method is used to energize and to test on-site power cables
with sinusoidal AC frequencies. In addition this method can
DAC testing can be used as simple withstand test or in easily be used to measure and to locate on-site partial
combination with partial discharges (PD) and dissipation factor discharges in power cables in accordance with IEC 60270
(DF) measurements. recommendations, figure 8. The system consists of a digitally
As a result the use of damped AC voltages for testing power controlled power supply to charge capacitive load of power
cables is in compliance to the following international cables with large capacitive load e.g. 10 μF. With this method,
standards: the cable under test is charged during a time tcharge=Umax
Ccable/Iload with increasing voltage over a period of a number of
seconds to the selected maximum test voltage level. Then a

652
III. PRACTICAL EXAMPLES
Application of damped AC voltages to testing and
diagnosis of transmission power cables up to 230 kV has a
history of more than 6 years [5, 8, 9]. Hereafter with regard to
the discussion about the importance of monitored testing three
examples will be discussed.
A newly installed 12 km long, 50 kV XLPE insulated
underground cable circuit has been tested in accordance to the
Dutch NEN 3630 recommendation. This norm recommends
voltage withstands testing using AC resonance system 25-200
Hz applied at 2.5xUo. It has been decided to perform
Figure 4 Schematic overview of one DAC excitation. The maximum monitored withstand testing by using DAC resonant circuit
DAC voltage level is determined by the voltage peak values VDAC with damped sinusoidal AC voltages (25-200 Hz) for 1 hour
respectively RMS-values VDAC/¥2 of the 1st DAC cycle. testing at 2.5xUo. During the whole time of withstand test
standardized PD detection has been applied. As a result of 1
hour DAC over-voltage no breakdown has been observed,

0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150

Figure 5. Schematic overview of withstand test by damped sinusoidal AC voltage excitations. The duration of the test is determined by a number of DAC
excitations which have been applied to the power cable under the test at a selected DAC test voltage. The maximum DAC withstand voltage level is
determined by the voltage peak values VDAC respectively RMS-values VDAC/¥2 of the 1st DAC cycle.

figure 7. Also no internal PD activity has been registered


(except external corona). It has been concluded that up to
+9SRZHU +9 7HVW2EMHFW +9'LYLGHU 1.7Uo the complete cable system was PD–free (background
VRXUFH ,QGXFWRU 3RZHU&DEOH 3''HWHFWRU
noise level < 10 pC) and the test has been considered as
G8GW successful.
N9 PD A newly installed 4.5 km long, 150 kV XLPE insulated
underground cable circuit has been tested using DAC
resonance system at 63 Hz applied up to 1.7xUo. It has been
'$&UHVRQDQFHFLUFXLW
decided to perform monitored withstand testing. During
increase of the DAC test voltage and starting from 0.6Uo PD
activity has been observed in a joint at 2.5 km location, figure
+9
8. Increasing of the test voltage has shown increase of PD
6ZLWFK activity and at 1xUo test voltage a breakdown during the DAC
Figure 6. Schematic diagrams of damped AC systems for on-site testing voltage period has occurred. Due to the fact that the DAC
and PD detection of distribution and transmission power cables. breakdown energy was very low no further damage has been
done to the joint and based on the PD mapping the failed joint
specially designed solid-state switch connects an air-core has been localized and replaced.
inductor to the cable sample in a closing time of <1μs. At this
moment the series of AC voltage cycles starts with the IV. CONCLUSIONS
resonance frequency of the circuit fDAC = 1/(2Ȇ√(L ⋅ Ccable)) Based on the results above the following can be concluded:
where L represents the fixed inductance of the air core and
Ccable represents the capacitance of the cable sample, figure 6. 1. According to newest developments the monitored
The air core inductor has a low loss factor and design, resulting voltage withstand testing is becoming more and more a
in a slowly decaying AC waveform of test voltage applied to common practice. The use of the PD measurement
the cable sample. During a number of AC voltage cycles the helps to detect and to localize discharging defects in
PD signals are initiated in a way similar to 50(60) Hz inception the insulation and in accessories of power cables.
conditions [12]. 2. For testing power cables damped AC voltages can be
applied as an alternative to continuous AC test
voltages.

653
1 80
1 60
1 40
1 20

3' S&
1 00


80
60
40
20
0
0 20 0 40 0 6 00 8 00 1, 00 0 1 ,2 00 1 ,40 0 1, 60 0 1, 8 00 2 ,000 2,20 0 2, 4 00 2 ,6 00 2 ,80 0 3, 00 0 3 ,2 00 3 , 40 0 3, 60 0

(a) 0 .9
0 .8
18 0
16 0

9R OW DJ H N93HDN
0 .7 14 0

'ORVVHV 
0 .6
(b) 12 0
10 0



0 .5




0 .4 80
0 .3 60
0 .2 40
0 .1 20
0 0
0 20 0 4 00 6 00 80 0 1, 0 00 1 ,2 00 1,40 0 1, 60 0 1 ,8 00 2 ,00 0 2, 20 0 2 ,4 00 2 ,6 00 2, 80 0 3,0 00 3 ,2 00 3 , 40 0 3,60 0
7 LP H V
1? ?\ HOORZ Y Z G       7X HV GD \ 2 FW R EH U      $ 0

Figure 7 Monitored voltages withstand testing of a 50 kV XLPE cable underground circuit (12 km): a) example of PD pattern at 1.7xUo, b) DAC
voltage withstand test 1hrs at 2.5xUo

(a)

[8R [8R

(b)

[8R [8R

Figure 8. Monitored voltages withstand testing of a 150 kV XLPE cable underground circuit (4.5 km): a) example of PD PD mapping as obtained
during DAC voltage testing up to 1.0xUo b) PD-phase resolved patterns as observed at 0.6xUo, 0.73xUo, 0.9xUo and at the breakdown voltage at
1.0xUo
3. Regarding breakdown and as compared to non- [7] Densley J., Ageing Mechanisms and Diagnostics for Power Cables – An
monitored continuous AC voltage testing in case of Overview, IEEE Electrical Insulation Magazine, Vol. 17 Nr. 1 pp. 14-
21, Jan/Feb 2001
inhomogeneous defects (PD occurrence) monitored
[8] Gulski E., Wester E.F.J., Wester P., Groot E.R.S., van Doeland J.W.,
testing using damped AC voltages can be less Condition assessment of high voltage power cables. Proceedings CIGRE
destructive and more sensitive (in case there is no 2004 Session, paper D1-103.
breakdown observed) to detect and to localize [9] Gulski E., Smit J.J., Cichecki P., Seitz P.P., Quak B., de Vries F.,
discharging defects in the accessories. Petzold F., Insulation Diagnosis of HV Power Cables, Proceedings
Jicable'07, 7th International Conference on Insulated Power Cables,
V. REFERENCES France, Versailles, June 2007, paper 51.
[1] Aucourt C., Boone W., Kalkner, W., Naybour R.D. Ombello, F., [10] Gulski E., Cichecki P., Smit J.J., de Vries F., Bodega R., Hermans T.,
Recommendations for a New After Laying Test Method for High Seitz P.P., Dielectric loss diagnosis of service aged HV power cables,
Voltage Extruded Cable Systems, CIGRE Paper No. 21-105, August, Proceedings of CIGRE D1 Colloquium, Hungary Budapest, 2009
1990. [11] Cichecki P., Jongen R.A., Gulski E., Smit J.J., (2008). Statistical
[2] Seitz P.P., Quak B., Gulski E., Smit J.J., Cichecki P., de Vries P., approach in power cables diagnostic data analysis. IEEE transactions on
Petzold F., Novel Method for On-site Testing and Diagnosis of dielectrics and electrical insulation, 15(6), 1559-1569
Transmission Cables up to 250kV, Proceedings JiCable '07, 7th Intern. [12] Gulski E., Cichecki P., Wester F.J., Smit J.J., Bodega R., Hermans
Conf. Insulated Power Cables, Versailles, France, Paper 16, 2007 T.J.W.H., Seitz P.P., Quak B., de Vries F., On-site testing and PD
[3] Wester F.J., Gulski E., Smit J.J., Detection of PD at Different AC diagnosis of high voltage power cables, IEEE transactions on dielectrics
Voltage Stresses in Power Cables, IEEE Electr. Insul. Mag., Vol. 23, and electrical insulation, 2008
No. 4, pp. 28-43, 2007 [13] Gulski E., Cichecki P., Jiankang Z., Rong X., Jongen R., Seitz P.P.,
[4] Gulski E., Lemke E., Gamlin M., Gockenbach E., Hauschild W., Porsche A., Huang L., Practical aspects of on-site testing and diagnosis
Pultrum E., Experiences in partial discharge detection of distribution of transmission power cables in China, CMD2010
power cable systems, CIGRE, Vol 208 Electra, pp. 34-43, 2003 [14] CIGRE Technical Brochure 502 On-site testing and PD measurements
[5] Gulski E., Cichecki P., Groot E.R.S, Smit J.J., de Vries F., Slangen J., [15] Gulski E., Patterson R., Importance of On-site Testing and Diagnosis of
Groot E.R.S., Pellis J., van Houwelingen D., Hermans T.J.W.H., Power Cables, NETA PowerTest 2011 Conference, Washington DC,
Wegbrands B., Lamballais L., Conditon Assessment of Service Aged USA.
HV Power Cables, CIGRE, Paper D1-206, 2008
[6] Popma J., Pellis J., Diagnostics for high voltage cable systems,
proceedings ERA conference on HV plant life extension, Belgium, 23-
24 November, 2000.

654

You might also like