You are on page 1of 6

Reclosers

Analysis of
Distribution System Reliability and Outage Rates
R280-90-7 Reference Data

RELIABILITY ANALYSIS Average Service Availability Index (ASAI)


Reference Data R280-90-7 provides information on methods to Defines the ratio of the total number of customer hours that ser-
measure and improve distribution system reliability and outage vice was available during year, to the total customer hours
rates. Standard indices are described that are used to measure demanded. (customer hours demanded = 24 hours/day x 365
distribution system reliability and calculate improvements. days = 8760 hours)
Outage rates goals are discussed and examples of various ASAI = 8760 - SAIDI
types of distribution systems are provided, showing logical 8760
switchgear applications that will reduce outage rates and For example, a SAIDI of 1.0 hours per year.
improve overall system operation. ASAI = 8760 - 1.0 = 99.989%
Transient and permanent faults are defined and discussed. 8760
Transient fault protection schemes including reclosers and fuses
for sectionalizing feeder lines and taps are discussed. The differ- OUTAGE RATE GOALS
ence in fault protection philosophy for overhead versus under- For the purposes of this discussion an outage is defined as any
ground systems is examined. Additional reliability improvements loss of service for more than a normal reclosing interval. Many
are discussed that can be obtained through system automation utilities define an outage as loss of service for more than two
by remote identification of faulted sections, coupled with remote minutes.
switching to isolate the fault and restore service to the rest of the
line. Urban and Rural Systems
Outage rate goals will vary depending upon the nature of the
PERFORMANCE INDICES distribution system. Urban systems typically have less line expo-
For discussion of outage rates, performance indices are sure than rural systems. As a result, urban systems experience
frequenly used as described in the EPRI report EL-2081, fewer outages per year than rural systems.
Volume 2, Project 1356-1, pages 3-3 and 3-4. Use of these Typical outage rate goals for urban and rural distribution sys-
“standard” indices will permit meaningful comparison between tems are to limit outages to an average of 1.0 (urban) and 1.5
utilities or between different divisions of a given utility, and per- (rural) outages per year (SAIFI). With each outage lasting an
haps most importantly; allow evaluation of system changes by a average duration of 1 hour (CAIDI), the average annual interrup-
direct comparison of past and future performance of a feeder or tion is 1.0 hours for urban systems and 1.5 hours for rural distri-
system as changes are made. These standard indices are bution systems.
defined as follows:
Table 1
System Average Interruption Frequency Typical Utility Outage Rate Goals
Index (SAIFI)
Defines the average number of times that a customer’s service System
is interrupted during a year. A customer interruption is defined Index Type Operating Goal
as one interruption to one customer. SAIFI Urban 1.0 Outages Per Year
SAIFI = total number of customer interruptions SAIFI Rural 1.5 Outages Per Year
total number of customers served CAIDI Rural/Urban 1.0 Hours Per Outage
SAIDI Urban 1.0 Outage Hours Per Year
System Average Interruption Duration SAIDI Rural 1.5 Outage Hours Per Year
ASAI Urban 99.989% Annual Service Availability
Index (SAIDI) ASAI Rural 99.983% Annual Service Availability
Defines the average interruption duration per customer served
per year.
SAIDI = sum of customer interruption durations Many utilities have found that their service reliability deterio-
total number of customers
rated significantly when they converted to a higher distribution
Customer Average Interruption Frequency voltage (for example; 4kV to 13kV). The higher distribution volt-
Index (CAIFI) age allowed them to service longer feeder lengths and more
Defines the average number of interruptions per customer inter- customers with a given feeder. However, each outage that
rupted per year. occurred affected more customers and the longer feeders
required more patrol time to locate the fault.
CAIFI = total number of customer interruptions total
number of customers affected To restore service reliability, the first step is to sectionalize
each feeder into smaller sections, limiting the number of cus-
Customer Average Interruption Duration tomers affected by a given outage and reducing the patrol time
Index (CAIDI) needed to locate and repair the fault. Operating experience of a
Defines the average interruption duration for those customers number of utilities that have adopted this sectionalizing practice
interrupted during a year. has suggested that an optimum feeder segment is 3 to 5 MVA.
CAIDI = sum of customer interruption durations As the load of a line segment approaches 8 to 10 MVA, outage
total number of customer interruptions rates increase to unsatisfactory levels.

December 1987 ● Supersedes 10/86 1


When further relability improvement is desired, some utilities A combination of a recloser and fuses (shown in Figure 1) is
have utilized “loop” operation (figure 9) of adjacent feeders. This typically used to provide protection against both transient and
operation not only sectionalizes the feeder into smaller seg- permanent faults.
ments, it allows the utility to restore service to the customers at
the end of a feeder, minimizing any outage to the smallest pos-
sible segment of the feeder. Two large eastern utilities that have
adopted this scheme have achieved the following service conti-
nuity records:

Utility A
0.715 outages per customer per year (SAIFI),1.056 hours per
outage (CAIDl ), resulting in 0.767 outage hours per customer Figure 1.
per year (SAIDI). Reclosers and fuses provide protection against transient
and permanent faults.
Utility B
0.475 outages per customer per year (SAIFI), 1.4 hours per out-
age (CAIDI), resulting in 0.665 hours per outage per customer The fast trip curve of the recloser is used to clear all transient
per year. faults on the main feeder and taps. For permanent faults on the
taps, the recloser time delay curve allows the tap fuse to clear,
TYPES OF FAULTS—TRANSIENT VS. resulting in an outage on the tap only, as shown in Figure 2.
PERMANENT
Maximum service reliabiIity is achieved when the distribution
system is designed and operated to minimize the effect of any
fault that may occur.
Two types of faults are encountered on an overhead distribu-
tion system: transient and permanent. A transient fault is one
whose cause is transitory in nature. If the arc that results can be
cleared quickly, before it burns into a permanent fault, the cause
of the fault is gone, no equipment damage has occurred, and
the circuit can be re-energized immediately, returning service to
the entire system. Since the “open” time between fault interrup-
tion and re-energization is typically a few seconds in duration,
this operation normally is not classified as an outage.

Examples of Transient Faults Include:


Wind blowing two conductors together temporarily. A tree
branch that falls across two conductors and then falls clear. A
bird or small animal that briefly causes an arc from a live termi-
nal to ground, and then falls clear.
On most distribution systems, the majority of faults (50 to
90%) are transient in nature. With proper protection devices
(fast tripping with fast reclosing), these faults can be cleared
without a reportable outage.

Examples of Permanent Faults


A permanent fault is one in which permanent damage has
resulted from the cause of the fault. Examples would include a
broken insulator, a broken conductor, an automobile knocking a
pole down, etc. With these permanent faults, the line must be
de-energized, a line crew must be brought to the site and
repairs made. Outage times range from 30 minutes to many
hours and result in recorded outages. Figure 2.
For permanent faults, the extent of the outage can be mini- Recloser/fuse link coordination.
mized by limiting the size and length of the affected line. The
shorter line segment minimizes the number of customers affect-
ed and minimizes the time required to patrol the line and locate OUTAGE RATE REDUCTION METHODS
the fault. The following examples describe how outage rates can be
For faults on the main feeder line, a line sectionalizing device reduced by various approaches to using main line sectionaliz-
(recloser or sectionalizer) can be used to divide the feeder into ing devices, recloser-fuse coordination and loop schemes.
smaller line segments. All taps should have a protective device
(fuses for small taps, a recloser or sectionalizer for larger taps) ExampIe 1
where they connect to the main feeder. Even on very small taps, Use of Main Line Sectionalizing Device
a fuse should be used. The justification is that this type of tap
fuse does not protect the tap, it protects the remainder of the
distribution feeder from a fault on the tap. PROBLEM
All permanent faults on the main line result in an outage of
the entire feeder.

2
R280-90-7
Investigate outage rates for one fault at F1 and one fault at F2 2. If committed to existing breaker protection adding a recloser
as shown in Figure 3. in line will still provide a dramatic decrease in outage rate:
Each outage = 1 hour in length (time required to locate fault a. 25% decrease due to line sectionalizing as described in
and restore service). earlier systems.
PLUS
b. Reduction in tap outages due to transient fault protection
provided by recloser. 50% of taps x 70% transient fault
rate = 35% reduction in outage rate.
c. Therefore, the total reduction in outage equals 25% +
35% = 60% reduction in outage rate.

Example 3
Figure 3.
Circuit Breaker In Substation With Fast
Calculating reliability.
And Delayed Relay Settings
PROBLEM
Breaker utilizing conventional relay settings of one INST trip
With No Line Recloser:
followed by time delay trip operations, with the INST trip level
Fault at F1: 1000 customers x 1 hr. = 1000 cust. hrs.
set typically at 2-1/2 times the basic phase and ground trip set-
Fault at F2: 1000 customers x 1 hr. = 1000 cust. hrs.
tings. Refer to Figure 5.
Outage Total = 2000 cust. hrs.
Phase trip = 800 amperes, INST at 2000 amperes
Ground trip = 300 amperes, INST at 750 amperes
OPTION TO IMPROVE SERVICE RELIABILITY
The 750 ampere ground trip instantaneous setting generally
1. Refer to Figure 3. Add a recloser at point A as a main line
will not provide “reach” for faults distant from the substation;
sectionalizing device to reduce outage rates caused by faults
thus all transient faults occurring at these locations and all
on the main feeder.
faults below 750 ampere magnitude on any tap, will result in an
With Recloser At A:
outage.
Fault at F1: 1000 customers x 1 hr. = 1000 cust. hrs.
Fault at F2: 500 customers x 1 hr. = 500 cust. hrs.
Outage Total = 1500 cust. hrs.

Outage rate with line recloser equals 1500/2000 or 75% of rate


without line recloser; or: 500/2000 = 25% reduction in outage
rate.

NOTE: A sectionalizer can be substituted at point A to produce the


same 25% reduction in outage rate. Figure 5.
Substation breaker with typical relay settings.
The actual reduction in outage rate will be greater than the
25% calculated due to the shorter time required to patrol the line OPTIONS TO IMPROVE SERVICE RELIABILITY
and locate the fault (crew must patrol only 1/2 of total line for 1. Replace breaker with recloser with conventional recloser
fault at either F1 or F2). sequence providing “fast” tripping at basic trip levels select-
ed. With electronic control, the “fast” TCC can be selected
Example 2 with adequate time delay near minimum trip to prevent any
Circuit Breaker In Substation Without “nuisance” trips. Sequence coordination feature can be used
Instantaneous Tripping for even better coordination if any down line reclosers are
used.
PROBLEM The reduction in outage rate is dependent on the parame-
All faults on taps result in an outage due to fuse operation and ters of the circuit—how many faults below 750 amperes (as
outage rates can be high. Refer to Figure 4. an example) are experienced. For a moderateIy long feeder
with lengthy taps, a 50% reduction in the outage rate may be
reasonable.
2. Even without breaker changeout, adding a recloser in line will
still provide dramatic improvement. The 25% reduction in out-
age rate is due to a line recloser, plus the reduction in out-
ages on the taps due to the increased “reach” of the recloser.

Example 4
Figure 4. Feeder Protected By Recloser
Substation breaker set on all delay operations to lockout.
OPTION TO IMPROVE RELIABILITY
1. Refer to Figure 6. Add a recloser in the line. This will provide
OPTIONS TO IMPROVE SERVICE RELIABILITY the 25% reduction in the outage rate as described earlier,
1. Replace breaker with recloser. plus some added improvement due to the added “reach” (or
a. Outage rate should decrease by a rate equal to the ratio sensitivity) afforded by the more sensitive trip settings of the
of transient faults to permanent faults on the system. line recloser.
Therefore, if 70% of faults are initially transient by nature,
outage rate will decrease by 70%.

3
NOTE: It is generally very difficult or impossible, for any substation Add a normally open tie recloser between feeders as shown in
device to be set to provide reach for protection to the ends of all taps. Figure 9, set to close upon loss of voltage from either side. The
mid-point reclosers will be sectionalizing type reclosers, set to
automatically open for loss of voltage from their source side.
Fault at F1: 500 customers x 1 hr. = 500 cust. hrs.
Fault at F2: 500 customers x 1 hr. = 500 cust. hrs.
Fault at F3: 500 customers x 1 hr. = 500 cust. hrs.
Fault at F4: 500 customers x 1 hr. = 500 cust. hrs.
Outage Total = 2000 cust. hrs.
Adding the tie recloser as shown in Figure 9 and operating the
Figure 6. mid-point reclosers as sectionalizing reclosers has resulted in a
Feeder recloser with conventional recloser settings. 33-1/3% reduction in customer outage:
(3000-2000)/3000 = 33-1/3%.
Adding the three reclosers as shown in Figure 9 to the two
Example 5 feeders has reduced the outage rate to 50% of the original:
Loop Schemes (4000-2000)/4000 = 50%.
For the highest level of service reliability, some utilities have uti-
lized loop schemes. The following example shows the improve-
ment in service reliability that can be accomplished by mid-point
sectionalizing, and addition of a “tie” recloser between feeders.
Refer to Figure 7 and assume one fault at each section, for
one hour duration each.
Fault at F1: 1000 customers x 1 hr. = 1000 cust. hrs.
Fault at F2: 1000 customers x 1 hr. = 1000 cust hrs.
Fault at F3: 1000 customers x 1 hr. = 1000 cust hrs.
Fault at F4: 1000 customers x 1 hr. = 1000 cust. hrs.
Figure 9.
Normally open tie recloser between feeders.

Example 6
Application Of Recloser At Feeder Tap
Refer to Figure 10 and assume “reach” of recloser A extends to
point D on tap.
If a fuse is used at location C:
1. Any transient fault on the main tap line beyond location D will
cause fuse “C” to operate, resulting in an outage on the entire
tap, for a fault that was initially transient.
2. Service restoration can be delayed since crew may spend
Figure 7.
considerable time looking for a fault that no longer exists.
Typical recloser-protected feeders without mid-point 3. For a transient fault beyond any of the downline fuses, the
sectionalizing. downline fuse will operate, again resulting in an unnecessary
outage for a fault that was initially transient.
Refer to Figure 8 and assume one fault at each section for Use of a recloser at location C can normally be sized to pro-
one hour duration to show the effects of mid-point sectionaliz- vide reach for the entire tap. The “fast” trip of the recloser (as
ing. shown in Figure 2) will then clear transient faults, the reclosing
Fault at F1: 1000 customers x 1 hr. = 1000 cust. hrs. operation then restoring service to all customers on the tap.
Fault at F2: 500 customers x 1 hr. = 500 cust. hrs.
Fault at F3: 1000 customers x 1 hr. = 1000 cust. hrs.
Fault at F4: 500 customers x 1 hr. = 500 cust. hrs.
Outage Total = 3000 cust. hrs.
(25% reduction)

Figure 10.
Feeder tap without recloser protection.

Figure 8.
Reclosers at midpoint of feeders.

4
R280-90-7
UNDERGROUND DlSTRIBUTlON For this automated operation, switches have been developed
For an underground distribution feeder or system, comparison to that have a stored energy operator (allows remote switching
an overhead distribution system for purpose of operating reliabil- without power at the switch location) and fault indicators to pro-
ity presents some differences. An underground feeder has no vide remote indication of fault location. Use of switches allows
transient faults, fewer outages and outages of longer duration. more sectionalizing points on the feeder without adding any
steps of coordination. Reclosers are used to provide immediate
Since an underground system has no transient faults, there local fault clearing capabilities that are independent of the com-
generally is no need for fast tripping or reclosing operations. munication system or remote computer control.
Typically, protection at the substation consists of a single time
delay trip operation and lock open. SUMMARY
An underground system will have fewer faults than an over- Increased usage of electricity has led to the need to increase
head system, since there is no exposure to wind, trees, ice, distribution system voltages. Utilization of these higher distribu-
sleet, etc., and limited exposure to wildlife, lightning surges, etc. tion voltages has resulted in decreased system reliability and
When a fault does occur, the outage duration can be quite higher customer outage rates. Efficient application of reclosers
long. The time to patrol the line and locate the fault can be quite can provide dramatic improvements in distribution system relia-
lengthy, equipment or cable repair can also require considerably bility.
more time than equivalent overhead equipment repair. Even Using reclosers to provide transient fault protection on the
though the number of outages on an underground feeder may entire distribution system can improve outage rates by 50-90%.
be limited, the long outage times required for fault location and Reclosers or sectionalizers used as main line sectionalizing
repair can result in unacceptable outage ratio. Addition of a mid- devices can improve outage rates an additional 25%.
point fault sensing and interrupting device can be used to Even greater service continuity can be achieved by using
reduce the number of customers affected and reduce the time nearby feeders as backup supplies. By using reclosers or sec-
required for fault location. tionalizers as normally open feeder ties with local supervisory
controls, outage rates can be improved by an additional 50%
SYSTEM AUTOMATION over unsectionalized systems.
After protective devices are properly applied on a distribution Additional improvements in distribution system reliability can
system, the next higher level of system reliability can be be obtained through the application of supervisory control or
achieved by automating the entire system for remote identifica- distribution automation.
tion of faulted sections and rapid isolation of these sections by
means of remote switching operations.
Remote identification of the faulted section eliminates the time
required for line patrol. The remote switching function allows the
faulted line to be isolated, and service restored to all other line
sections (assuming availability of an alternate feed to the remote
sections) in less than 2 minutes. Thus, the outage is limited to
only the faulted portion of the line.
Figure 11 illustrates a distribution system using both remotely
operated switches and line reclosers that can also be operated
remotely.

Figure 11.
Automated distribution system.

5
P.O. Box 1640
© 1996 Cooper Industries, Inc. Waukesha, WI 53187
Kyle® is a registered trademark of Cooper Industries, Inc. www.cooperps.com

Printed on Recycled Paper KTM


7/97

You might also like