Dikerjakan :
DINAS BINA MARGA Dikerjakan Oleh :
UPTD. PENGUJIAN DAN PENGENDALIAN MUTU Dihitung Oleh :
Jln. Sakti Lubis No. 7 - R Telp./ Fax. ( 061 ) 7867172 Medan Digambar Oleh :
Diperiksa Oleh :
KONTRAKTOR :
PROYEK :
PAKET :
quarry : PT. Karya Murni Perkasa, Patumbak
Uraian Ukuran Saringan
Inchi 1½" 1" 3/4 " 1/2 " 3/8 " #4 #8 # 16 # 30 # 50 # 100 # 200
mm 37.5 25.4 19 12.7 9.5 4.75 2.36 1.18 0.6 0.3 0.15 0.075
Data Gradasi
C. Agg. 1½" 100.00 60.17 40.07 12.89 5.58 2.48 1.92 0.00 0.00 0.00 0.00 0.00
C. Agg. 3/4" 100.00 100.00 100.00 49.26 16.21 3.41 2.65 1.91 0.00 0.00 0.00 0.00
M. Agg. 100.00 100.00 100.00 100.00 100.00 31.64 9.00 4.49 3.59 2.89 2.20 0.20
Abu Batu 100.00 100.00 100.00 100.00 100.00 100.00 76.87 53.35 38.16 29.25 21.00 15.08
Pasir 100.00 100.00 100.00 100.00 100.00 100.00 97.82 82.79 45.30 16.00 3.47 1.36
Filler Semen 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Combinasi Agregat
C. Agg. 1½" 22.00% 22.00 13.24 8.82 2.84 1.23 0.55 0.42 0.00 0.00 0.00 0.00 0.00
C. Agg. 3/4" 25.00% 25.00 25.00 25.00 12.32 4.05 0.85 0.66 0.48 0.00 0.00 0.00 0.00
M. Agg. 27.10% 27.10 27.10 27.10 27.10 27.10 8.57 2.44 1.22 0.97 0.78 0.60 0.05
Abu Batu 19.00% 19.00 19.00 19.00 19.00 19.00 19.00 14.61 10.14 7.25 5.56 3.99 2.87
Pasir 6.00% 6.00 6.00 6.00 6.00 6.00 6.00 5.87 4.97 2.72 0.96 0.21 0.08
Filler Semen 0.90% 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90
Total campuran 100.00% 100.00 91.24 86.82 68.15 58.28 35.87 24.90 17.70 11.84 8.20 5.69 3.90
Spec. Gradasi
Max 100.0 100.0 90.0 76.0 66.0 39.5 26.8 18.1 13.6 11.4 10.0 7.0
Min 100.0 90.0 73.0 55.0 45.0 28.0 19.0 12.0 7.0 5.0 4.5 3.0
Persen Berat Lolos ( % )
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Perkiraan Aspal ( Pb ) :
CA = 75.10 FA = 21.00 FF = 3.90
Pb = 0,035 x CA + 0,045 x FA + 0,18 x FF + 1 = 5.28%
PEMERINTAH PROVINSI SUMATERA UTARA Tgl. Dikerjakan :
DINAS BINA MARGA Dikerjakan Oleh :
UPTD. PENGUJIAN DAN PENGENDALIAN MUTU Dihitung Oleh :
Jln. Sakti Lubis No. 7 - R Telp./ Fax. ( 061 ) 7867172 Medan Digambar Oleh :
Diperiksa Oleh :
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Ukuran Saringan
Gradasi Gabungan ( mm
GK. Max. ) GK. Min.
Perkiraan Aspal ( Pb ) :
CA = 52.08 FA = 39.76 FF = 8.16
Pb = 0,035 x CA + 0,045 x FA + 0,18 x FF + 1 = 6.08%
PEMERINTAH PROVINSI SUMATERA UTARA
DINAS BINA MARGA
UPTD. PENGUJIAN DAN PENGENDALIAN MUTU
Jln. Sakti Lubis No. 7 - R Telp./ Fax. ( 061 ) 7867172 Medan
C. Agg. 3/4"
M. Agg.
Abu Batu
Pasir
Filler Semen
Combinasi Agregat
C. Agg. 1½"
C. Agg. 3/4"
M. Agg.
Abu Batu
Pasir
Filler Semen
Total campuran
Spec. Gradasi
Max 100.0 100.0 100.0 90.0 69.0 53.0 40.0 30.0 22.0 15.0 10.0
Min 100.0 100.0 90.0 72.0 54.0 39.1 31.6 23.1 15.5 9.0 4.0
Persen Berat Lolos ( % )
100
90
80
70
60
50
40
30
20
10
20
10
0
0.01 0.1 1 10 100
Perkiraan Aspal ( Pb ) :
CA = FA = FF =
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Ukuran Saringan
Gradasi Gabungan ( mm
GK. Max. ) GK. Min.
Perkiraan Aspal ( Pb ) :
CA = 71.43 FA = 23.60 FF = 4.97
Pb = 0,035 x CA + 0,045 x FA + 0,18 x FF + 1 = 5.46%
PEMERINTAH PROVINSI SUMATERA UTARA Tgl. Dikerjakan :
DINAS BINA MARGA Dikerjakan Oleh :
UPTD. PENGUJIAN DAN PENGENDALIAN MUTU Dihitung Oleh :
Jln. Sakti Lubis No. 7 - R Telp./ Fax. ( 061 ) 7867172 Medan Digambar Oleh :
Diperiksa Oleh :
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Ukuran Saringan
Gradasi Gabungan ( mm
GK. Max. ) GK. Min.
Perkiraan Aspal ( Pb ) :
CA = 52.08 FA = 39.76 FF = 8.16
Pb = 0,035 x CA + 0,045 x FA + 0,18 x FF + 1 = 6.08%
PT. Karya Murni Perkasa Pb = 6.0%
AC - WC ( Gradasi Halus )
% Aspal 5.0 5.5 6.0 6.5 7.0 Keterangan
Total Campuran 1200
Aspal 60.00 66.00 72.00 78.00 84.00
Total Aggregate 1140.00 1134.00 1128.00 1122.00 1116.00
KOMULATIF
PRD ( Refusal )
% Aspal 5.5 6.0 6.5 Keterangan
Total Campuran 2750
Aspal 151.25 165.00 178.75
Total Aggregate 2598.75 2585.00 2571.25
KOMULATIF
AC - BC ( Gradasi Kasar )
% Aspal 4.5 5.0 5.5 6.0 6.5 Keterangan
Total Campuran 1200
Aspal 54.00 60.00 66.00 72.00 78.00
Total Aggregate 1146.00 1140.00 1134.00 1128.00 1122.00
KOMULATIF
PRD ( Refusal )
% Aspal 5.0 5.5 6.0 Keterangan
Total Campuran 2750
Aspal 137.5 151.25 165
Total Aggregate 2612.5 2598.75 2585
Coarse Aggregate 3/4" 24.00% 627.00 623.70 620.40
Medium Aggregate 47.10% 1230.49 1224.01 1217.54
Abu Batu 19.00% 496.38 493.76 491.15
Pasir 8.00% 209.00 207.90 206.80
Semen 1.90% 49.64 49.38 49.12
Total 100.00% 2612.50 2598.75 2585.00
KOMULATIF