You are on page 1of 45

PRECIOS UNITARIOS RAMPA JNG ABRIL 2012

PU ABRIL PU MARZO VARIACION


DESCRIPCION
2012 U.S.$ 2012 U.S.$ %
RAMPA 4.5 M X 4.2 M CON EQUIPOS 581.68 580.43 0.22%
RAMPA 4.5 M X 4.2 M ALTA DIFICULTAD CON EQUIPOS 598.96 597.53 0.24%
PRECORTE RAMPA 4.5 M X 4.2 M CON EQUIPOS 573.39 572.24 0.20%
CRUCERO 4.5 M X 4.2 M CON EQUIPOS 543.02 541.87 0.21%
RAMPA 3.50 M X 3.50 M CON EQUIPOS 486.86 485.81 0.22%
CRUCERO 3.50 M X 3.50 M CON EQUIPOS 471.89 470.84 0.22%
RAMPA 3.0 M X 3.0 M CON EQUIPO 423.51 422.39 0.26%
CRUCERO 3.0 M X 3.0 M CON EQUIPO 413.23 412.11 0.27%
CRUCERO 2.0 M X 2.0 M CON EQUIPO(REFUGIO) 331.01 330.21 0.24%
INSTALACION PERNO HELICOIDAL DE 6' CEMBOL 23.26 23.21 0.22%
INSTALACION PERNO HELICOIDAL DE 8' CEMBOL 29.26 29.19 0.21%
PERNO HIDRABOLT 5FTS CON EQUIPO 24.02 24.00 0.08%
PERNO HIDRABOLT 7FTS CON EQUIPO 24.77 24.75 0.08%
INSTALACION DE MALLA ELECTROSOLDADA 10.21 10.19 0.17%
SHOTCRETE 1" 0 DRAMIX 18.90 18.81 0.51%
SHOTCRETE 1" 10 DRAMIX 20.35 20.25 0.47%
SHOTCRETE 1" 20 DRAMIX 21.79 21.69 0.44%
SHOTCRETE 1" 30 DRAMIX 23.23 23.14 0.41%
SHOTCRETE 1" 40 DRAMIX 24.68 24.58 0.39%
SHOTCRETE 2" 0 DRAMIX 38.07 37.88 0.51%
SHOTCRETE 2" 10 DRAMIX 40.99 40.80 0.47%
SHOTCRETE 2" 20 DRAMIX 43.91 43.72 0.44%
SHOTCRETE 2" 30 DRAMIX 46.83 46.64 0.41%
SHOTCRETE 2" 40 DRAMIX 49.75 49.56 0.39%
SHOTCRETE 2" 0 DRAMIX 57.03 56.74 0.51%
SHOTCRETE 2" 10 DRAMIX 61.41 61.12 0.47%
SHOTCRETE 2" 20 DRAMIX 65.80 65.51 0.44%
SHOTCRETE 2" 30 DRAMIX 70.18 69.89 0.41%
SHOTCRETE 2" 40 DRAMIX 74.56 74.27 0.39%
ESTRUCTURA DE COSTOS MANO DE OBRA TODO COSTO
TIPO DE CAMBIO: 2.654
CATEG CATEGORIA UNIDAD JORNAL S/. JORNAL U.S.$ L.SOCIALES TOTAL
OPERADOR 1-A MAESTRO JUMBERO S/.XJORNAL 84.00 31.65 32.60 64.25
MAESTRO 3 MAESTRO SOSTENIMIENTO S/.XJORNAL 57.00 21.48 22.12 43.60
MAESTRO 2 MAESTRO PERFORISTA/WINCHERO/PALERO S/.XJORNAL 60.00 22.61 23.28 45.89
AYUDANTE 1 AYUDANTE 1 S/.XJORNAL 54.00 20.35 20.95 41.30
OPERADOR 2-A ESCOOPERO/ROBOT LANZADOR CONCRETO S/.XJORNAL 72.00 27.13 27.94 55.07

FACTOR INCREMENTO REGIMEN LABORAL 1.00

GASTOS GENERALES %
CONTINGENCIAS % 5%
UTILIDAD % 10%
LISTADO DE PRECIOS DE MATERIALES
PRECIO ABR PRECIO ABR
TIPO DESCRIPCION UNIDAD
2012 S/. 2012 U.S.$
Aceite de Perforación Almo U.S.$/Gln 9.16
Alambre # 16 U.S.$/Kg 1.22
Alcayata triple de 1/2" para tuberia de 2" U.S.$/Pza 3.36
Grampa de Fe corrugado 3/8" U.S.$/Pza 1.21
Malla Electrosoldad de 4"x4" U.S.$/Mt2 3.18
Adaptador de Perno U.S.$/Pza 88.00
Perno helicohidal de 6'+tuerca+placa U.S.$/Pza 8.12
Perno helicohidal de 8'+tuerca+placa U.S.$/Pza 9.54
Perno Hydrabolt 6',tuerca,placa U.S.$/Pza 12.82
Perno Hydrabolt 7',tuerca,placa U.S.$/Pza 13.92
Cartucho Cemento U.S.$/Pza 0.22
Resina Unidad 0.75
manga ventilacion 30" U.S.$/Mt 4.82
Petroleo S./Gln 13.01 4.90
Cemento S./Bls 30.32 11.42
MATERIALES Acelerante U.S.$/Kgs 0.82
Dramix U.S.$/Kgs 1.95
Calibradores U.S.$/Pza 0.15
Tuberia de polietileno de 2" AGUA U.S.$/Pza 2.34
Tuberia de polietileno de 4" AIRE U.S.$/Pza 7.06
Tubo PVC ( Recorte Voladura) U.S.$/Pza 0.41
Manguera de Aire 1" U.S.$/Mts 2.70
Manguera de Agua 1/2" U.S.$/Mts 1.33
Soldadura Supercito 1 /8" U.S.$/Kg 3.91
Sacos de polipropileno (50 Kgs/saco) U.S.$/Unid 0.38
Fierro corrugado 3/4" x 8" (cancamo) U.S.$/Pza 5.67
Varilla 1/2" x 9 U.S.$/Pza 9.38
Varilla 3/4" x9 U.S.$/Pza 21.28
Varilla 5/8" x9 U.S.$/Pza 14.55
Dramix U.S.$/Kg 1.95
Calibradores U.S.$/Pza 0.15
Barra de extension porta broca conica 2' U.S.$/Pza 60.50
Barra de extension porta broca conica 4', 7876-6112-11 U.S.$/Pza 68.20
Barra de extension porta broca conica 6', 7876-6118-11 U.S.$/Pza 94.60
Barra de extension porta broca conica 8', 7876-1124-11 U.S.$/Pza 103.40
Broca de 40 mm U.S.$/Pza 25.30
Broca de 38 mm U.S.$/Pza 24.75
Barra MF T38 X H35 X R32 X 14", 7324-6543-20 U.S.$/Pza 581.90
ACEROS DE Broca boton R32 X 1-3/4", 7733-5245-S45 U.S.$/Pza 93.50
PERFORACION Shank adapter HLX5 X T38, 7304-7585-01 U.S.$/Pza 366.30
Aco Top Cen R38 55,7994-3655 (COPLAS) U.S.$/Pza 71.50
Broca escar. 4" GRADOS 12,7721-4802-S45 (RIMADORA) U.S.$/Pza 233.20
Adaptador PIL R32 40 12 GRADOS,7821-3440 (ADAPTA U.S.$/Pza 271.70
Shank adapter hembra (BOLTER) U.S.$/Pza 341.00
Barra de extension R32 H25 (BOLTER) U.S.$/Pza 174.90
Broca boton R25 x 37 mm (BOLTER) U.S.$/Pza 80.30
Afiladora de Brocas U.S.$/Pza 1600.00
Cordon detonante 5p (pentacord)(caja x 1500) U.S.$/Mts 0.23
Igniter cord U.S.$/Pza 0.41
Guia ensamblada 2.4 mts - carmex (300) U.S.$/Pza 0.76
Emulex 45% 1 1/8" x 12" (128) U.S.$/Cart 0.52
Emulex 45% 1 1/8" x 12" (128) (25 kGS) U.S.$/Kgs 2.66
Exsadit 45% 7/8" x 7" (328) U.S.$/Cart 0.17
Exsadit 45% 7/8" x 7" (328) (25 Kgs) U.S.$/Kgs 2.23
EXPLOSIVOS Y Exsablock 7/8" x 7" (276) U.S.$/Cart 0.16
ACCESORIOS
Exsablock 7/8" x 7" (276) (20 Kgs) U.S.$/Kgs 2.21
Exsanel 2.1 mts U.S.$/Pza 1.15
Exsanel 3.0 mts N 288 (200) U.S.$/Pza 1.32
Exsanel 4.8 mts N 180 (200) U.S.$/Pza 1.58
Fulminante electrico de 4 m U.S.$/Pza 4.54
Emulnor 1000 1" x 7" (264) U.S.$/Kgs 1.79
Emulnor 3000 1 1/8" x 12" (114) U.S.$/Kgs 1.96
MADERA Tabla 8" x 2" x 4' S./Pza 7.97 3.00
Botas U.S.$/Pza 19.57
Chaleco de malla con cinta reflectiva U.S.$/Pza 7.34
Casco tipo Sombrero con orejera U.S.$/Pza 51.47
Faja Ergonomica de proteccion lumbar U.S.$/Pza 7.11
Casco tipo Sombrero U.S.$/Pza 11.32
Barbiquejo U.S.$/Pza 0.68
Respirador U.S.$/Pza 23.13
Filtro U.S.$/Pza 3.18
Cartucho U.S.$/Pza 4.52
IMPLEMENTOS DE Retenedor U.S.$/Pza 2.63
SEGURIDAD Guantes de Cuero U.S.$/Pza 3.30
Correa Portalampara U.S.$/Pza 3.63
Tapon de oido U.S.$/Pza 0.63
Mameluco U.S.$/Pza 18.67
Pantalon de Jebe U.S.$/Pza 12.56
Casaca de jebe U.S.$/Pza 12.56
Lampara U.S.$/Pza 17.00
Anteojo U.S.$/Pza 5.20
Cordon Sujetador U.S.$/Pza 2.28
Tafilete U.S.$/Pza 4.21
Corvina U.S.$/Pza 51.70
Palana U.S.$/Pza 9.39
Pico U.S.$/Pza 10.90
Comba de 6 Lbs U.S.$/Pza 7.83
HERRAMIENTAS
Llave Stilson de 8" U.S.$/Pza 4.79
Llave Francesa de 8" U.S.$/Pza 5.90
Azuela de 3 Lbs U.S.$/Pza 9.24
Chotana U.S.$/Pza 11.18
LEYES SOCIALES DE CTTA A TODO COSTO
T Anual : 365.00
41.01 D.NORMALES 273.00 22.75
DOMINGOS 52.00
Basico 31.33 1,500.00 DESC.MEDICO 4.00
Asig. Fam. 2.000 60.00 FERIADOS 10.00
33.33 1560.00 VACAC. 26.00
INGRESO: MENSUAL ANUAL
Obreros Empleados Obreros Empleados Obreros Empleados Conceptos
Cálculo de Leyes Sociales
% % Obreros
Mensual: 758.26 1,560.00 9,099.09 18,720.00

CTS 98.56 0.00 1,182.72 0.00 13.00% 14/12/12*365/273


1 VACACIONES 83.33 0.00 999.96 0.00 10.99% (30/273)
2 GRATIFICACIONES 166.65 0.00 1,999.80 0.00 21.98% (60/273)
3 DOMINGOS & FERIADOS-DESC.MEDICO 172.21 0.00 2,066.52 0.00 22.71% (62/273)
DESCANSO MEDICO 11.11 0.00 133.32 0.00 1.47% (4/273)

ESSALUD 68.24 0.00 818.92 0.00 9.00% A


JUBILACION ANTICIPADA 15.17 0.00 181.98 0.00 2.00% B
SCTR-SALUD 7.36 0.00 88.26 0.00 0.97% C
SCTR-PENSIONES(interior Mina) 65.97 0.00 791.62 0.00 8.70% D
VIDA LEY 3.26 0.00 39.13 0.00 0.43% E
APORTES REM. PRINCIPAL 21.10%

ESSALUD 7.50 0.00 89.99 0.00 0.99% 1*A


IES 1.67 0.00 20.00 0.00 0.22% 1*B
SCTR-SALUD 0.81 0.00 9.70 0.00 0.11% 1*C
SCTR-PENSIONES 7.25 0.00 86.99 0.00 0.96% 1*D
VIDA LEY 0.36 0.00 4.30 0.00 0.05% 1*E
IMPUESTOS VACACIONES 2.32%

ESSALUD 15.00 0.00 179.98 0.00 1.98% 2*A


IES 3.33 0.00 40.00 0.00 0.44% 2*B
SCTR-SALUD 1.62 0.00 19.40 0.00 0.21% 2*C
SCTR-PENSIONES 14.50 0.00 173.98 0.00 1.91% 2*D
VIDA LEY 0.72 0.00 8.60 0.00 0.09% 2*E
IMPUESTO GRATIFICACIONES 4.64%

ESSALUD 15.50 0.00 185.98 0.00 2.04% 3*A


IES 3.44 0.00 41.33 0.00 0.45% 3*B
SCTR-SALUD 1.67 0.00 20.04 0.00 0.22% 3*C
SCTR-PENSIONES 14.98 0.00 179.78 0.00 1.98% 3*D
VIDA LEY 0.74 0.00 8.89 0.00 0.10% 3*E
IMPUESTO DOM Y FER.DES.MED. 4.79%

TOTAL: 1,539.21 1,560.00 18,470.28 18,720.00 102.989%

DIAS UTILES DOMINGOS FERIADOS DES.MEDICVACACIONES


ENERO 0 5 0 26
FEBRERO 24 4 0
MARZO 27 4 0
ABRIL 23 5 2
MAYO 26 4 1
JUNIO 25 4 1
JULIO 24 5 2
AGOSTO 26 4 1
SEPTIEMBRE 26 4 0
OCTUBRE 25 5 1
NOVIEMBRE 25 4 1
DICIEMBRE 22 4 1 4
273 52 10 4 26
ACUMULADO 273 325 335 339 365
TIPO DE CAMBIO (Venta): 2.654

EQUIPOS UNIDAD COSTO PROPIED COSTO OPERACIÓ COSTO TOTAL


U.S.$/HR U.S.$/HR U.S.$/HR
JUMBO ELECTROHIDR DE 1 BRAZO (*) $/HR 86.87 23.13 110.00
SCOOP DIESEL 4 YD3 $/HR 45.79 17.21 63.00
BOMBA 10 H.P. $/HR 1.06 3 4.06
VENTILADOR 20000 CFM $/HR 1.65 0.7 2.35
ALQUILER DE PERFORADORA U.S.$/Pie 0.24

CONTINGENCIAS % 5%
GASTOS GENERALES % 0%
UTILIDAD % 10%
FACTOR DE EFICIENCIA EN COLOCADO CUADROS MADERA 100%

COSTO HORARIO DE EQUIPOS U.S.$/HR


WINCHES ELECTRICOS DE ARRASTRE JOY DE 20 3.65
PALA NEUMATICA 12B 6.31
SHOTCRETERA ALIVA 5.84
LOCOMOTORA 3.5 TN A BATERIA U.S.$/Mes 1,400.00
LOCOMOTORA 5.5 TN A BATERIA U.S.$/Mes 2,200.00
LOCOMOTORA TROLLEY DE 5.5 TN U.S.$/Mes 3,400.00
LOCOMOTORA TROLLEY DE 10 TN U.S.$/Mes 8,000.00
CARROS MINEROS GRAMBY 90.82
CARROS MINEROS U35 47.03
CARROS MINEROS GRAMBY 180.00
MEZCLADORA U.S.$/Hr 4.44 Consumo Unidad
SCOOP 2.2 Yd3 $/Hr 50.00 3.00 Glns/Hr
SCOOP 1.5 Yd3 $/Hr 40.00 2.00 Glns/Hr
SCOOP 3.5 Yd3 $/Hr 63.00 3.50 Glns/Hr
JUMBO ROCKET BOOMER $/Hr 90.00 1.50 Glns/Hr
VOLQUETE BAJO PERFIL $/Hr 50.00 4.00 Glns/Hr
PERFORADORA JACK LEG (U.S.$/Ft) $/Hr 0.10

COSTO DE TRANSPORTE DE MADERA


RUBRO Und CONSUMO P.UNIT COSTO TOTAL COSTO UNIT OBSERVACION
$/pie
MADERA Pie2-Mina-mes 530,984.18 0.00 0.00 0.00
PERSONAL Glb 1.00 19,175.25 19,175.25 0.04
GASTOS ADMINISTRATIVOS % 0.07 0.00
MANTENIMIENTO CALESAS Und 39.00 23.00 897.00 0.00 Entregada x CMHSA
COSTO LOCOMOTORA SERVICIOS Glb 1.00 1,196.00 1,196.00 0.00
CAMION DYNA Und 1.00 0.00 0.00 0.00 Transporte Madera Boca a Interior Mina x Rampa RNG
TOTAL 0.04
NOTA: 2,236.62

Factor de correccion longitud madera (pies a mts) 0.98


COSTOS FIJOS MENSUALES
L.SOC. OBR. 102.99% L.SOC. EMP. 65.91% T.CAMBIO 2.654

SUELDO
DESCRIPCION CANT L.SOCIALES TOTAL S/. TOTAL U.S.$ SUB-TOTAL TOTAL US$
BASICO
U.S.$
Ing. Residente 0.00 7,000.00 4,613.84 11,613.84 4,375.98 0.00 0.00
Ing. Asistente Residente 1.00 6,000.00 3,954.72 9,954.72 3,750.84 3,750.84 3,750.84
Ingeniero de Seguridad 0.00 6,000.00 3,954.72 9,954.72 3,750.84 0.00 0.00
Ing. Asistente Seguridad 1.00 4,500.00 2,966.04 7,466.04 2,813.13 2,813.13 2,813.13
Ingeniero Jefe de Guardia 2.00 5,000.00 3,295.60 8,295.60 3,125.70 6,251.39 6,251.39
Administrador 0.00 3,000.00 1,977.36 4,977.36 1,875.42 0.00 0.00
Asistenta Social 0.00 2,000.00 1,318.24 3,318.24 1,250.28 0.00 0.00
Auxiliar Administrativo 1.00 1,000.00 659.12 1,659.12 625.14 625.14 625.14
Auxiliar Almacen 1.00 1,470.00 968.91 2,438.91 918.95 918.95 918.95

Capataz 3.00 2,640.00 1,740.08 4,380.08 1,650.37 4,951.10 4,951.10


Bodeguero/Afilador /Lamparero 3.00 1,380.00 909.59 2,289.59 862.69 2,588.08 2,588.08
Inspector Seguridad 1.00 1,530.00 1,008.45 2,538.45 956.46 956.46 956.46
Herrero 0.00 1,500.00 988.68 2,488.68 937.71 0.00 0.00
Lamparero 1.00 1,200.00 790.94 1,990.94 750.17 750.17 750.17
TOTAL COSTO FIJO 23,605.26

GASTOS GENERALES
MOVILIDAD Y OTROS 1.00
Camioncito Servicios 0.50 6,174.46 3,087.23
Camioneta Operaciones 0.50 6,174.46 3,087.23
Precio/Dia Dia Mes Sistema
Alimentacion supervisores 6 16.00 30.00 0.67 120.57 723.44
Alimentacion obreros 37 16.00 30.00 0.67 120.57 4,461.19
Examen médico 43 190.00 6.00 2.00 23.86 1,026.12
Pasajes Obreros (Parcoy - Trujillo
37 250.00 1.00 0.67 62.80 2,323.54
- Parcoy)
Pasajes Supervisores (Lima - Mina 6 249.50 2.00 1.00 188.02 1,128.11

IMPLEMENTOS SEGURIDAD 1.00


Supervisores y otros 13.00 37.13 482.70

GASTOS GENERALES PROPIAMENTE


Gastos Generales Lima 4,000.00
Gastos Generales operación mina 1,000.00
SUB TOTAL US$ 21,319.56
TOTAL GENERAL US$ 44,924.82

COSTO ACTUAL CAMIONETA (Inlcuido Petroleo) Dias trabajados


U.S.$/Día Cantidad U.S.$/Mes 30.00 p' vehi
Camioneta $112.08 1.00 3,362.47 S/. U.S.$
Choferes $30.01 3.00 2,700.60 48.00 31.64 79.64 30.01
EPPS 1.86 3.00 111.39 Petroleo 180 4.90 882.37 29.41
TOTAL MES 6,174.46
RAMPA 4.5 M X 4.2 M CON EQUIPOS

GRADIENTE: 5/1000 N° de Taladros: 51.00 Avance/Disp. 3.00 MT


Factor Incidencia 12%
FACTOR
MANO DE OBRA UNIDAD CANTIDAD FACT MO PU SUB TOTAL U.S.$/MT
INCIDENCIA
OPERADOR DE JUMBO Hom/Disp 1.00 1.00 1.00 64.25 64.25
AYUDANTE OPER.JUMBO Hom/Disp 1.00 1.00 1.00 41.30 41.30
OPERADOR SCOOPTRAM Hom/Disp 1.00 1.00 1.00 55.07 55.07
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 1.00 1.00 55.07 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 1.00 1.00 45.89 137.67
BOMBERO Hom/Disp 1.00 1.00 1.00 41.30 41.30
SERVICIOS AUXILIARES Hom/Disp 1.00 1.00 1.00 41.30 41.30
SUB-TOTAL 380.89 127.14

MATERIALES
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 200.47 2,500 0.08 581.90 15.58
BROCAS DE 45 MM MT/DISP 189.34 200 0.95 93.50 29.54
SHANK ADAPTER MT/DISP 200.47 3,500 0.06 366.30 7.00
AFILADOR BROCAS MT/DISP 189.34 100,000 0.00 1,600.00 1.01
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 11.14 200 0.06 233.20 4.33
ADAPTADOR DE RIMADORA MT/DISP 11.14 200 0.06 271.70 5.05
TUBO PVC (Voladura recorte) PZAS/DISP 10.00 0.41 1.37
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS GLB 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.49
PETROLEO(Para Scooptram ) 3.50 3.50 4.90 20.04
SUB-TOTAL 93.64

IMPLEMENTOS SEGURIDAD
COSTO UNIT COSTO
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
U.S.$/Pers U.S.$
IMPLEMENTOS SEGURIDAD Unidad 8.00 2.69 21.53 7.19

VOLADURA
CANTIDAD/ CANTIDAD COSTO
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS U.S.$/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 20.00 11.30 226.00 44.14 2.66 39.19
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 11.00 12.27 135.00 26.37 2.66 23.41
EXADIT 45% 7/8" X 7" Corona TALADROS 17.00 6.00 102.00 7.77 2.23 5.79
CORDON DETONANTE 5P MTS 45.00 0.23 3.45
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.51
EXANEL 4.8 Mts PZAS 48.00 1.58 25.31
SUB-TOTAL 97.66

EQUIPOS
COSTO COSTO COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. TOTAL U.S.$/MT
U.S.$/HR U.S.$/HR $/HR U.S.$
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petr HORAS 2.50 110.00 275.00
SCOOP DIESEL 4 YD3 HORAS 3.50 63.00 220.50
CAMION DE BAJO PERFIL (2 CAMIONES X 2Hrsx HORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 50 HP HORAS 0.00 0.00
BOMBA DE 10 HP HORAS 5.00 1.06 3.00 4.06 20.30
PERFORADORA P.P 12.00 0.24 2.88
SUB-TOTAL 539.83 180.19

TOTAL COSTOS DIRECTOS 505.81

CONTINGENCIA 5% 25.29
UTILIDAD 10% 50.58
SUB TOTAL COSTOS INDIRECTOS 75.87

TOTAL COSTOS U.S.$/Mt (Con equipos) 581.68

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO AL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EXADIT
EMULEX
EMULEX 45% 45%
ESTAND 45% 1
CICLO UNIDAD UNIDAD 1 1/8"X12 7/8"X7"
AR 1/8"X12
Cebo
DESCRIPCION Arrastre
Corona
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 3.00
LONG BARRA DE EXTEN PIES 14.00 Arranque 3.00 39.00 0.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 4.00 44.00 0.00
LONG PERFORACION MT 3.71 2da Ayuda Arranque 4.00 44.00 0.00
EFIC.AVANCE % 81% 3ra Ayuda Arranque 4.00 44.00 0.00
LONG DE AVANCE EFECTIVA MT 3.00 Ayudas de Alzas 5.00 55.00 0.00
DURACION GUARDIA H 11 Ayudas de Arrastre 4.00 0.00 44.00
GUARDIAS/DIA GDA/D 2 Contorno 4.00 0.00 24.00 0.00
PRODUCCION/DIA M/D 11.98 Contorno de Recorte 13.00 0.00 78.00 0.00
Arrastres 7.00 0.00 91.00
VOLUMEN POR DISPARO LABOR TOTAL 51.00 226.00 102.00 135.00
ANCHO LABOR MT 4.5 TOTAL KGS 51.00 44.14 7.77 26.37
ALTO LABOR MT 4.2
LONGITUD MT 3.00 PESO Kgs/Cartucho 0.20 0.08 0.20
SOBREROTURA % 6%
VOLUMEN TOTAL M3 60.13 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 159.36 Densidad de Carga Kgs/mt 26.13
Factor de Carga Kgs/Ton 0.49
RAMPA 4.5 M X 4.2 M ALTA DIFICULTAD CON EQUIPOS

N° de
GRADIENTE: 5/1000 48.00 Avance/Disp. 2.64 MT
Taladros:

FACTOR
MANO DE OBRA UNIDAD CANTIDAD FACT MO PU SUB TOTAL U.S.$/MT
INCIDENCIA
OPERADOR DE JUMBO Hom/Disp 1.00 1.00 1.00 64.25 64.25 0.00
AYUDANTE OPER.JUMBO Hom/Disp 1.00 1.00 1.00 41.30 41.30
OPERADOR SCOOPTRAM Hom/Disp 1.00 1.00 1.00 55.07 55.07 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 1.00 1.00 55.07 0.00 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 1.00 1.00 45.89 137.67 0.00
BOMBERO Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
SERVICIOS AUXILIARES Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
SUB-TOTAL 380.89 144.21
MATERIALES CMHSA
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 162.29 2,500 0.06 581.90 14.30
BROCAS DE 45 MM MT/DISP 152.74 200 0.76 93.50 27.04
SHANK ADAPTER MT/DISP 162.29 3,500 0.05 366.30 6.43
AFILADOR BROCAS MT/DISP 152.74 100,000 0.00 1,600.00 0.93
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 9.55 200 0.05 233.20 4.21
ADAPTADOR DE RIMADORA MT/DISP 9.55 200 0.05 271.70 4.91
TUBO PVC (Voladura recorte) PZAS/DISP 10.00 0.41 1.55
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS 1.21 0.46
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 5.09
PETROLEO(Para Scooptram ) 3.50 3.50 4.90 22.74
SUB-TOTAL 87.65

IMPLEMENTOS SEGURIDAD
COSTO UNIT COSTO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
U.S.$/Pers $
IMPLEMENTOS SEGURIDAD Unidad 8.00 2.69 21.53 8.15

VOLADURA
CANTIDAD/ CANTIDAD COSTO U.S.
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS $/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 18.00 10.33 186.00 36.33 2.66 36.59
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 11.00 11.27 124.00 24.22 2.66 24.39
EXABLOCK 7/8"X 7" Corona TALADROS 16.00 5.00 80.00 5.80 2.21 4.85
CORDON DETONANTE 5P MTS 45.00 0.23 3.92
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.58
EXANEL 4.8 Mts PZAS 45.00 1.58 26.92
SUB-TOTAL 97.24

EQUIPOS
COSTO COSTO
COSTO TOTAL COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN U.S.$/MT
U.S.$/HR TOTAL U.S.$
U.S.$/HR U.S.$/HR
JUMBO ELECTROHIDR DE 1 BRAZO (*) 2.00 HORAS 2.00 110.00 220.00
SCOOP DIESEL 4 YD3 3.50 HORAS 3.50 63.00 220.50
CAMION DE BAJO PERFIL (2 CAMIONES X 2HrsxDisparo) HORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP 3.00 HORAS 5.00 1.06 3.00 4.06 20.30
PERFORADORA HORAS 12.00 0.24 2.88
SUB-TOTAL 484.83 183.57

TOTAL COSTOS DIRECTOS 520.83

CONTINGENCIAS 5% 26.04
UTILIDAD 10% 52.08
SUB TOTAL COSTOS INDIRECTOS 78.12

TOTAL COSTOS (Sin equipos) 389.11


TOTAL COSTOS U.S.$/Mt (Con equipos) 598.96

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO AL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS

EXABLOCK EMULEX 45%


ESTAND EMULEX 45%
CICLO UNIDAD UNIDAD 7/8"X7" 1 1/8"X12
AR 1 1/8"X12 Cebo
Corona Arrastre
DESCRIPCION
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 3.00
LONG BARRA DE EXTEN PIES 12.00 Arranque 3.00 36.00 0.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 3.00 30.00 0.00
LONG PERFORACION MT 3.18 2da Ayuda Arranque 4.00 40.00 0.00
EFIC.AVANCE % 83% 3ra Ayuda Arranque 4.00 40.00 0.00
LONG DE AVANCE EFECTIVA MT 2.64 Ayudas de Alzas 4.00 40.00 0.00
DURACION GUARDIA H 11 Ayudas de Arrastre 4.00 0.00 40.00
GUARDIAS/DIA GDA/D 2 Contorno 4.00 0.00 20.00 0.00
PRODUCCION/DIA M/D 10.56 Contorno de Recorte 12.00 0.00 60.00 0.00
Arrastres 7.00 0.00 84.00
VOLUMEN POR DISPARO LABOR TOTAL 48.00 186.00 80.00 124.00
ANCHO LABOR MT 4.5 TOTAL KGS 48.00 36.33 5.80 24.22
ALTO LABOR MT 4.2
LONGITUD MT 2.64 PESO Kgs/Cartucho 0.20 0.07 0.20
SOBREROTURA % 13%
VOLUMEN TOTAL M3 56.52 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 149.77 Densidad de Carga Kgs/mt 25.12
Factor de Carga Kgs/Ton 0.44
PRECORTE RAMPA 4.5 M X 4.2 M CON EQUIPOS
(ZONA1: Rampa 940: TUNEL BALCON)
GRADIENTE: 5/1000 N° de Taladros: 54.00 Avance/Disp. 2.70 MT

FACTOR FACT
MANO DE OBRA UNIDAD CANTIDAD PU SUB TOTAL U.S.$/MT
INCIDENCIA MO
OPERADOR DE JUMBO Hom/Disp 1.00 1.00 1.00 64.25 64.25 0.00
AYUDANTE OPER.JUMBO Hom/Disp 1.00 1.00 1.00 45.89 45.89
OPERADOR SCOOPTRAM Hom/Disp 1.00 1.00 1.00 55.07 55.07 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 1.00 1.00 55.07 0.00 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 1.00 1.00 45.89 137.67 0.00
BOMBERO Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
SERVICIOS AUXILIARES Hom/Disp 2.00 1.00 1.00 41.30 82.60 0.00
SUB-TOTAL 426.78 157.79

MATERIALES CMHSA
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 178.20 2,500 0.07 581.90 15.33
BROCAS DE 45 MM MT/DISP 171.83 200 0.86 93.50 29.70
SHANK ADAPTER MT/DISP 178.20 3,500 0.05 366.30 6.90
AFILADOR BROCAS MT/DISP 171.83 100,000 0.00 1,600.00 1.02
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 6.36 200 0.03 233.20 2.74
ADAPTADOR DE RIMADORA MT/DISP 6.36 200 0.03 271.70 3.20
TUBO PVC (Voladura recorte) PZAS/DISP 10.00 0.41 1.52
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS 1.21 0.45
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 0.00 3.36 0.00

SUB-TOTAL 60.85

IMPLEMENTOS SEGURIDAD
COSTO UNIT
DESCRIPCION UNIDAD MTS/DISP COSTO U.S.$ U.S.$/MT
U.S.$/Pers
IMPLEMENTOS SEGURIDAD Unidad 9.00 2.69 24.22 8.95

VOLADURA
CANTIDAD/ CANTIDAD COSTO U.S.
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS $/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 15.00 10.67 160.00 31.25 2.66 30.73
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 9.00 12.11 109.00 21.29 2.66 20.94
EXSABLOCK 7/8"X7" Corona TALADROS 15.00 6.00 90.00 6.52 2.21 5.33
CORDON DETONANTE 5P MTS 45.00 0.23 3.83
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.56
EXSANEL 4.8 Mts PZAS 52.00 1.58 30.38
SUB-TOTAL 91.76

EQUIPOS
COSTO COSTO COSTO
COSTO TOTAL
DESCRIPCION UNIDAD HRS/DISP PROPIEDA OPERACIÓN TOTAL U.S. U.S.$/MT
U.S.$
D U.S.$/HR U.S.$/HR $/HR
JUMBO ELECTROHIDR DE 1 BRAZO (*) 2.00 HORAS 2.00 110.00 220.00
SCOOP DIESEL 4 YD3 3.50 HORAS 3.50 63.00 220.50
CAMION DE BAJO PERFIL (2 CAMIONES X 2HrsxDiHORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM 9.00 HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP 5.00 HORAS 5.00 1.06 3.00 4.06 20.30
PERFORADORA HORAS 12.00 0.24 2.88
SUB-TOTAL 484.83 179.25

TOTAL COSTOS DIRECTOS 498.60

CONTINGENCIA 5% 24.93
UTILIDAD 10% 49.86
SUB TOTAL COSTOS INDIRECTOS 74.79

TOTAL COSTOS U.S.$/Mt (Sin equipos) 370.57


TOTAL COSTOS U.S.$/Mt (Con equipos) 573.39

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO AL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EMULEX 45% EXABLOCK EMULEX 45%
ESTAND
CICLO UNIDAD DESCRIPCION UNIDAD 1 1/8"X12 7/8"X7" 1 1/8"X12
AR
Cebo Corona Arrastre
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 2.00
LONG BARRA DE EXTEN PIES 12.00 Arranque 2.00 26.00 0.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 2.00 22.00 0.00
LONG PERFORACION MT 3.18 2da Ayuda Arranque 2.00 22.00 0.00
EFIC.AVANCE % 85% 3ra Ayuda Arranque 4.00 44.00 0.00
LONG DE PERF EFECTIVA MT 2.70 Ayuda Cuadrador 2.00 22.00 0.00
DURACION GUARDIA H 11 Ayudas de Alzas 3.00 24.00 0.00
GUARDIAS/DIA GDA/D 2 Ayudas de Arrastre 4.00 0.00 44.00
PRODUCCION/DIA M/D 10.82 Contorno de Precorte 15.00 0.00 90.00 0.00
Arrastres 5.00 0.00 65.00
Alivio de contornos 13.00
VOLUMEN POR DISPARO LABOR TOTAL 54.00 160.00 90.00 109.00
ANCHO LABOR MT 4.5 TOTAL KGS 54.00 31.25 6.52 21.29
ALTO LABOR MT 4.2
LONGITUD MT 2.70 PESO Kgs/Cartucho 0.20 0.07 0.20
SOBREROTURA % 13%
VOLUMEN TOTAL M3 57.88 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 153.38 Densidad de Carga Kgs/mt 21.84
Factor de Carga Kgs/Ton 0.39
CRUCERO 4.5 M X 4.2 M CON EQUIPOS

GRADIENTE: 5/1000 N° de Taladros: 48.00 Avance/Disp. 3.00 MT


Factor Incidencia 12%
FACTOR
MANO DE OBRA UNIDAD CANTIDAD FACT MO PU SUB TOTAL U.S.$/MT
INCIDENCIA
OPERADOR DE JUMBO Hom/Disp 1.00 1.00 1.00 64.25 64.25
AYUDANTE OPER.JUMBO Hom/Disp 1.00 1.00 1.00 41.30 41.30
OPERADOR SCOOPTRAM Hom/Disp 1.00 1.00 1.00 55.07 55.07
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 1.00 1.00 55.07 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 1.00 1.00 45.89 137.67
BOMBERO Hom/Disp 0.00 1.00 1.00 41.30 0.00
SERVICIOS AUXILIARES Hom/Disp 1.00 1.00 1.00 41.30 41.30
SUB-TOTAL 339.59 113.35

MATERIALES
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 185.62 2,500 0.07 581.90 14.42
BROCAS DE 45 MM MT/DISP 178.20 200 0.89 93.50 27.81
SHANK ADAPTER MT/DISP 185.62 3,500 0.05 366.30 6.48
AFILADOR BROCAS MT/DISP 178.20 100,000 0.00 1,600.00 0.95
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 7.42 200 0.04 233.20 2.89
ADAPTADOR DE RIMADORA MT/DISP 7.42 200 0.04 271.70 3.37
TUBO PVC (Voladura recorte) PZAS/DISP 10.00 0.41 1.37
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS GLB 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.49
PETROLEO(Para Scooptram ) 3.50 3.50 4.90 20.04
SUB-TOTAL 87.04

IMPLEMENTOS SEGURIDAD
COSTO UNIT COSTO
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
U.S.$/Pers U.S.$
IMPLEMENTOS SEGURIDAD Unidad 7.00 2.69 18.84 6.29

VOLADURA
CANTIDAD/ CANTIDAD COSTO
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS U.S.$/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 20.00 11.30 226.00 44.14 2.66 39.19
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 9.00 12.11 109.00 21.29 2.66 18.90
EXADIT 45% 7/8" X 7" Corona TALADROS 17.00 6.00 102.00 7.77 2.23 5.79
CORDON DETONANTE 5P MTS 45.00 0.23 3.45
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.51
EXANEL 4.8 Mts PZAS 46.00 1.58 24.26
SUB-TOTAL 92.10

EQUIPOS
COSTO COSTO COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. TOTAL U.S.$/MT
U.S.$/HR U.S.$/HR $/HR U.S.$
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petrole HORAS 2.50 110.00 275.00
SCOOP DIESEL 4 YD3 HORAS 3.50 63.00 220.50
CAMION DE BAJO PERFIL (2 CAMIONES X 2HrsxDis HORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 50 HP HORAS 0.00 0.00
BOMBA DE 10 HP HORAS 0.00 4.06 0.00
PERFORADORA HORAS 12.00 0.24 2.88
SUB-TOTAL 519.53 173.41

TOTAL COSTOS DIRECTOS 472.19

CONTINGENCIA 5% 23.61
UTILIDAD 10% 47.22
SUB TOTAL COSTOS INDIRECTOS 70.83

TOTAL COSTOS U.S.$/Mt (Con equipos) 543.02

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE


DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EXADIT
EMULEX
EMULEX 45% 45%
ESTAND 45% 1
CICLO UNIDAD UNIDAD 1 1/8"X12 7/8"X7"
AR 1/8"X12
Cebo
DESCRIPCION Arrastre
Corona
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 2.00
LONG BARRA DE EXTEN PIES 14.00 Arranque 3.00 39.00 0.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 4.00 44.00 0.00
LONG PERFORACION MT 3.71 2da Ayuda Arranque 4.00 44.00 0.00
EFIC.AVANCE % 81% 3ra Ayuda Arranque 4.00 44.00 0.00
LONG DE AVANCE EFECTIVA MT 3.00 Ayudas de Alzas 5.00 55.00 0.00
DURACION GUARDIA H 11 Ayudas de Arrastre 4.00 0.00 44.00
GUARDIAS/DIA GDA/D 2 Contorno 4.00 0.00 24.00 0.00
PRODUCCION/DIA M/D 11.98 Contorno de Recorte 13.00 0.00 78.00 0.00
Arrastres 5.00 0.00 65.00
VOLUMEN POR DISPARO LABOR TOTAL 48.00 226.00 102.00 109.00
ANCHO LABOR MT 4.5 TOTAL KGS 48.00 44.14 7.77 21.29
ALTO LABOR MT 4.2
LONGITUD MT 3.00 PESO Kgs/Cartucho 0.20 0.08 0.20
SOBREROTURA % 6%
VOLUMEN TOTAL M3 60.13 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 159.36 Densidad de Carga Kgs/mt 24.43
Factor de Carga Kgs/Ton 0.46
RAMPA 3.50 M X 3.50 M CON EQUIPOS

GRADIENTE: 5/1000 N° de Taladros: 44.00 Avance/Disp. 3.00 MT

FACTOR
MANO DE OBRA UNIDAD CANTIDAD FACT MO PU SUB TOTAL U.S.$/MT
INCIDENCIA
OPERADOR DE JUMBO Hom/Disp 1.00 1.00 1.00 64.25 64.25
AYUDANTE OP. JUMBO Hom/Disp 1.00 1.00 1.00 41.30 41.30
OPERADOR SCOOPTRAM Hom/Disp 1.00 1.00 1.00 55.07 55.07
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 1.00 1.00 55.07 0.00
CARGADOR/DISPARADOR Hom/Disp 2.00 1.00 1.00 45.89 91.78
BOMBERO Hom/Disp 1.00 1.00 1.00 41.30 41.30
SERVICIOS AUXILIARES Hom/Disp 1.00 1.00 1.00 41.30 41.30
SUB-TOTAL 335.00 111.82

MATERIALES
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 174.49 2,500 0.07 581.90 13.56
BROCAS DE 45 MM MT/DISP 163.35 200 0.82 93.50 25.49
SHANK ADAPTER MT/DISP 174.49 3,500 0.05 366.30 6.10
AFILADOR BROCAS MT/DISP 163.35 100,000 0.00 1,600.00 0.87
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 11.14 200 0.06 233.20 4.33
ADAPTADOR DE RIMADORA MT/DISP 11.14 200 0.06 271.70 5.05
TUBO PVC (Voaldura recorte) PZAS/DISP 10.00 0.41 1.37
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.49
PETROLEO(Para Scooptram ) 3.50 2.50 4.90 14.32
SUB-TOTAL 80.79

IMPLEMENTOS SEGURIDAD
COSTO UNIT
DESCRIPCION UNIDAD MTS/DISP COSTO U.S.$ U.S.$/MT
U.S.$/Pers
IMPLEMENTOS SEGURIDAD Unidad 7.00 2.69 18.84 6.29

VOLADURA
CANTIDAD/ CANTIDAD COSTO U.S.
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS $/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 18.00 11.44 206.00 40.23 2.66 35.72
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 9.00 12.33 111.00 21.68 2.66 19.25
EXADIT 45% 7/8" X 7" Corona TALADROS 14.00 6.00 84.00 6.40 2.23 4.77
CORDON DETONANTE 5P MTS 41.00 0.23 3.15
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.51
EXANEL 4.8 Mts PZAS 41.00 1.58 21.62
SUB-TOTAL 85.01

EQUIPOS
COSTO COSTO COSTO
COSTO TOTAL
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. U.S.$/MT
U.S.$
U.S.$/HR U.S.$/HR $/HR
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petrHORAS 2.00 110.00 220.00
SCOOP DIESEL 4 YD3 HORAS 2.50 63.00 157.50
CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrHORAS 0.00 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 50 HP HORAS 0.00 0.00
BOMBA DE 10 HP HORAS 4.00 4.06 16.24
PERFORADORA HORAS 12.00 0.24 2.88
SUB-TOTAL 417.77 139.44

TOTAL COSTOS DIRECTOS 423.36

CONTINGENCIA 5% 21.17
UTILIDAD 10% 42.34
SUB TOTAL COSTOS INDIRECTOS 63.50

TOTAL COSTOS U.S.$/Mt (Sin equipos) 486.86

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO DEL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EMULEX 45% EXADIT 45% EMULEX 45%
ESTAND
CICLO UNIDAD UNIDAD 1 1/8"X12 7/8"X7" 1 1/8"X12
AR
DESCRIPCION Cebo Corona Arrastre
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 3.00
LONG BARRA DE EXTEN PIES 14.00 Arranque 4.00 52.00 0.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 4.00 44.00 0.00
LONG PERFORACION MT 3.71 2da Ayuda Arranque 4.00 44.00 0.00
EFIC.AVANCE % 81% 3ra Ayuda Arranque 4.00 44.00 0.00
LONG DE PERF EFECTIVA MT 3.00 Ayudas de Alzas 2.00 22.00 0.00
DURACION GUARDIA H 11 Ayudas de Arrastre 3.00 0.00 33.00
GUARDIAS/DIA GDA/D 2 Contorno 9.00 0.00 54.00 0.00
PRODUCCION/DIA M/D 11.98 Contorno de Recorte 5.00 0.00 30.00 0.00
Arrastres 6.00 0.00 78.00
VOLUMEN POR DISPARO LABOR TOTAL 44.00 206.00 84.00 111.00
ANCHO LABOR MT 3.5 TOTAL KGS 44.00 40.23 6.40 21.68
ALTO LABOR MT 3.2
LONGITUD MT 3.00 PESO Kgs/Cartucho 0.20 0.08 0.20
SOBREROTURA % 6%
VOLUMEN TOTAL M3 35.64 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 94.43 Densidad de Carga Kgs/mt 22.80
Factor de Carga Kgs/Ton 0.72
CRUCERO 3.50 M X 3.50 M CON EQUIPOS

GRADIENTE: 5/1000 N° de Taladros: 42.00 Avance/Disp. 3.00 MT

FACTOR
MANO DE OBRA UNIDAD CANTIDAD FACT MO PU SUB TOTAL U.S.$/MT
INCIDENCIA
OPERADOR DE JUMBO Hom/Disp 1.00 1.00 1.00 64.25 64.25 0.00
AYUDANTE OP. JUMBO Hom/Disp 1.00 1.00 1.00 41.30 41.30
OPERADOR SCOOPTRAM Hom/Disp 1.00 1.00 1.00 55.07 55.07 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 1.00 1.00 55.07 0.00 0.00
CARGADOR/DISPARADOR Hom/Disp 2.00 1.00 1.00 45.89 91.78 0.00
BOMBERO Hom/Disp 0.00 1.00 1.00 41.30 0.00 0.00
SERVICIOS AUXILIARES Hom/Disp 2.00 1.00 1.00 41.30 82.60 0.00
SUB-TOTAL 335.00 111.82

MATERIALES
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 167.06 2,500 0.07 581.90 12.98
BROCAS DE 45 MM MT/DISP 155.92 200 0.78 93.50 24.33
SHANK ADAPTER MT/DISP 167.06 3,500 0.05 366.30 5.84
AFILADOR BROCAS MT/DISP 155.92 100,000 0.00 1,600.00 0.83
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 11.14 200 0.06 233.20 4.33
ADAPTADOR DE RIMADORA MT/DISP 11.14 200 0.06 271.70 5.05
TUBO PVC (Voaldura recorte) PZAS/DISP 10.00 0.41 1.37
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.49
PETROLEO(Para Scooptram ) 3.50 2.50 4.90 14.32
SUB-TOTAL 78.76

IMPLEMENTOS SEGURIDAD
COSTO UNIT
DESCRIPCION UNIDAD MTS/DISP COSTO U.S.$ U.S.$/MT
U.S.$/Pers
IMPLEMENTOS SEGURIDAD Unidad 7.00 2.69 18.84 6.29

VOLADURA
CANTIDAD/ CANTIDAD COSTO U.S.
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS $/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 18.00 11.44 206.00 40.23 2.66 35.72
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 7.00 12.14 85.00 16.60 2.66 14.74
EXADIT 45% 7/8" X 7" Corona TALADROS 14.00 6.00 84.00 6.40 2.23 4.77
CORDON DETONANTE 5P MTS 41.00 0.23 3.15
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.51
EXANEL 4.8 Mts PZAS 39.00 1.58 20.57
SUB-TOTAL 79.45

EQUIPOS
COSTO COSTO COSTO
COSTO TOTAL
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. U.S.$/MT
U.S.$
U.S.$/HR U.S.$/HR $/HR
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petroleoHORAS 2.00 110.00 220.00
SCOOP DIESEL 4 YD3 HORAS 2.50 63.00 157.50
CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrsxDiHORAS 0.00 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 50 HP HORAS 0.00 0.00 0.00
B OMBA DE 10 HP HORAS 0.00 4.06 0.00
PERFORADORA HORAS 12.00 0.24 2.88
SUB-TOTAL 401.53 134.02

TOTAL COSTOS DIRECTOS 410.34

CONTINGENCIA 5% 20.52
UTILIDAD 10% 41.03
SUB TOTAL COSTOS INDIRECTOS 61.55

TOTAL COSTOS U.S.$/Mt (Sin equipos) 471.89

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO DEL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EMULEX 45% EXADIT 45% EMULEX 45%
ESTAND
CICLO UNIDAD UNIDAD 1 1/8"X12 7/8"X7" 1 1/8"X12
AR
DESCRIPCION Cebo Corona Arrastre
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 3.00
LONG BARRA DE EXTEN PIES 14.00 Arranque 4.00 52.00 0.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 4.00 44.00 0.00
LONG PERFORACION MT 3.71 2da Ayuda Arranque 4.00 44.00 0.00
EFIC.AVANCE % 81% 3ra Ayuda Arranque 4.00 44.00 0.00
LONG DE AVANCE EFECTIVA MT 3.00 Ayudas de Alzas 2.00 22.00 0.00
DURACION GUARDIA H 11 Ayudas de Arrastre 3.00 0.00 33.00
GUARDIAS/DIA GDA/D 2 Contorno 9.00 0.00 54.00 0.00
PRODUCCION/DIA M/D 11.98 Contorno de Recorte 5.00 0.00 30.00 0.00
Arrastres 4.00 0.00 52.00
VOLUMEN POR DISPARO LABOR TOTAL 42.00 206.00 84.00 85.00
ANCHO LABOR MT 3.5 TOTAL KGS 42.00 40.23 6.40 16.60
ALTO LABOR MT 3.2
LONGITUD MT 3.00 PESO Kgs/Cartucho 0.20 0.08 0.20
SOBREROTURA % 6%
VOLUMEN TOTAL M3 35.64 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 94.43 Densidad de Carga Kgs/mt 21.11
Factor de Carga Kgs/Ton 0.67
RAMPA 3.0 M X 3.0 M CON EQUIPO

N° de Taladro 38 Avance/Disp. 3.00 MT

MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT


OPERADOR DE JUMBO 1.00 Hom/Disp 1.00 1.00 1.00 64.25 64.25 0.00
AYUDANTE OP. JUMBO 1.00 Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
OPERADOR SCOOPTRAM 1.00 Hom/Disp 1.00 1.00 1.00 55.07 55.07 0.00
OPERADOR CAMION DE BAJO PERFIL 0.00 Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR 1.00 Hom/Disp 2.00 1.00 1.00 45.89 91.78 0.00
BOMBERO 0.00 Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
SERVICIOS AUXILIARES 0.00 Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
SUB-TOTAL 362.54 121.01

MATERIALES
VIDA
ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP ECONOMICA U.S.$/MT
PZAS/DISP $/PZA
MTS
BARRAS DE PERFORACION MT/DISP 122.83 2,500 0.05 581.90 9.54
BROCAS DE 45 MM MT/DISP 113.85 200 0.57 93.50 17.77
SHANK ADAPTER MT/DISP 122.83 3,500 0.04 366.30 4.29
AFILADOR BROCAS MT/DISP 113.85 100,000 0.00 1600.00 0.61
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 8.99 200 0.04 233.20 3.50
ADAPTADOR DE RIMADORA MT/DISP 8.99 200 0.04 271.70 4.08
TUBO PVC (Voladura recorte) PZAS/DISP 5.00 0.41 0.68
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06
HERRAMIENTAS 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.49
PETROLEO(Para Scooptram ) 3.50 2.50 4.90 14.32
SUB-TOTAL 64.49

IMPLEMENTOS SEGURIDAD
COSTO UNIT COSTO
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 7.50 2.69 20.18 6.74

VOLADURA
CANTIDAD/TA CANTIDAD COSTO
DESCRIPCION UNIDAD TALADROS UNIDAD KGS U.S.$/MT
LADRO PZA U.S.$/Kgs
EMULEX 45% 1 1/8" X 12" (128) TALADROS 24.00 7.25 174.00 33.98 2.66 30.17
EXADIT 45% 7/8" X 7" (328) TALADROS 11.00 5.00 55.00 4.19 2.23 3.12
CORDON DETONANTE 5P MTS 35.00 0.23 2.69
GUIA ENSAMBLADA 2.4 MTL - CARMEX (300) PZAS 2.00 0.76 0.51
EXSANEL 4.80 MTL PZAS 35.00 1.58 18.46
SUB-TOTAL 54.95

EQUIPOS
COSTO COSTO COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. TOTAL U.S. U.S.$/MT
U.S.$/HR U.S.$/HR $/HR $
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petrol HORAS 1.50 110.00 165.00
SCOOP DIESEL 3.5 YD3 HORAS 2.50 63.00 157.50
CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrsxDi HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
BOMBA DE 10 HP HORAS 4.00 4.06 16.24
PERFORADORA PIES 12.00 0.24 2.88
SUB-TOTAL 362.77 121.09

TOTAL COSTOS DIRECTOS 368.27

CONTINGENCIA 5% 18.41
UTILIDAD 10% 36.83
SUB TOTAL COSTOS INDIRECTOS 55.24

TOTAL COSTOS U.S.$/Mt (Con Jumbo) 423.51

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO AL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
ESTAND EMULEX EXADIT 45 TOTAL
CICLO UNIDAD DESCRIPCIO# CART # TAL TOTAL PZAS
AR 11/8"X12" 7/8"X7" KGMS
TIEMPO DE CICLO H/DISP 3.21 Alivio de arranque 3.00
LONG BARRA DE EXTEN PIES 14.00 Arranque 10.00 4.00 40.00 40.00 7.81
EFIC DE PERF % 87% AXERA 1ra Ayuda Ar 9.00 2.00 18.00 18.00 3.52
LONG PERFORACION MT 3.71 2da Ayuda Ar 9.00 2.00 18.00 18.00 3.52
EFIC.AVANCE % 81% 3ra Ayuda Ar 6.00 2.00 12.00 12.00 2.34
LONG DE PERF EFECTIVA MT 3.00 4ta Ayuda Arr 6.00 2.00 12.00 12.00 2.34
DURACION GUARDIA H 11.00 Ayudas de Cu 4.00 2.00 8.00 8.00 1.56
GUARDIAS/DIA GDA/D 2.00 Ayudas de Co 4.00 3.00 12.00 12.00 2.34
PRODUCCION/DIA M/D 11.98 Ayudas de Arr 6.00 3.00 18.00 18.00 3.52
Cuadradores 5.00 6.00 30.00 30.00 2.29
VOLUMEN POR DISPARO LABOR Coronas 5.00 5.00 25.00 25.00 1.91
ANCHO LABOR MT 3.00 Arrastres 9.00 4.00 36.00 36.00 7.03
ALTO LABOR MT 3.00 TOTAL PERFORADOS 38.00 174.00 55.00 229.00 38.18
LONGITUD MT 3.00 TOTAL CARGADOS 35.00 TOTAL KG
SOBREROTURA % 6% TOTAL KG 33.98 4.19 38.18
VOLUMEN TOTAL M3 28.64 PESO Kgs/Cartucho 0.195 0.076
DENSIDAD MATERIAL TMS/M3 2.65
EXADIT 45
EFICIENCIAS EMULEX 11/8"X12"
TONELAJE TMS/DISP 75.88 7/8"X7"
DESCRIPCIO UNIDAD VALOR Kgs/Cart 0.195 0.076
Densidad de Kgs/mt 12.74 Cart/Caja 128.00 328.00
Factor de Car Kgs/Ton 0.50 KGS/CAJA 25.00 25.00
PRECIOS UNITARIOS RAMPA 4.5 M X 4.2 M(CON JUMBO Y OPERADOR EQUIPO SIN VOLQUETE BAJO PERFIL)

GRADIENTE: 5/1000 N° de Taladros: 51.00 Avance/Disp. 3.00 MT


COD ´90001
MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT

OPERADOR DE JUMBO Hom/Disp 1.00 0.50 1.00 64.25 32.12 0.00


AYUDANTE OPER.JUMBO Hom/Disp 1.00 0.50 1.00 41.30 20.65
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
OPERADOR CAMION DE BAJO PERFILHom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 0.50 1.00 45.89 68.84 0.00
BOMBERO Hom/Disp 1.00 0.50 1.00 41.30 20.65 0.00
SERVICIOS AUXILIARES Hom/Disp 2.00 0.50 1.00 41.30 41.30 0.00
SUB-TOTAL 238.63 79.54

MATERIALES CMHSA
VIDA
DESCRIPCION UNIDAD MTS/DISP ECONOMI ESTANDAR PRECIO U.S.$/MT
CA
MTS PZAS/DISP U.S.$/PZA
BARRAS DE PERFORACION MT/DISP 189.34 2500 0.08 581.90 14.69
BROCAS DE 45 MM MT/DISP 189.34 200 0.95 93.50 29.50
SHANK ADAPTER MT/DISP 189.34 3500 0.05 366.30 6.61
AFILADOR BROCAS MT/DISP 189.34 100000 0.00 1,600.00 1.01
COPLAS MT/DISP 189.34 3000 0.06 71.50 1.50
RIMADORA DE 89 MM MT/DISP 11.14 200 0.06 233.20 4.33
ADAPTADOR DE RIMADORA MT/DISP 11.14 200 0.06 271.70 5.04
TUBO PVC (Voladura recorte) PZAS/DISP 10.00 0.41 1.37
TUBERIA DE POLIETILENO DE 2" AGU PZAS/DISP 1.50 2.34 1.17
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 1.50 7.06 3.53
HERRAMIENTAS 1.21 0.40
ALCAYATAS DE 3/4" PZAS/DISP 4.00 3.36 4.48

SUB-TOTAL 73.64

IMPLEMENTOS SEGURIDAD
DESCRIPCION UNIDAD MTS/DISP COSTO UNIT COSTO U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 4.50 2.69 12.11 4.04

VOLADURA
CANTIDAD
DESCRIPCION UNIDAD MTS/DISP CANTIDAD UNIDAD COSTO U.S.$/MT
/TALADRO
PZAS KGS U.S.$/Kgs
EMULNOR 3000 1 1/8" X 12" Cebos TALADROS 20.00 11.30 226.00 49.56 1.96 32.38
EMULNOR 3000 1 1/8" X 12" ArrastresTALADROS 11.00 12.27 135.00 29.61 1.96 19.34
EMULNOR 1000 1"X7" Coron TALADROS 17.00 6.00 102.00 9.66 1.79 5.76
CORDON DETONANTE 5P MTS 45.00 0.23 3.45
GUIA ENSAMBLADA 1.8 mts (Carmex) PZAS 2.00 0.76 0.51
FANEL DE 1/2 segundo PZAS 48.00 NO SE CO #VALUE!
SUB-TOTAL #VALUE!

EQUIPOS
COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDA OPERACIÓ COSTO TOTAL COSTO U.S.$/MT
D N TOTAL
U.S.$
U.S.$/HR U.S.$/HR U.S.$/HR
JUMBO ELECTROHIDR DE 1 BRAZO (*) HORAS 2.00 #REF! #REF! #REF! #REF!
SCOOP DIESEL 4 YD3 HORAS 3.50 #REF! #REF! #REF! #REF!
CAMION DE BAJO PERFIL (2 CAMIONES XHORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP HORAS 4.00 #REF! #REF! #REF! #REF!
PERFORADORA HORAS 6.00 #REF! #REF!
SUB-TOTAL #REF! #REF!

TOTAL COSTOS DIRECTOS #REF!

UTILIDAD 10.00% #REF!

TOTAL COSTOS #REF!


395.86
LIMPIEZA SCOOPTRAM HASTA HASTA SIN SOBREDISTANCIA HASTA CARGUIO CON VOLQUETE O PCOKET
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS

CEBO(Cart.) EMULNO
EMULNOR R 1000 EMULNOR
CICLO UNIDAESTANDAR UNIDAD
3000 1 1"X7" 3000 1
1/8"X12 1/8" X 12"
DESCRIPCION Corona
TIEMPO DE CICLO H/DIS 3.21 Taladro Alivio 3
LONG BARRA DE EXTEN PIES 14.00 Arranque 3 39 0
EFIC DE PERF % 87% 1ra Ayuda Arranque 4 44 0
LONG PERFORACION MT 3.71 2da Ayuda Arranque 4 44 0
EFIC.AVANCE % 81% 3ra Ayuda Arranque 4 44 0
LONG DE PERF EFECTIV MT 3.01 Ayudas de Alzas 5 55 0
DURACION GUARDIA H 11 Ayudas de Arrastre 4 0 44
GUARDIAS/DIA GDA/D 2 Contorno 4 0 24.00 0
PRODUCCION/DIA M/D 12.03 Contorno de Recorte 13 0 78.00 0
Arrastres 7 0 91
VOLUMEN POR DISPARO LABOR TOTAL 51 226 102 135
ANCHO LABOR MT 4.5 TOTAL KGS 51 49.56 9.66 29.61
ALTO LABOR MT 4.2
LONGITUD MT 3.01 PESO Kgs/Cartucho 0.22 0.09 0.22
SOBREROTURA % 13%
VOLUMEN TOTAL M3 64.35 EFICIENCIAS
DENSIDAD MATERIAL TMS/M 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/D 170.52 Densidad de Carga Kgs/mt 29.54
Factor de Carga Kgs/Ton 0.52
RAMPA 4.5 M X 4.2 M GRADO ALTA DIFICULTAD (CON JUMBO Y OPERADOR EQUIPO SIN VOLQUETE BAJO
PERFIL)

GRADIENTE: 5/1000 N° de Taladro 48.00 Avance/Disp. 2.64 MT


COD
SUB
MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU U.S.$/MT
TOTAL

OPERADOR DE JUMBO Hom/Disp 1.00 0.50 1.00 64.25 32.12 0.00


AYUDANTE OPER.JUMBO Hom/Disp 1.00 0.50 1.00 41.30 20.65
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 0.50 1.00 45.89 68.84 0.00
BOMBERO Hom/Disp 1.00 0.50 1.00 41.30 20.65 0.00
SERVICIOS AUXILIARES Hom/Disp 2.00 0.50 1.00 41.30 41.30 0.00
SUB-TOTAL 238.63 90.35

MATERIALES CMHSA
VIDA
DESCRIPCION UNIDAD MTS/DISP
ECONOMICA ESTANDAR PRECIO U.S.$/MT
MTS PZAS/DISP U.S.$/PZA
BARRAS DE PERFORACION MT/DISP 152.74 2500 0.06 581.90 13.46
BROCAS DE 45 MM MT/DISP 152.74 200 0.76 93.50 27.04
SHANK ADAPTER MT/DISP 152.74 3500 0.04 366.30 6.05
AFILADOR BROCAS MT/DISP 152.74 100000 0.00 1,600.00 0.93
COPLAS MT/DISP 152.74 3000 0.05 71.50 1.38
RIMADORA DE 89 MM MT/DISP 9.55 200 0.05 233.20 4.21
ADAPTADOR DE RIMADORA MT/DISP 9.55 200 0.05 271.70 4.91
TUBO PVC (Voladura recorte) PZAS/DISP 10.00 0.41 1.55
TUBERIA DE POLIETILENO DE 2" AGUAPZAS/DISP 1.32 2.34 1.17
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 1.32 7.06 3.53
HERRAMIENTAS 1.21 0.46
ALCAYATAS DE 3/4" PZAS/DISP 4.00 3.36 5.09

SUB-TOTAL 69.78

IMPLEMENTOS SEGURIDAD
DESCRIPCION UNIDAD MTS/DISP COSTO UNIT COSTO U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 4.50 2.69 12.11 4.58

VOLADURA
CANTIDAD/T
DESCRIPCION UNIDAD MTS/DISP
ALADRO CANTIDAD UNIDAD COSTO U.S.$/MT
PZAS KGS U.S.$/Kgs
EMULNOR 3000 1 1/8" X 12" Cebos TALADROS 18.00 10.33 186.00 40.79 1.96 30.27
EMULNOR 3000 1 1/8" X 12" ArrastresTALADROS 11.00 11.27 124.00 27.19 1.96 20.18
EMULNOR 1000 1"X7" Coron TALADROS 16.00 5.00 80.00 7.58 1.79 5.13
CORDON DETONANTE 5P MTS 45.00 0.23 3.92
GUIA ENSAMBLADA 1.8 mts (Carmex) PZAS 2.00 0.76 0.58
FANEL DE 1/2 segundo PZAS 45.00 NO SE CO #VALUE!
SUB-TOTAL #VALUE!

EQUIPOS
DESCRIPCION UNIDAD HRS/DISP
COSTO COSTO
COSTO TOTAL COSTO U.S.$/MT
PROPIEDAD OPERACIÓN TOTAL
U.S.$/HR U.S.$/HR U.S.$/HR U.S.$
JUMBO ELECTROHIDR DE 1 BRAZO (*) HORAS 2.00 #REF! #REF! #REF! #REF!
SCOOP DIESEL 4 YD3 HORAS 3.50 #REF! #REF! #REF! #REF!
CAMION DE BAJO PERFIL (2 CAMIONES XHORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP HORAS 4.00 #REF! #REF! #REF! #REF!
PERFORADORA HORAS 6.00 #REF! #REF!
SUB-TOTAL #REF! #REF!

TOTAL COSTOS DIRECTOS #REF!

UTILIDAD 10.00% #REF!

TOTAL COSTOS #REF!


423.31
LIMPIEZA SCOOPTRAM HASTA HASTA SIN SOBREDISTANCIA HASTA CARGUIO CON VOLQUETE O PCOKET
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS

CEBO(Cart.) EMULNO
EMULNOR R 1000 EMULNOR
CICLO UNIDADESTANDAR UNIDAD 3000 1 1"X7" 3000 1
1/8"X12
1/8" X 12"
DESCRIPCION Corona
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 3
LONG BARRA DE EXTEN PIES 12.00 Arranque 3 36 0
EFIC DE PERF PIES 87% 1ra Ayuda Arranque 3 30 0
LONG PERFORACION PIES 3.18 2da Ayuda Arranque 4 40 0
EFIC.AVANCE PIES 83% 3ra Ayuda Arranque 4 40 0
LONG DE PERF EFECTIVA PIES 2.64 Ayudas de Alzas 4 40 0
DURACION GUARDIA PIES 11 Ayudas de Arrastre 4 0 40
GUARDIAS/DIA PIES 2 Contorno 4 0 20.00 0
PRODUCCION/DIA PIES 10.56 Contorno de Recorte 12 0 60.00 0
Arrastres 7 0 84
VOLUMEN POR DISPARO LABOR TOTAL 48 186 80 124
ANCHO LABOR MT 4.5 TOTAL KGS 48 40.79 7.58 27.19
ALTO LABOR MT 4.2
LONGITUD MT 2.64 PESO Kgs/Cartucho 0.22 0.09 0.22
SOBREROTURA % 13%
VOLUMEN TOTAL M3 56.52 EFICIENCIAS
DENSIDAD MATERIAL TMS/M 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/D 149.77 Densidad de Carga Kgs/mt 28.61
Factor de Carga Kgs/Ton 0.50
PRECIOS UNITARIOS CRUCERO 4.5 M X 4.2 M CON ALTO GRADO DIFICULTAD (CON JUMBO Y OPERADOR EQUIPO SIN VOLQUETE
BAJO PERFIL)

GRADIENTE: 5/1000 N° de Taladros: 48.00 Avance/Disp. 2.64 MT

MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT

OPERADOR DE JUMBO Hom/Disp 1.00 0.50 1.00 64.25 32.12 0.00


AYUDANTE OP. JUMBO Hom/Disp 1.00 0.50 1.00 41.30 20.65
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 0.50 1.00 45.89 68.84 0.00
BOMBERO Hom/Disp 0.00 0.38 1.00 0.00 0.00
SERVICIOS AUXILIARES Hom/Disp 2.00 0.50 1.00 41.30 41.30 0.00
SUB-TOTAL 217.98 82.53

MATERIALES
VIDA
DESCRIPCION UNIDAD MTS/DISP
ECONOMICA ESTANDAR PRECIO U.S.$/MT
MTS PZAS/DISP U.S.$/PZA
BARRAS DE PERFORACION MT/DISP 152.74 2500 0.06 581.90 13.46
BROCAS DE 45 MM MT/DISP 152.74 200 0.76 93.50 27.04
SHANK ADAPTER MT/DISP 152.74 3500 0.04 366.30 6.05
AFILADOR BROCAS MT/DISP 152.74 100000 0.00 1,600.00 0.93
COPLAS MT/DISP 152.74 3000 0.05 71.50 1.38
RIMADORA DE 89 MM MT/DISP 9.55 200 0.05 233.20 4.21
ADAPTADOR DE RIMADORA MT/DISP 9.55 200 0.05 271.70 4.91
TUBO PVC (Voaldura recorte) PZAS/DISP 10.00 0.41 1.55
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 1.32 2.34 1.17
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 1.32 7.06 3.53
HERRAMIENTAS 1.21 0.46
ALCAYATAS DE 3/4" PZAS/DISP 4.00 3.36 5.09
0.00
SUB-TOTAL 69.78

IMPLEMENTOS SEGURIDAD
DESCRIPCION UNIDAD MTS/DISP COSTO UNIT COSTO U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 4.00 2.69 10.76 4.08

VOLADURA
CANTIDAD/TA
DESCRIPCION UNIDAD MTS/DISP
LADRO CANTIDAD UNIDAD COSTO U.S.$/MT
PZAS KGS U.S.$/Kgs
EMULNOR 3000 1 1/8" X 12" Cebos TALADROS 20.00 9.30 186.00 40.79 1.96 30.27
EMULNOR 3000 1 1/8" X 12" Arrastres TALADROS 9.00 10.67 96.00 21.05 1.96 15.62
EMULNOR 1000 1"X7" Corona TALADROS 16.00 5.00 80.00 7.58 1.79 5.13
CORDON DETONANTE 5P MTS 45.00 0.23 3.92
GUIA ENSAMBLADA 1.8 mts (Carmex) PZAS 2.00 0.76 0.58
FANEL DE 1/2 segundo PZAS 45.00 NO SE COM #VALUE!
SUB-TOTAL #VALUE!

EQUIPOS
DESCRIPCION UNIDAD HRS/DISP
COSTO COSTO
COSTO TOTAL COSTO U.S.$/MT
PROPIEDAD OPERACIÓN TOTAL U.S.
U.S.$/HR U.S.$/HR U.S.$/HR $
JUMBO ELECTROHIDR DE 1 BRAZO (*) HORAS 2.00 #REF! #REF! #REF! #REF!
SCOOP DIESEL 4 YD3 HORAS 3.00 #REF! #REF! #REF! #REF!
CAMION DE BAJO PERFIL (2 CAMIONES X 2HrsxDisparo) HORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP HORAS 0.00 0.00
PERFORADORA HORAS 6.00 #REF! #REF!
SUB-TOTAL #REF! #REF!

TOTAL COSTOS DIRECTOS #REF!

UTILIDAD 10.00% #REF!

TOTAL COSTOS #REF!


392.42
LIMPIEZA SCOOPTRAM HASTA HASTA SIN SOBREDISTANCIA HASTA CARGUIO CON VOLQUETE O PCOKET
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS

CEBO(Cart.) EMULNOR
EMULNOR
CICLO UNIDAD ESTANDAR UNIDAD EMULNOR 1000 1"X7"
3000 1 1/8"X12 3000 1 1/8"
DESCRIPCION X 12"
Corona
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 3
LONG BARRA DE EXTEN PIES 12.00 Arranque 3 33 0
EFIC DE PERF % 87% 1ra Ayuda Arranque 4 36 0
LONG PERFORACION MT 3.18 2da Ayuda Arranque 4 36 0
EFIC.AVANCE % 83% 3ra Ayuda Arranque 4 36 0
LONG DE PERF EFECTIVA MT 2.64 Ayudas de Alzas 5 45 0
DURACION GUARDIA H 11 Ayudas de Arrastre 4 0 36
GUARDIAS/DIA GDA/D 2 Contorno 4 0 20.00 0
PRODUCCION/DIA M/D 10.56 Contorno de Recorte 12 0 60.00 0
Arrastres 5 0 60
VOLUMEN POR DISPARO LABOR TOTAL 48 186 80 96
ANCHO LABOR MT 4.5 TOTAL KGS 48 40.79 7.58 21.05
ALTO LABOR MT 4.2
LONGITUD MT 2.64 PESO Kgs/Cartucho 0.22 0.09 0.22
SOBREROTURA % 13%
VOLUMEN TOTAL M3 56.52 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 149.77 Densidad de Carga Kgs/mt 26.28
Factor de Carga Kgs/Ton 0.46
PRECIOS UNITARIOS CRUCERO 4.5 M X 4.2 M(CON JUMBO Y OPERADOR EQUIPO SIN VOLQUETE BAJO PERFIL)

GRADIENTE: 5/1000 N° de Taladros: 48.00 Avance/Disp. 3.00 MT


COD ´90002
MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT

OPERADOR DE JUMBO Hom/Disp 1.00 0.50 1.00 64.25 32.12 0.00


AYUDANTE OP. JUMBO Hom/Disp 1.00 0.50 1.00 41.30 20.65
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR Hom/Disp 3.00 0.50 1.00 45.89 68.84 0.00
BOMBERO Hom/Disp 0.00 0.38 1.00 0.00 0.00
SERVICIOS AUXILIARES Hom/Disp 2.00 0.50 1.00 41.30 41.30 0.00
SUB-TOTAL 217.98 72.66

MATERIALES
VIDA
DESCRIPCION UNIDAD MTS/DISP
ECONOMICA ESTANDAR PRECIO U.S.$/MT
MTS PZAS/DISP U.S.$/PZA
BARRAS DE PERFORACION MT/DISP 178.20 2500 0.07 581.90 13.83
BROCAS DE 45 MM MT/DISP 178.20 200 0.89 93.50 27.77
SHANK ADAPTER MT/DISP 178.20 3500 0.05 366.30 6.22
AFILADOR BROCAS MT/DISP 178.20 100000 0.00 1,600.00 0.95
COPLAS MT/DISP 178.20 3000 0.06 71.50 1.42
RIMADORA DE 89 MM MT/DISP 11.14 200 0.06 233.20 4.33
ADAPTADOR DE RIMADORA MT/DISP 11.14 200 0.06 271.70 5.04
TUBO PVC (Voaldura recorte) PZAS/DISP 10.00 0.41 1.37
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 1.50 2.34 1.17
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 1.50 7.06 3.53
HERRAMIENTAS 1.21 0.40
ALCAYATAS DE 3/4" PZAS/DISP 4.00 3.36 4.48
0.00
SUB-TOTAL 70.50

IMPLEMENTOS SEGURIDAD
DESCRIPCION UNIDAD MTS/DISP COSTO UNIT COSTO U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 4.00 2.69 10.76 3.59

VOLADURA
CANTIDAD/TA
DESCRIPCION UNIDAD MTS/DISP
LADRO CANTIDAD UNIDAD COSTO U.S.$/MT
PZAS KGS U.S.$/Kgs
EMULNOR 3000 1 1/8" X 12" Cebos TALADROS 20.00 11.30 226.00 49.56 1.96 32.38
EMULNOR 3000 1 1/8" X 12" Arrastres TALADROS 9.00 12.11 109.00 23.90 1.96 15.62
EMULNOR 1000 1"X7" Corona TALADROS 17.00 6.00 102.00 9.66 1.79 5.76
CORDON DETONANTE 5P MTS 45.00 0.23 3.45
GUIA ENSAMBLADA 1.8 mts (Carmex) PZAS 2.00 0.76 0.51
FANEL DE 1/2 segundo PZAS 46.00 NO SE COM #VALUE!
SUB-TOTAL #VALUE!

EQUIPOS
DESCRIPCION UNIDAD HRS/DISP
COSTO COSTO
COSTO TOTAL COSTO U.S.$/MT
PROPIEDAD OPERACIÓN TOTAL U.S.
U.S.$/HR U.S.$/HR U.S.$/HR $
JUMBO ELECTROHIDR DE 1 BRAZO (*) HORAS 2.00 #REF! #REF! #REF! #REF!
SCOOP DIESEL 4 YD3 HORAS 3.00 #REF! #REF! #REF! #REF!
CAMION DE BAJO PERFIL (2 CAMIONES X 2HrsxDisparo) HORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP HORAS 0.00 0.00
PERFORADORA HORAS 6.00 #REF! #REF!
SUB-TOTAL #REF! #REF!

TOTAL COSTOS DIRECTOS #REF!

UTILIDAD 10.00% #REF!

TOTAL COSTOS #REF!


364.76
LIMPIEZA SCOOPTRAM HASTA HASTA SIN SOBREDISTANCIA HASTA CARGUIO CON VOLQUETE O PCOKET
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS

CEBO(Cart.) EMULNOR
EMULNOR
CICLO UNIDAD ESTANDAR UNIDAD EMULNOR 1000 1"X7"
3000 1 1/8"X12 3000 1 1/8"
DESCRIPCION X 12"
Corona
TIEMPO DE CICLO H/DISP 3.21 Taladro Alivio 2
LONG BARRA DE EXTEN PIES 14.00 Arranque 3 39 0
EFIC DE PERF % 87% 1ra Ayuda Arranque 4 44 0
LONG PERFORACION MT 3.71 2da Ayuda Arranque 4 44 0
EFIC.AVANCE % 81% 3ra Ayuda Arranque 4 44 0
LONG DE PERF EFECTIVA MT 3.01 Ayudas de Alzas 5 55 0
DURACION GUARDIA H 11 Ayudas de Arrastre 4 0 44
GUARDIAS/DIA GDA/D 2 Contorno 4 0 24.00 0
PRODUCCION/DIA M/D 12.03 Contorno de Recorte 13 0 78.00 0
Arrastres 5 0 65
VOLUMEN POR DISPARO LABOR TOTAL 48 226 102 109
ANCHO LABOR MT 4.5 TOTAL KGS 48 49.56 9.66 23.90
ALTO LABOR MT 4.2
LONGITUD MT 3.01 PESO Kgs/Cartucho 0.22 0.09 0.22
SOBREROTURA % 13%
VOLUMEN TOTAL M3 64.35 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 170.52 Densidad de Carga Kgs/mt 27.64
Factor de Carga Kgs/Ton 0.49
PRECIOS UNITARIOS CRUCERO 3.50 M X 3.50 M (JACK LEG, CON OPERADOR EQUIPO SIN VOLQUETE BAJO PERFIL)

GRADIENTE: 5/1000 N° de Taladr 42.00 Avance/Disp 1.60 MT


COD ´90004
MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT

PERFORISTA Hom/Disp 2.00 0.50 1.00 45.89 45.89 0.00


AYUDANTE OP. PERFORISTA Hom/Disp 1.00 0.50 1.00 41.30 20.65
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
SERVICIOS AUXILIARES Hom/Disp 1.00 0.50 1.00 41.30 20.65 0.00
SUB-TOTAL 142.26 88.91

MATERIALES
VIDA
DESCRIPCION UNIDAD MTS/DISP
ECONOMICA ESTANDAR PRECIO U.S.$/MT
MTS PZAS/DISP U.S.$/PZA
Barra de 6¨ FTS/DISP 252.00 1820 0.14 94.60 8.19
Broca de 40 mm FTS/DISP 252.00 350 0.72 25.30 11.39
Aceite de Perforación GLNS/DISP 0.50 0 9.16 2.86
AFILADOR BROCAS MT/DISP 252.00 100000 0.00 1,600.00 2.52
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 1.60 2.34 2.34
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 1.60 7.06 7.06
HERRAMIENTAS 1.21 0.76
ALCAYATAS DE 3/4" PZAS/DISP 1.00 3.36 2.10

SUB-TOTAL 37.21

IMPLEMENTOS SEGURIDAD
DESCRIPCION UNIDAD MTS/DISP COSTO UNIT COSTO U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 3.00 2.69 8.07 5.05

VOLADURA
CANTIDAD/T
DESCRIPCION UNIDAD MTS/DISP
ALADRO CANTIDAD UNIDAD U.S.$/MT
PZAS KGS U.S.$/PZA
EMULNOR 3000 1 1/8" X 12" Cebos TALADROS 18.00 6.22 112.00 24.56 1.96 30.09
EMULNOR 3000 1 1/8" X 12" Arrastres 7.00 6.57 46.00 10.09 1.96 12.36
EMULNOR 1000 1"X7" Corona 14.00 3.00 42.00 3.98 1.79 4.45
FANEL TALADROS 39.00 NO SE COMPRA #VALUE!
Carmex 8´ TALADROS 2.00 0.76 0.95
Pentacord MTS 15.00 0.23 2.16
Igniter Cord PZAS 0.25 0.41 0.06

SUB-TOTAL #VALUE!

EQUIPOS
COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP
PROPIEDAD OPERACIÓN
COSTO TOTAL COSTO TOTAL U.S.$/MT
U.S.$
U.S.$/HR U.S.$/HR U.S.$/HR

SCOOP DIESEL 4 YD3 HORAS 1.80 #REF! #REF! #REF! #REF!


CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrsxDisparo) HORAS 0.00 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00 0.00
BOMBA DE 50 HP HORAS 0.00 0.00 0.00
B OMBA DE 10 HP HORAS 0.00 #REF! #REF! #REF! #REF!
PERFORADORA HORAS 252.00 #REF! #REF!
SUB-TOTAL #REF! #REF!

TOTAL COSTOS DIRECTOS #REF!

UTILIDAD 10.00% #REF!

TOTAL COSTOS #REF!


291.65
LIMPIEZA SCOOPTRAM HASTA HASTA SIN SOBREDISTANCIA HASTA CARGUIO CON VOLQUETE O PCOKET
DATOS
DISTRIBUCION DE CARGA DE EXPLOSIVOS

CEBO(Cart.) EMULNOR
EMULNOR
UNIDAD EMULNOR 1000 1"X7"
3000 1 1/8"X12 3000 1 1/8"
Corona
DESCRIPCION X 12"
Taladro Alivio 3
Arranque 4 28 0
1ra Ayuda Arranque 4 24 0
2da Ayuda Arranque 4 24 0
3ra Ayuda Arranque 4 24 0
Ayudas de Alzas 2 12 0
Ayudas de Arrastre 3 0 18
Contorno 9 0 27.00 0
Contorno de Recorte 5 0 15.00 0
Arrastres 4 0 28
TOTAL 42 112 42 46
TOTAL KGS 42 24.56 3.98 10.09

PESO Kgs/Cartucho 0.22 0.09 0.22


PRECIOS UNITARIOS CRUCERO 3.0 M X 3.0 M CON JUMBO

N° de Taladros 31.00 Avance/Disp. 3.00 MT


COD ´90008
MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT

OPERADOR DE JUMBO Hom/Disp 1.00 0.50 1.00 64.25 32.12 0.00


AYUDANTE OP. JUMBO Hom/Disp 1.00 0.50 1.00 41.30 20.65
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR Hom/Disp 2.00 0.50 1.00 45.89 45.89 0.00
BOMBERO Hom/Disp 0.00 0.38 1.00 0.00 0.00
SERVICIOS AUXILIARES Hom/Disp 0.00 0.50 1.00 41.30 0.00 0.00
SUB-TOTAL 153.73 51.24

MATERIALES
VIDA
DESCRIPCION UNIDAD MTS/DISP
ECONOMICA ESTANDAR PRECIO U.S.$/MT
MTS PZAS/DISP U.S.$/PZA
BARRAS DE PERFORACION MT/DISP 107.72 2500 0.04 581.90 8.36
BROCAS DE 45 MM MT/DISP 107.72 200 0.54 93.50 16.79
SHANK ADAPTER MT/DISP 107.72 3500 0.03 366.30 3.76
AFILADOR BROCAS MT/DISP 107.72 100000 0.00 1,600.00 0.57
COPLAS MT/DISP 107.72 3000 0.04 71.50 0.86
RIMADORA DE 89 MM MT/DISP 10.42 200 0.05 233.20 4.05
ADAPTADOR DE RIMADORA MT/DISP 10.42 200 0.05 271.70 4.72
TUBO PVC (Voaldura recorte) PZAS/DISP 5.00 0.41 0.68
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 1.50 2.34 1.17
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 7.06 0.00
HERRAMIENTAS 1.21 0.40
ALCAYATAS DE 3/4" PZAS/DISP 4.00 3.36 4.48
0.00
SUB-TOTAL 45.84

IMPLEMENTOS SEGURIDAD
DESCRIPCION UNIDAD MTS/DISP COSTO UNIT U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 2.50 2.69 6.73 2.24

VOLADURA
CANTIDAD/TA
DESCRIPCION UNIDAD MTS/DISP
LADRO CANTIDAD UNIDAD COSTO U.S.$/MT
PZAS KGS U.S.$/Kgs
EMULNOR 3000 1 1/8" X 12" Cebos TALADROS 14.00 7.71 108.00 20.25 1.96 13.23
EMULNOR 3000 1 1/8" X 12" Arrastres TALADROS 7.00 7.14 50.00 10.96 1.96 7.16
EMULNOR 1000 1"X7" Corona TALADROS 8.00 5.13 41.00 6.13 1.79 3.66
CORDON DETONANTE 5P MTS 10.00 0.23 0.77
GUIA ENSAMBLADA 1.8 mts (Carmex) PZAS 2.00 0.76 0.51
FANEL DE 1/2 segundo PZAS 29.00 NO SE COMPR #VALUE!
SUB-TOTAL #VALUE!

EQUIPOS
COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP
PROPIEDAD OPERACIÓN
COSTO TOTAL COSTO U.S.$/MT
TOTAL U.S.$
U.S.$/HR U.S.$/HR U.S.$/HR
JUMBO ELECTROHIDR DE 1 BRAZO (*) HORAS 1.50 #REF! #REF! #REF! #REF!
SCOOP DIESEL 4 YD3 HORAS 2.00 #REF! #REF! #REF! #REF!
CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrsxDisparo HORAS 0.00 #REF! #REF! #REF! #REF!
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 0.00 0.00
BOMBA DE 50 HP HORAS 0.00 0.00
B OMBA DE 10 HP HORAS 0.00 0.00
PERFORADORA HORAS 12.00 #REF! #REF!
SUB-TOTAL #REF! #REF!

TOTAL COSTOS DIRECTOS #REF!

UTILIDAD 10.00% #REF!

TOTAL COSTOS #REF!


234.23
LIMPIEZA SCOOPTRAM HASTA HASTA SIN SOBREDISTANCIA HASTA CARGUIO CON VOLQUETE O PCOKET
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EXADIT
CEBO(Cart.) EMULNOR
45% 7/8"X7"
CICLO UNIDAD ESTANDAR UNIDAD EMULNOR 3000 3000 1 1/8" X
1 1/8"X12 12"
DESCRIPCION Corona
TIEMPO DE CICLO H/DISP 2 Taladro Alivio 2
LONG BARRA DE EXTEN PIES 12.00 Arranque 2 20.0
EFIC DE PERF % 95% AXERA 1ra Ayuda Arranque 2 16.0
LONG PERFORACION MT 3.47 2da Ayuda Arranque 2 16.0
EFIC.AVANCE % 87% 3ra Ayuda Arranque 2 16.0
LONG DE PERF EFECTIVA MT 3.02 Ayudas de Cuadrador 2 16.0
DURACION GUARDIA H 7 Ayudas de Corona 3 21.0
GUARDIAS/DIA GDA/D 2 Ayudas de Arrastre 3 18.0
PRODUCCION/DIA M/D 12.09 Cuadradores 4 24.00 0.0
Coronas 5 20.00 0.0
VOLUMEN POR DISPARO LABOR Arrastres 4 32.0
ANCHO LABOR MT 3 TOTAL 31 44.00 155
ALTO LABOR MT 3 TOTAL KGS 29 - 3.35 33.99
LONGITUD MT 3.00
SOBREROTURA % 13% PESO Kgs/Cartucho 0.08 0.22
VOLUMEN TOTAL M3 30.57
DENSIDAD MATERIAL TMS/M3 2.65 EFICIENCIAS
TONELAJE TMS/DISP 81.01 DESCRIPCION UNIDAD VALOR
Densidad de Carga Kgs/mt 12.45
Factor de Carga Kgs/Ton 0.46
CRUCERO 3.0 M X 3.0 M CON EQUIPO

N° de Taladro 36 Avance/Disp. 3.00 MT

MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT


OPERADOR DE JUMBO 1.00 Hom/Disp 1.00 1.00 1.00 64.25 64.25 0.00
AYUDANTE OP. JUMBO 1.00 Hom/Disp 1.00 1.00 1.00 41.30 41.30 0.00
OPERADOR SCOOPTRAM 1.00 Hom/Disp 1.00 1.00 1.00 55.07 55.07 0.00
OPERADOR CAMION DE BAJO PERFIL 0.00 Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR 1.00 Hom/Disp 2.00 1.00 1.00 45.89 91.78 0.00
BOMBERO 0.00 Hom/Disp 0.00 1.00 1.00 41.30 0.00 0.00
SERVICIOS AUXILIARES 0.00 Hom/Disp 2.00 1.00 1.00 41.30 82.60 0.00
SUB-TOTAL 362.54 120.85

MATERIALES
VIDA
ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP ECONOMICA U.S.$/MT
PZAS/DISP $/PZA
MTS
BARRAS DE PERFORACION MT/DISP 132.04 2,500 0.05 581.90 10.24
BROCAS DE 45 MM MT/DISP 125.09 200 0.63 93.50 19.49
SHANK ADAPTER MT/DISP 132.04 3,500 0.04 366.30 4.61
AFILADOR BROCAS MT/DISP 125.09 100,000 0.00 1600.00 0.67
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 6.95 200 0.03 233.20 2.70
ADAPTADOR DE RIMADORA MT/DISP 6.95 200 0.03 271.70 3.15
TUBO PVC (Voladura recorte) PZAS/DISP 5.00 0.41 0.68
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.48
PETROLEO(Para Scooptram ) 3.50 2.50 4.90 14.30
SUB-TOTAL 65.54

IMPLEMENTOS SEGURIDAD
COSTO UNIT
DESCRIPCION UNIDAD MTS/DISP COSTO U.S.$ U.S.$/MT
U.S.$/Pers
Implementos Seguridad Unidad 7.50 2.69 20.18 6.73

VOLADURA
CANTIDAD/TA CANTIDAD COSTO U.S.
DESCRIPCION UNIDAD TALADROS UNIDAD KGS U.S.$/MT
LADRO PZA $/Kgs
EMULEX 45% 1 1/8" X 12" (128) TALADROS 22.00 7.09 156.00 30.47 2.66 27.02
EXADIT 45% 7/8" X 7" (328) TALADROS 11.00 5.00 55.00 4.19 2.23 3.12
CORDON DETONANTE 5P MTS 35.00 0.23 2.68
GUIA ENSAMBLADA 2.4 MTL - CARMEX (300) PZAS 2.00 0.76 0.51
EXSANEL 4.80 MTL PZAS 33.00 1.58 17.38
SUB-TOTAL 50.70

EQUIPOS
COSTO COSTO COSTO
COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. U.S.$/MT
TOTAL U.S.$
U.S.$/HR U.S.$/HR $/HR
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petrol HORAS 1.50 110.00 165.00
SCOOP DIESEL 3.5 YD3 HORAS 2.50 63.00 157.50
CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrsxDi HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
B OMBA DE 10 HP HORAS 0.00 4.06 0.00
PERFORADORA PIES 12.00 0.24 2.88
SUB-TOTAL 346.53 115.51

TOTAL COSTOS DIRECTOS 359.33

CONTINGENCIA 5% 17.97
UTILIDAD 10% 35.93
SUB TOTAL COSTOS INDIRECTOS 53.90

TOTAL COSTOS U.S.$/Mt (Con Jumbo) 413.23

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO AL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
ESTAND EMULEX EXADIT 45 TOTAL
CICLO UNIDAD DESCRIPCIO# CART # TAL TOTAL PZAS
AR 11/8"X12" 7/8"X7" KGMS
TIEMPO DE CICLO H/DISP 3.21 Alivio de arranque 2.00
LONG BARRA DE EXTEN PIES 12.00 Arranque 10.00 4.00 40.00 40.00 7.81
EFIC DE PERF % 95% AXERA 1ra Ayuda Arr 9.00 2.00 18.00 18.00 3.52
LONG PERFORACION MT 3.47 2da Ayuda Ar 9.00 2.00 18.00 18.00 3.52
EFIC.AVANCE % 81% 3ra Ayuda Arr 6.00 2.00 12.00 12.00 2.34
LONG DE PERF EFECTIVA MT 2.80 4ta Ayuda Arr 6.00 2.00 12.00 12.00 2.34
DURACION GUARDIA H 11.00 Ayudas de Cu 4.00 2.00 8.00 8.00 1.56
GUARDIAS/DIA GDA/D 2.00 Ayudas de Co 4.00 3.00 12.00 12.00 2.34
PRODUCCION/DIA M/D 11.22 Ayudas de Arr 6.00 3.00 18.00 18.00 3.52
Cuadradores 5.00 6.00 30.00 30.00 2.29
VOLUMEN POR DISPARO LABOR Coronas 5.00 5.00 25.00 25.00 1.91
ANCHO LABOR MT 3.00 Arrastres 9.00 2.00 18.00 18.00 3.52
ALTO LABOR MT 3.00 TOTAL PERFORADOS 35.00 156.00 55.00 211.00 34.66
LONGITUD MT 2.80 TOTAL CARGADOS 33.00 TOTAL KG
SOBREROTURA % 6% TOTAL KG 30.47 4.19 34.66
VOLUMEN TOTAL M3 26.80 PESO Kgs/Cartucho 0.195 0.076
DENSIDAD MATERIAL TMS/M3 2.65
EMULEX EXADIT 45
EFICIENCIAS
TONELAJE TMS/DISP 71.02 11/8"X12" 7/8"X7"
DESCRIPCIO UNIDAD VALOR Kgs/Cart 0.195 0.076
Densidad de Kgs/mt 12.36 Cart/Caja 128.00 328.00
Factor de Car Kgs/Ton 0.49 KGS/CAJA 25.00 25.00
CRUCERO 2.0 M X 2.0 M CON EQUIPO(REFUGIO)

N° de Taladro 28 Avance/Disp. 3.00 MT

MANO DE OBRA UNIDAD CANTIDAD FACTOR FACT MO PU SUB TOTAL U.S.$/MT


OPERADOR DE JUMBO 1.00 Hom/Disp 1.00 0.67 1.00 64.25 43.05 0.00
AYUDANTE OP. JUMBO 1.00 Hom/Disp 1.00 0.67 1.00 41.30 27.67 0.00
OPERADOR SCOOPTRAM 1.00 Hom/Disp 1.00 0.67 1.00 55.07 36.90 0.00
OPERADOR CAMION DE BAJO PERFIL 0.00 Hom/Disp 1.00 0.50 1.00 55.07 27.53 0.00
CARGADOR/DISPARADOR 1.00 Hom/Disp 2.00 0.67 1.00 45.89 61.49 0.00
BOMBERO 0.00 Hom/Disp 0.00 0.67 1.00 41.30 0.00 0.00
SERVICIOS AUXILIARES 0.00 Hom/Disp 2.00 0.67 1.00 41.30 55.34 0.00
SUB-TOTAL 251.99 84.11

MATERIALES
VIDA
ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP ECONOMICA U.S.$/MT
PZAS/DISP $/PZA
MTS
BARRAS DE PERFORACION MT/DISP 92.87 2,500 0.04 581.90 7.22
BROCAS DE 45 MM MT/DISP 83.89 200 0.42 93.50 13.09
SHANK ADAPTER MT/DISP 92.87 3,500 0.03 366.30 3.24
AFILADOR BROCAS MT/DISP 83.89 100,000 0.00 1600.00 0.45
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 8.99 200 0.04 233.20 3.50
ADAPTADOR DE RIMADORA MT/DISP 8.99 200 0.04 271.70 4.08
TUBO PVC (Voladura recorte) PZAS/DISP 5.00 0.41 0.68
TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00
TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06
HERRAMIENTAS 1.21 0.40
MANGA VENTILACION 30" MT/DISP 3.00 1 4.82 4.82
ALCAYATAS DE 3/4" 4.00 PZAS/DISP 4.00 3.36 4.49
PETROLEO(Para Scooptram ) 3.50 2.00 4.90 11.45
SUB-TOTAL 53.42

IMPLEMENTOS SEGURIDAD
COSTO UNIT COSTO
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
U.S.$/Pers U.S.$
Implementos Seguridad Unidad 5.19 2.69 13.97 4.66

VOLADURA
CANTIDAD/TA CANTIDAD COSTO
DESCRIPCION UNIDAD TALADROS UNIDAD KGS U.S.$/MT
LADRO PZA U.S.$/Kgs
EMULEX 45% 1 1/8" X 12" (128) TALADROS 17.00 7.41 126.00 24.61 2.66 21.85
EXADIT 45% 7/8" X 7" (328) TALADROS 8.00 5.00 40.00 3.05 2.23 2.27
CORDON DETONANTE 5P MTS 35.00 0.23 2.69
GUIA ENSAMBLADA 2.4 MTL - CARMEX (300) PZAS 2.00 0.76 0.51
EXSANEL 4.80 MTL PZAS 25.00 1.58 13.18
SUB-TOTAL 40.50

EQUIPOS
COSTO COSTO COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. TOTAL U.S. U.S.$/MT
U.S.$/HR U.S.$/HR $/HR $
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petrol HORAS 1.50 110.00 165.00
SCOOP DIESEL 3.5 YD3 HORAS 2.00 63.00 126.00
CAMION DE BAJO PERFIL (2 CAMIONES X 1.8HrsxDi HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 9.00 1.65 0.70 2.35 21.15
B OMBA DE 10 HP 0.00 HORAS 0.00 4.06 0.00
PERFORADORA PIES 12.00 0.24 2.88
SUB-TOTAL 315.03 105.15

TOTAL COSTOS DIRECTOS 287.84

CONTINGENCIA 5% 14.39
UTILIDAD 10% 28.78
SUB TOTAL COSTOS INDIRECTOS 43.18

TOTAL COSTOS U.S.$/Mt (Con Jumbo) 331.01

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE O CARGUIO AL VOLQUETE, POCKET, O CAMARA DENTRO DE ESTE RANGO
DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
ESTAND EMULEX EXADIT 45 TOTAL
CICLO UNIDAD DESCRIPCIO# CART # TAL TOTAL PZAS
AR 11/8"X12" 7/8"X7" KGMS
TIEMPO DE CICLO H/DISP 3.21 Alivio de arranque 3.00
LONG BARRA DE EXTEN PIES 14.00 Arranque 10.00 3.00 30.00 30.00 5.86
EFIC DE PERF % 87% AXERA 1ra Ayuda Arr 9.00 2.00 18.00 18.00 3.52
LONG PERFORACION MT 3.71 2da Ayuda Ar 9.00 2.00 18.00 18.00 3.52
EFIC.AVANCE % 81% 3ra Ayuda Arr 6.00 2.00 12.00 12.00 2.34
LONG DE PERF EFECTIVA MT 3.00 4ta Ayuda Arr 6.00 1.00 6.00 6.00 1.17
DURACION GUARDIA H 11.00 Ayudas de Cu 4.00 1.00 4.00 4.00 0.78
GUARDIAS/DIA GDA/D 2.00 Ayudas de Co 4.00 2.00 8.00 8.00 1.56
PRODUCCION/DIA M/D 11.98 Ayudas de Arr 6.00 2.00 12.00 12.00 2.34
Cuadradores 5.00 4.00 20.00 20.00 1.52
VOLUMEN POR DISPARO LABOR Coronas 5.00 4.00 20.00 20.00 1.52
ANCHO LABOR MT 3.00 Arrastres 9.00 2.00 18.00 18.00 3.52
ALTO LABOR MT 3.00 TOTAL PERFORADOS 28.00 126.00 40.00 166.00 27.66
LONGITUD MT 3.00 TOTAL CARGADOS 25.00 TOTAL KG
SOBREROTURA % 6% TOTAL KG 24.61 3.05 27.66
VOLUMEN TOTAL M3 28.64 PESO Kgs/Cartucho 0.195 0.076
DENSIDAD MATERIAL TMS/M3 2.65
EMULEX EXADIT 45
EFICIENCIAS
TONELAJE TMS/DISP 75.88 11/8"X12" 7/8"X7"
DESCRIPCIO UNIDAD VALOR Kgs/Cart 0.195 0.076
Densidad de Kgs/mt 9.23 Cart/Caja 128.00 328.00
Factor de Car Kgs/Ton 0.36 KGS/CAJA 25.00 25.00
DESQUICHE CON JUMBO

GRADIENTE: 5/1000 N° de Taladros: 48.00 Avance/Disp. 56.70 MT


Factor Incidencia 12%
FACTOR
MANO DE OBRA UNIDAD CANTIDAD FACT MO PU SUB TOTAL U.S.$/MT
INCIDENCIA
OPERADOR DE JUMBO Hom/Disp 1.00 0.80 1.00 64.25 51.40
AYUDANTE OPER.JUMBO Hom/Disp 1.00 0.80 1.00 41.30 33.04
OPERADOR SCOOPTRAM Hom/Disp 1.00 0.80 1.00 55.07 44.05
OPERADOR CAMION DE BAJO PERFIL Hom/Disp 0.00 0.80 1.00 55.07 0.00
CARGADOR/DISPARADOR Hom/Disp 2.00 0.80 1.00 45.89 73.42
BOMBERO Hom/Disp 0.00 0.80 1.00 41.30 0.00
SERVICIOS AUXILIARES Hom/Disp 0.00 0.80 1.00 41.30 0.00
SUB-TOTAL 201.92 3.56

MATERIALES
VIDA UTIL ESTANDAR PRECIO U.S.
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
MTS PZAS/DISP $/PZA
BARRAS DE PERFORACION MT/DISP 178.20 2,500 0.07 581.90 0.73
BROCAS DE 45 MM MT/DISP 178.20 200 0.89 93.50 1.47
SHANK ADAPTER MT/DISP 178.20 3,500 0.05 366.30 0.33
AFILADOR BROCAS MT/DISP 178.20 100,000 0.00 1,600.00 0.05
COPLAS MT/DISP 0.00 3,000 0.00 71.50 0.00
RIMADORA DE 89 MM MT/DISP 0.00 200 0.00 233.20 0.00
ADAPTADOR DE RIMADORA MT/DISP 0.00 200 0.00 271.70 0.00

TUBERIA DE POLIETILENO DE 2" AGUA PZAS/DISP 0.00 2.34 0.00


TUBERIA DE POLIETILENO DE 4" AIRE PZAS/DISP 0.00 7.06 0.00
HERRAMIENTAS GLB 1.21 0.02
MANGA VENTILACION 30" MT/DISP 56.70 1 4.82 4.82

PETROLEO(Para Scooptram ) 3.50 3.00 4.90 0.91


SUB-TOTAL 8.33

IMPLEMENTOS SEGURIDAD
COSTO UNIT COSTO
DESCRIPCION UNIDAD MTS/DISP U.S.$/MT
U.S.$/Pers U.S.$
IMPLEMENTOS SEGURIDAD Unidad 4.00 2.69 10.76 0.19

VOLADURA
CANTIDAD/ CANTIDAD COSTO
DESCRIPCION UNIDAD MTS/DISP UNIDAD KG U.S.$/MT
TALADRO PZAS U.S.$/Kg
EMULEX 45% 1 1/8" X 12" Cebos TALADROS 13.00 10.00 130.00 25.39 2.66 1.19
EMULEX 45% 1 1/8" X 12" Arrastres TALADROS 9.00 7.78 70.00 13.67 2.66 0.64
EXADIT 45% 7/8" X 7" Corona TALADROS 10.00 6.00 60.00 4.57 2.23 0.18
CORDON DETONANTE 5P MTS 45.00 0.23 0.18
GUIA ENSAMBLADA 2.4 mts (Carmex) PZAS 2.00 0.76 0.03
EXANEL 4.8 Mts PZAS 48.00 1.58 1.34
SUB-TOTAL 3.56

EQUIPOS
COSTO COSTO COSTO COSTO
DESCRIPCION UNIDAD HRS/DISP PROPIEDAD OPERACIÓN TOTAL U.S. TOTAL U.S.$/MT
U.S.$/HR U.S.$/HR $/HR U.S.$
JUMBO ELECTROHIDR DE 1 BRAZO (Incluye petroleo) HORAS 2.00 110.00 220.00
SCOOP DIESEL 4 YD3 HORAS 3.00 63.00 189.00
CAMION DE BAJO PERFIL (2 CAMIONES X 2HrsxDisp) HORAS 0.00 0.00
VENTILADOR DE 60,000 CFM HORAS 0.00 0.00
VENTILADOR DE 20,000 CFM HORAS 8.00 1.65 0.70 2.35 18.80
BOMBA DE 50 HP HORAS 0.00 0.00
BOMBA DE 10 HP HORAS 0.00 4.06 0.00
PERFORADORA HORAS 12.00 0.24 2.88
SUB-TOTAL 430.68 7.60

TOTAL COSTOS DIRECTOS 23.24

CONTINGENCIA 5% 1.16
UTILIDAD 10% 2.32
SUB TOTAL COSTOS INDIRECTOS 3.49

TOTAL COSTOS U.S.$/Mt (Con equipos) 26.72

LIMPIEZA SCOOPTRAM HASTA 150 MTS DEL FRENTE


DATOS
EFICIENCIA DE AVANCES DISTRIBUCION DE CARGA DE EXPLOSIVOS
EXADIT
EMULEX
EMULEX 45% 45%
45% 1
CICLO UNIDAD ESTANDAR UNIDAD 1 1/8"X12 7/8"X7"
1/8"X12
Cebo
DESCRIPCION Arrastre
Corona
TIEMPO DE CICLO H/DISP 3.21
LONG BARRA DE EXTEN PIES 14.00
EFIC DE PERF % 87% 1ra Ayuda Arranque 3.00 30.00 0.00
LONG PERFORACION MT 3.71 2da Ayuda Arranque 3.00 30.00 0.00
EFIC.AVANCE % 81% 3ra Ayuda Arranque 3.00 30.00 0.00
LONG DE AVANCE EFECTIVA MT 3.00 Ayudas de Alzas 4.00 40.00 0.00
DURACION GUARDIA H 11 Ayudas de Arrastre 4.00 0.00 40.00
GUARDIAS/DIA GDA/D 2 Contorno 4.00 0.00 24.00 0.00
PRODUCCION/DIA M/D 11.98 Contorno de Recorte 6.00 0.00 36.00 0.00
Arrastres 5.00 0.00 30.00
VOLUMEN POR DISPARO LABOR TOTAL 32.00 130.00 60.00 70.00
ANCHO LABOR MT 4.5 TOTAL KGS 32.00 25.39 4.57 13.67
ALTO LABOR MT 4.2
LONGITUD MT 3.00 PESO Kgs/Cartucho 0.20 0.08 0.20
SOBREROTURA % 6%
VOLUMEN TOTAL M3 60.13 EFICIENCIAS
DENSIDAD MATERIAL TMS/M3 2.65 DESCRIPCION UNIDAD VALOR
TONELAJE TMS/DISP 159.36 Densidad de Carga Kgs/mt 14.56
Factor de Carga Kgs/Ton 0.27
FORMATO DE PRECIOS UNITARIOS DE AVANCES
ACUMULACION PARCOY
CONSORCIO MINER0 HORIZONTE S.A.
CH. 2.50 x 2.50 Mts.Limpieza Sin Scoop directo a la Tolva, hasta 30 mts altura N° Taladros: 35 u
Distancia de recorrido 150 mts N° Tal.carg.: 31 u
AVANCE: 1.00 ml

ITEM DESCRIPCION INCID. UNI. CANTID. PRECIO SUBTOT. TOTAL


UNITARIO $ US$/UNID
1.- MANO DE OBRA
Perforistas Tareas 1.25 45.89 $/Tarea 57.36
Ayudante Perforista Tareas 1.25 41.30 $/Tarea 51.63
Ayudante Tareas 0.50 41.30 $/Tarea 20.65
129.64 129.64
2.- IMPLEMENTOS
Tareas con ropa de Agua Tareas 3.00 2.69 8.07
8.07 8.07
3.- MATERIALES Y HERRAMIENTAS
Barra de 6¨ P.P. 175.000 94.60 $/pp 9.10
Broca de 40 mm PP 175.000 25.30 $/uni 2.43
Aceite de Perforación Gln. 0.250 9.16 $/gln. 2.29
Herramientas de Mina Global Global 1.01
14.83 14.83
4.- EXPLOSIVOS 3.58 m3
EMULEX 45% x 1 1/8" x 12" (128) Pza. 80.00 0.520 $/uni 41.60
EXADIT 45% 7/8" X 7" (328) Pza. 65.00 0.170 $/uni 11.05
EXSANEL 3.0 m Pza. 31.00 1.320 $/uni 40.92
GUIA ENSAMBLADA 2.4 MTL - CARMEX (300) Pza. 2.00 0.760 $/uni 1.52
CORDON DETONANTE 5P Mts. 10.00 0.230 $/mts. 2.30
IGNICION RAPIDA Mts. 0.25 0.410 $/mts. 0.10
97.49 97.49
5.- EQUIPOS
Scooptrams de 3.50 Yd3 Hrs. 0.70 63.00 $/hr 44.10
Ventilador Hrs. 0.00 2.35 $/hr 0.00
Perforadora P.P. 175.00 0.24 $/pp 42.00
86.10 86.10
336.13
6.- GASTOS INDIRECTOS
Contingencias 5% $ 16.81
Gastos Generales 0% $ 0.00
Utilidad 10% $ 33.61
TOTAL COSTO METRO LINEAL EN DOLARES (US$/M-L) 386.55
Energía Eléctrica, Tuberias y Accesorios proporciona Cía, hasta 50 Mts del top del frente
FORMATO DE PRECIOS UNITARIOS DE AVANCES

CONSORCIO MINER0 HORIZONTE S.A.


CH. 1.50 x 1.50 Mts. Limpieza con Scoop, hasta los 30 mts altura N° Taladros: 18 u
Distancia de recorrido 150 Mts. N° Tal.carg.: 14 u
AVANCE: 1.30 ml

ITEM DESCRIPCION INCID. UNI. CANTID. PRECIO SUBTOT. TOTAL


UNITARIO $ US$/UNID
1.- MANO DE OBRA
Perforistas Tareas 1.25 45.89 $/Tarea 57.36
Ayudante Perforista Tareas 1.25 41.30 $/Tarea 51.63
Operador Scooptram Tareas 0.00 41.30 $/Tarea 0.00
Bodeguero Tareas $/Tarea
108.99 83.84
2.- IMPLEMENTOS
Tareas con ropa de Agua Tareas 2.50 2.69 6.73

6.73 5.17
3.- MATERIALES Y HERRAMIENTAS
Barra de 6¨ P.P. 90.000 94.60 $/pp 4.68
Broca de 40 mm PP 90.000 25.30 $/uni 1.25
Aceite de Perforación Gln. 0.250 9.16 $/gln. 2.29
Herramientas de Mina Global Global 1.01
9.23 7.10
4.- EXPLOSIVOS

EMULEX 45% x 1 1/8" x 12" (128) Unid. 50.00 0.520 $/uni 26.00
EXADIT 45% 7/8" X 7" (328) Unid. 20.00 0.170 $/uni 3.40
EXSANEL 3.0m Unid. 14.00 1.320 $/uni 18.48
GUIA ENSAMBLADA 2.4 MTL - CARMEX (300) Pza. 2.00 0.760 $/uni 1.52
CORDON DETONANTE 5P Mts. 10.00 0.230 $/mts. 2.30
IGNICION RAPIDA Mts. 0.25 0.410 $/mts. 0.10
51.80 39.85
5.- EQUIPOS
Scooptrams de 3.50 Yd3 Hrs. 0.40 63.00 $/hr 25.20
Perforadora P.P. 90.00 0.240 $/pp 21.60
46.80 36.00
171.96
6.- GASTOS INDIRECTOS
Contingencias 5% $ 8.60
Gastos Generales 0% $ 0.00
Utilidad 10% $ 17.20
TOTAL COSTO METRO LINEAL EN DOLARES (US$/M-L) 197.75
Energía Eléctrica, Tuberias y Accesorios proporciona Cía, hasta 50 Mts del tope del frente
INSTALACION PERNO HELICOIDAL DE 6' CEMBOL
Solo instalación del perno
Longitud Taladro : 1.80 Mts.
Rendimiento : 18.00 Unid.

DESCRIPCIÓN Unid. Cant. FACT Costo Vida Costo x Costo/Pza.


FACTOR INCIDENCIA MO Unit.$ Util Disp. $ (US$/pza.)
1. MANO DE OBRA
Perforistas 1.00 Tarea 1.00 1.00 45.89 45.89
Ayud. Perforista 1.00 Tarea 1.00 1.00 41.30 41.30
Ayud. 1.00 Tarea 1.00 1.00 41.30 41.30
3.00 128.49 7.14
2. IMPLEMENTOS SEGURIDAD
Tareas sin ropa de agua Tar. 3.00 2.69 8.07

8.07 0.45
3. MATERIALES Y HERRAMIENTAS
Barra conica 6' Pza 108 94.60 1,820 5.61
Broca 40 mm Pza 108 25.30 350 7.81
Aceite Perforación Gln. 0.22 9.16 2.02
Perno Helicohidal de 6',tuerca,placa (1x18)=18 Pza. 18 8.12 146.16
Resina (1x18)=18 Cart 18 0.75 13.50
Cembolt (6x18)=108 Cart 108 0.22 23.76
Adaptador para inst perno (1) Pza. 1 88.00 200 0.44
Herramientas de mina Global 1.55
200.84 11.16
5. EQUIPO PERFORACIÓN-LIMPIEZA
perforadora P.P. 108.00 0.24 25.92
Manguera aire 1" Mts. 30.00 2.70 150.00 0.54
Manguera agua 1/2" Mts. 30.00 1.33 150.00 0.27

26.73 1.48
COSTOS DIRECTOS 20.23
COSTOS FIJOS ( van en lista por separado )
20.23
Contingencia 5% 1.01
Utilidad 10% 2.02
COSTO TOTAL (US$/Pza. Con material) 23.26
INSTALACION PERNO HELICOIDAL DE 8' CEMBOL
Solo instalación del perno
Longitud Taladro : 2.40 Mts.
Rendimiento : 15.00 Unid.

DESCRIPCIÓN Unid. Cant. FACT Costo Vida Costo x Costo/Pza.


FACTOR INCIDENCIA MO Unit.$ Util Disp. $ (US$/pza.)
1. MANO DE OBRA
Perforistas 1.00 Tarea 1.00 1.00 45.89 45.89
Ayud. Perforista 1.00 Tarea 1.00 1.00 41.30 41.30
Ayudante 1.00 Tarea 1.00 1.00 41.30 41.30
3.00 128.49 8.57
2. IMPLEMENTOS SEGURIDAD

Tareas sin ropa de agua Tar. 3.00 2.69 8.07


8.07 0.54
3. MATERIALES Y HERRAMIENTAS
Barra conica 8' P.P. 112.50 103.40 1,820 6.39
Broca 40 mm Pza 112.50 25.30 350 8.13
Aceite Perforación Gln. 0.23 9.16 2.11
Perno Helicohidal de 8',tuerca,placa (1x15)=15 Pza. 15.00 9.54 143.10
Resina (2x15)=30 Cart 30.00 0.75 22.50
Cembol (10x15)=150 Cart 150.00 0.22 33.00
Adaptador para inst perno (1) Pza. 1.00 88.00 200 0.44
Herramientas de mina Global 1.55
217.22 14.48
5. EQUIPO PERFORACIÓN-LIMPIEZA
perforadora P.P. 112.50 0.24 27.00
Manguera aire 1" Mts. 30.00 2.70 150 0.54
Manguera agua 1/2" Mts. 30.00 1.33 150 0.27

27.81 1.85
COSTOS DIRECTOS 25.44
COSTOS FIJOS ( van en lista por separado )
25.44
Contingecia 5% 1.27
Utilidad 10% 2.54
COSTO TOTAL (US$/Pza. Con material) 29.26
PERNO HIDRABOLT 5FTS CON EQUIPO

Longitud Taladro : 1.50 Mts.


Rendimiento : 80.00 Unid./gdia (8 horas)

DESCRIPCIÓN Unid. Cant. Costo Vida Costo x Costo/Pza.


Unit.$ Util Disp. $ (US$/pza.)
1. MANO DE OBRA
Operdaor Jumbero Tarea 1.00 64.25 64.25
Ayud. Perforista Tarea 1.00 41.30 41.30
2.00 105.55 1.32
2. IMPLEMENTOS SEGURIDAD
Tareas sin ropa de agua Tar. 2.00 2.69 5.38
5.38 0.07
3. MATERIALES Y HERRAMIENTAS
Barra Extension R32 Pza 400.00 174.90 5,000 13.99
Broca boton R25 x 37mm Pza 400.00 80.30 500 64.24
Shank Adapter hembra Pza 400.00 341.00 11,480 11.88
Perno Hydrabolt 7',tuerca,placa Pza. 80.00 13.92 1,113.60
Herramientas de mina Global 1.55
1,205.26 15.07
5. EQUIPO PERFORACIÓN-LIMPIEZA
Manguera aire 1" Mts. 30.00 2.70 150 0.54
Manguera agua 1/2" Mts. 30.00 1.33 150 0.27
Empernador Bolter 77 con Brazo Enmallador Hrs 6.67 53.06 353.73
354.54 4.43
COSTOS DIRECTOS 20.88

Contingencia 5% 1.04
Utilidad 10% 2.09
COSTO TOTAL (US$/Pza Con material) 24.02
PERNO HIDRABOLT 7FTS CON EQUIPO

Longitud Taladro : 1.80 Mts.


Rendimiento : 70.00 Unid./gdia (8 horas)

DESCRIPCIÓN Unid. Cant. Costo Vida Costo x Costo/Pza.


Unit.$ Util Disp. $ (US$/pza.)
1. MANO DE OBRA
Operdaor Jumbero Tarea 1.00 64.25 64.25
Ayud. Perforista Tarea 1.00 41.30 41.30
2.00 105.55 1.51
2. IMPLEMENTOS SEGURIDAD
Tareas sin ropa de agua Tar. 2.00 2.69 5.38
5.38 0.08
3. MATERIALES Y HERRAMIENTAS
Barra Extension R32 Pza 490.00 174.90 5,000 17.14
Broca boton R25 x 37mm Pza 490.00 80.30 500 78.69
Shank Adapter hembra Pza 490.00 341.00 11,480 14.55
Perno Hydrabolt 7',tuerca,placa Pza. 70.00 13.92 974.40
Herramientas de mina Global 1.55
1,086.33 15.52
5. EQUIPO PERFORACIÓN-LIMPIEZA
Manguera aire 1" Mts. 30.00 2.70 150 0.54
Manguera agua 1/2" Mts. 30.00 1.33 150 0.27
Empernador Bolter 77 con Brazo Enmallador Hrs 5.83 53.06 309.52
310.32 4.43
COSTOS DIRECTOS 21.54

Contingencia 5% 1.08
Utilidad 10% 2.15
COSTO TOTAL (US$/Pza Con material) 24.77
INSTALACION DE MALLA ELECTROSOLDADA

Rendimiento / Gdia. 42.50 M2 Taladros: 50

DESCRIPCIÓN FACTOR
Unid. Cant. FACT Costo Vida Costo x Costo/Pza.
INCIDENCIA MO Unit.$ Util Disp. $ (US$/pza.)
1. MANO DE OBRA
Maestro 1.00 Tarea 1.00 1.00 45.89 45.89
Ayudante 1.00 Tarea 1.00 1.00 41.30 41.30

2.00 87.19 2.05


2. IMPLEMENTOS SEGURIDAD
Implementos Seguridad Tar. 2.00 2.69 5.38

5.38 0.13
3. MATERIALES Y HERRAMIENTAS
Malla Electrosoldada 4'x4' M2 50.00 3.18 1.00 159.00
Cemento Bolsa 1.00 11.42 1.00 11.42
Alambre No16 Kgs 3.00 1.22 1.00 3.66
Grampa de Fe Coruugado 3/8" Pzas 75.00 1.21 1.00 90.75
Herramientas Global 1.55
266.38 6.27
5. EQUIPO PERFORACIÓN-LIMPIEZA
Perforadora P.P. 50.00 0.24 12.00
Barra de 4¨ P.P. 50.00 68.20 $/uni 1.87
Broca de 40 mm PP 50.00 25.30 $/uni 3.61
Manguera aire 1" Mts. 30.00 2.70 150.00 0.54
Manguera agua 1/2" Mts. 30.00 1.33 150.00 0.27
18.29 0.43

COSTOS DIRECTOS 8.88

8.88
Contingencia 5% 0.44
Utilidad 10% 0.89
COSTO TOTAL (US$/M2. Sin material) 10.21

Costo Incluye transporte de la cancha de madera a sus labores a cuenta Contrata


Malla Electrosoldada y todos los materiales es a costo de CMHSA-MARSA
PRECIOS UNITARIOS SHOTCRETE 1"

SHOTCRETE TODO COSTO 1" (DRAMIX: 0 Kgs/M3,10 Kgs/M3, 20 kgs/M3, 30 kgs/M3, 40 kgs/M3)
Avance Mts 2/Cuadrilla...........: 3.00 M3 46.6 m2 15.53 M2/M3

DESCRIPCION UNIDAD CANTID. FACT MO COST./UNIT. INCID U.S.$ U.S.$/Gdia


MANO DE OBRA
Maestro Prepar. Mezcla Tarea - 1.00 43.60 - -
Ayudantes Prep. Mezcla Tarea 2.00 1.00 41.30 0.04 1.77
Maestro Shotcretero Tarea 1.00 1.00 43.60 0.02 0.94
Ayudantes Prep. Shotcre. Tarea - 1.00 41.30 - -
Ayud1 Tarea 1.00 1.00 41.30 0.02 0.89
Operador Scoop Tarea 0.38 1.00 55.07 0.01 0.44
4.38 4.04
IMPLEMENTOS SEGURIDAD Nº Tars.
Tareas con ropa de agua 4.38 2.69 0.09 0.25
- -
0.25
MATERIAL Y HERRAMIENTAS
Otras Herramientas Global 1.00 1.55 1.55
Pesaje material (3x10)=30$ $/M3 - 10.00 -
Cemento (10x3M3)=30 Bolsa 30.00 11.42 342.73
Fibra Acero (0,30,60,90,120 Kgs) Kg 120.00 1.95 234.00
Acelerante (15x3M3)=45 lt 45.00 0.82 36.90
Calibradores (46.60M2x1) Pza 46.60 0.15 6.99
Petroleo(Para Scooptram ) Glns/Hr 3.50 2.00 4.90 34.31
EQUIPOS 656.48 14.09
Scooptram de 4 Yd3. Hrs. 2.00 63.00 126.00
Shotcretera y accesorios Hrs. 3.00 5.84 17.52
143.52 3.08
SUB TOTAL DIRECTOS 21.46

SUB-TOTAL COSTOS DIRECTOS


Contingencia 5% 1.07
Utilidad 10% 2.15
COSTO TOTAL U.S.$/M2. 3.22
24.68
DRAMIX
DRAMIX (0 KGS/M3) 0 18.90
DRAMIX (10 KGS/M3) 30 20.35
DRAMIX (20 KGS/M3) 60 21.79
DRAMIX (30 KGS/M3) 90 23.23
DRAMIX (40 KGS/M3) 120 24.68
PRECIOS UNITARIOS SHOTCRETE 2"

SHOTCRETE TODO COSTO 1" (DRAMIX: 0 Kgs/M3,10 Kgs/M3, 20 kgs/M3, 30 kgs/M3, 40 kgs/M3)
Avance Mts 2/Cuadrilla...........: 3.00 M3 23.03 m2 7.68 M2/M3

DESCRIPCION UNIDAD CANTID. FACT MO COST./UNIT. INCID U.S.$ U.S.$/Gdia


MANO DE OBRA
Maestro Prepar. Mezcla Tarea - 1.00 43.60 - -
Ayudantes Prep. Mezcla Tarea 2.00 1.00 41.30 0.09 3.59
Maestro Shotcretero Tarea 1.00 1.00 43.60 0.04 1.89
Ayudantes Prep. Shotcre. Tarea - 1.00 41.30 - -
Ayud1 Tarea 1.00 1.00 41.30 0.04 1.79
Operador Scoop Tarea 0.38 1.00 55.07 0.02 0.90
4.38 8.17
IMPLEMENTOS SEGURIDAD Nº Tars.
Tareas con ropa de agua 4.38 2.69 0.19 0.51
- -
0.51
MATERIAL Y HERRAMIENTAS
Otras Herramientas Global 1.00 1.55 1.55
Pesaje material (3x10)=30$ $/M3 - 10.00 -
Cemento (10x3M3)=30 Bolsa 30.00 11.42 342.73
Fibra Acero (0,30,60,90,120 Kgs) Kg 120.00 1.95 234.00
Acelerante (15x3M3)=45 lt 45.00 0.82 36.90
Calibradores (23.30M2x1) Pza 23.03 0.15 3.45
Petroleo(Para Scooptram ) Glns/Hr 3.50 2.00 4.90 34.31
652.94 28.35
EQUIPOS
Scooptram de 4 Yd3. Hrs. 2.00 63.00 126.00
Shotcretera y accesorios Hrs. 3.00 5.84 17.52
143.52 6.23
SUB TOTAL DIRECTOS 43.26

SUB-TOTAL COSTOS DIRECTOS


Contingencia 5% 2.16
Utilidad 10% 4.33
COSTO TOTAL U.S.$/M2. 6.49
49.75
DRAMIX
DRAMIX (0 KGS/M3) 0 38.07
DRAMIX (10 KGS/M3) 30 40.99
DRAMIX (20 KGS/M3) 60 43.91
DRAMIX (30 KGS/M3) 90 46.83
DRAMIX (40 KGS/M3) 120 49.75
PRECIOS UNITARIOS SHOTCRETE 3"

SHOTCRETE TODO COSTO 1" (DRAMIX: 0 Kgs/M3,10 Kgs/M3, 20 kgs/M3, 30 kgs/M3, 40 kgs/M3)
Avance Mts 2/Cuadrilla...........: 3.00 M3 15.35 m2 5.12 M2/M3

DESCRIPCION UNIDAD CANTID. FACT MO COST./UNIT. INCID U.S.$ U.S.$/Gdia


MANO DE OBRA
Maestro Prepar. Mezcla Tarea - 1.00 43.60 - -
Ayudantes Prep. Mezcla Tarea 2.00 1.00 41.30 0.13 5.38
Maestro Shotcretero Tarea 1.00 1.00 43.60 0.07 2.84
Ayudantes Prep. Shotcre. Tarea - 1.00 41.30 - -
Ayud1 Tarea 1.00 1.00 41.30 0.07 2.69
Operador Scoop Tarea 0.38 1.00 55.07 0.02 1.35
4.38 12.26
IMPLEMENTOS SEGURIDAD Nº Tars.
Tareas con ropa de agua 4.38 2.69 0.29 0.77
- -
0.77
MATERIAL Y HERRAMIENTAS
Otras Herramientas Global 1.00 1.55 1.55
Pesaje material (3x10)=30$ $/M3 - 10.00 -
Cemento (10x3M3)=30 Bolsa 30.00 11.42 342.73
Fibra Acero (0,30,60,90,120 Kgs) Kg 120.00 1.95 234.00
Acelerante (15x3M3)=45 lt 45.00 0.82 36.90
Calibradores (15.35M2x1) Pza 15.35 0.15 2.30
Petroleo(Para Scooptram ) Glns/Hr 3.50 2.00 4.90 34.31
EQUIPOS 651.79 42.46
Scooptram de 4 Yd3. Hrs. 2.00 63.00 126.00
Shotcretera y accesorios Hrs. 3.00 5.84 17.52
143.52 9.35

SUB TOTAL DIRECTOS 64.84

SUB-TOTAL COSTOS DIRECTOS


Contingencia 5% 3.24
Utilidad 10% 6.48
COSTO TOTAL U.S.$/M2. 9.73
74.56
DRAMIX
DRAMIX (0 KGS/M3) 0 57.03
DRAMIX (10 KGS/M3) 30 61.41
DRAMIX (20 KGS/M3) 60 65.80
DRAMIX (30 KGS/M3) 90 70.18
DRAMIX (40 KGS/M3) 120 74.56
PRECIOS UNITARIOS SIN CONSIDERAR MATERIAL NI EQUIPO
SHOTCRETE VIA HUMEDA 1"

SHOTCRETE TODO COSTO 1" (DRAMIX: 0 Kgs/M3,10 Kgs/M3, 20 kgs/M3, 30 kgs/M3, 40 kgs/M3)
Avance Mts 2/Cuadrilla.................: Rendimiento: 120 m2

DESCRIPCION UNIDAD CANTID. FACT MO COST./UNIT. INCID U.S.$ U.S.$/Gdia


MANO DE OBRA
Maestro Prepar. Mezcla Tarea - 1.00 43.60 - -
Ayudantes Prep. Mezcla Tarea 2.00 1.00 41.30 0.02 0.69
Maestro Shotcretero Tarea 1.00 1.00 43.60 0.01 0.36
Ayudantes Prep. Shotcre. Tarea - 1.00 41.30 - -
Ayud1 Tarea 1.00 1.00 41.30 0.01 0.34
Operador Scoop Tarea 0.38 1.00 55.07 0.00 0.17
4.38 1.57
IMPLEMENTOS SEGURIDAD Nº Tars.
Tareas con ropa de agua 4.38 2.69 0.04 0.10
- -
0.10
MATERIAL Y HERRAMIENTAS
Otras Herramientas Global 1.00 1.55 0.01 0.01
0.01
-
SUB-TOTAL COSTOS DIRECTOS 1.68
Contingencia 5% 0.08
Utilidad 10% 0.17
COSTO TOTAL U.S.$/M2. 1.93
Nota: MATERIALES A COSTO DE CMHSA
PRECIOS UNITARIOS SIN CONSIDERAR MATERIAL NI EQUIPO
SHOTCRETE VIA HUMEDA 2"

SHOTCRETE TODO COSTO 2" (DRAMIX: 0 Kgs/M3,10 Kgs/M3, 20 kgs/M3, 30 kgs/M3, 40 kgs/M3)
Avance Mts 2/Cuadrilla.................: Rendimiento: 60 m2

DESCRIPCION UNIDAD CANTID. FACT MO COST./UNIT. INCID U.S.$ U.S.$/Gdia


MANO DE OBRA
Maestro Prepar. Mezcla Tarea - 1.00 43.60 - -
Ayudantes Prep. Mezcla Tarea 2.00 1.00 41.30 0.03 1.38
Maestro Shotcretero Tarea 1.00 1.00 43.60 0.02 0.73
Ayudantes Prep. Shotcre. Tarea - 1.00 41.30 - -
Ayud1 Tarea 1.00 1.00 41.30 0.02 0.69
Operador Scoop Tarea 0.38 1.00 55.07 0.01 0.34
4.38 3.14
IMPLEMENTOS SEGURIDAD Nº Tars.
Tareas con ropa de agua 4.38 2.69 0.07 0.20
- -
0.20
MATERIAL Y HERRAMIENTAS
Otras Herramientas Global 1.00 1.55 0.02 0.03
0.03
-
SUB-TOTAL COSTOS DIRECTOS 3.36
Contingencia 5% 0.17
Utilidad 10% 0.34
COSTO TOTAL U.S.$/M2. 3.86
Nota: MATERIALES A COSTO DE CMHSA
PRECIOS UNITARIOS SIN CONSIDERAR MATERIAL NI EQUIPO
SHOTCRETE VIA HUMEDA 3"

SHOTCRETE TODO COSTO 3" (DRAMIX: 0 Kgs/M3,10 Kgs/M3, 20 kgs/M3, 30 kgs/M3, 40 kgs/M3)
Avance Mts 2/Cuadrilla.................: Rendimiento: 44.83 m2

DESCRIPCION UNIDAD CANTID. FACT MO COST./UNIT. INCID U.S.$ U.S.$/Gdia


MANO DE OBRA
Maestro Prepar. Mezcla Tarea - 1.00 43.60 - -
Ayudantes Prep. Mezcla Tarea 2.00 1.00 41.30 0.04 1.84
Maestro Shotcretero Tarea 1.00 1.00 43.60 0.02 0.97
Ayudantes Prep. Shotcre. Tarea - 1.00 41.30 - -
Ayud1 Tarea 1.00 1.00 41.30 0.02 0.92
Operador Scoop Tarea 0.38 1.00 55.07 0.01 0.46
4.38 4.20
IMPLEMENTOS SEGURIDAD Nº Tars.
Tareas con ropa de agua 4.38 2.69 0.10 0.26
- -
0.26
MATERIAL Y HERRAMIENTAS
Otras Herramientas Global 1.00 1.55 0.02 0.03
0.03
-
SUB-TOTAL COSTOS DIRECTOS 4.49
Contingencia 5% 0.22
Utilidad 10% 0.45
COSTO TOTAL U.S.$/M2. 5.17
Nota: MATERIALES A COSTO DE CMHSA
FORMATO DE PRECIOS UNITARIOS DE NICHO TABLERO

CONSORCIO MINER0 HORIZONTE S.A.


NICHO PARA TABLERO ELECTRICO 0.60m x 0.60m N° Taladros: 30.00 u
Long. Perfor.: 2.00 pies
AVANCE: 1.00 Unid

ITEM DESCRIPCION INCID UNI. CANTID. PRECIO SUBTOT. TOTAL


UNITARIO $ US$/UNID
1.- MANO DE OBRA
Perforista 0.50 Tareas 1.00 45.89 $/Tarea 22.95
Ayudante Perforista 0.50 Tareas 1.00 41.30 $/Tarea 20.65

43.60 43.60
2.- IMPLEMENTOS
Implementos Tareas 2.00 2.69 5.38
5.38 5.38
3.- MATERIALES Y HERRAMIENTAS
Barra de 6¨ P.P. 60.000 94.60 $/uni 3.12
Broca de 40 mm PP 60.000 25.30 $/uni 4.34
Aceite de Perforación Gln 0.250 9.16 $/uni 2.29
Herramientas de Mina-Barretillas Global $/uni 1.01
10.76 10.76
4.- EQUIPOS
Perforadora P.P. 60.00 0.240 $/pp 14.40
Manguera Aire 1¨ Mts. 30.00 2.70 $/hr 0.54
Manguera Agua 1/2¨ Mts. 30.00 1.33 $/hr 0.27

15.21 15.21
74.94
6.- GASTOS INDIRECTOS
Contingencias 3% $ 2.25
Gastos Generales 0% $ 0.00
Utilidad 10% $ 7.49
TOTAL COSTO EN DOLARES (US$/UNIDAD) 84.68
Energía Eléctrica, Tuberias, accesorios proporciona Cía. 146.94
138.33
COSTO DE TAREA ADMINISTRATIVA

DESCRIPCIÓN Unid. Cant. Costo Costo x Costo/Tarea.


Unit.$ Tarea (US$/Tarea)
1. Mano de Obra
Ayudante Perforista Tarea 1.00 51.05 51.05
SUB TOTAL 51.05 51.05 51.05

IMPLEMENTOS SEGURIDAD MINEROS SUBTERRANEO


DESCRIPCION UNID. CANTIDAD PRECIO VIDA ECON. COSTO UNITARIO
US$/UNIDAD (Disparos) POR DISPARO
Botas de Jebe Punta Acero Par 1.00 19.57 183.00 0.11
Casco Tipo Sombrero Portalampara con orejera Pza 0.00 51.47 1,095.00 0.00
Faja Ergonomica de proteccion lumbar Pza 0.00 7.11 183.00 0.00
Chaleco de malla con cinta reflectiva Uni 1.00 7.34 90.00 0.08
Casco Tipo Sombrero Portalámpara Pza 1.00 11.32 1,095.00 0.01
Barbiquejo Elástico Gancho Metálico SEKUR Uni 1.00 0.68 90.00 0.01
Respirador Pza 1.00 23.13 365.00 0.06
Filtro Uni 2.00 3.18 7.00 0.91
Cartucho para gases Uni 0.00 4.52 365.00 0.00
Retenedor Uni 2.00 2.63 365.00 0.01
Guante de cuero Par 1.00 3.30 7.00 0.47
Correa Portalámpara Faja Plana 1 1/2" Uni 1.00 3.63 365.00 0.01
Tapón de Oido Par 1.00 0.63 45.00 0.01
Mameluco Jean Uni 1.00 18.67 183.00 0.10
Pantalón de Jebe Uni 1.00 12.56 90.00 0.14
Casaca de Jebe Uni 1.00 12.56 90.00 0.14
Lámpara Uni 1.00 17.00 30.00 0.57
Anteojos de cristal endurecido Uni 1.00 5.20 120.00 0.04
Cordón Sujetador de Anteojos Uni 0.00 2.28 183.00 0.00
Tafilete de 4 Puntas (Suspensión ECO V) Uni 1.00 4.21 365.00 0.01
SUB-TOTAL 2.69

HERRAMIENTAS 1.38
COSTOS DIRECTOS SUB-TOTAL 55.12

IMPREVISTOS (Alimentacion S/10.5, Pasaje) 3.75


UTILIDAD Y CONTINGENCIAS 10.00% 5.51
COSTOS INDIRECTOS SUB-TOTAL 9.26

COSTO TOTAL (US$/TAREA) 64.38


IMPLEMENTOS DE SEGURIDAD EMPLEADOS

DESCRIPCION UNID. CANTIDAD PRECIO VIDA ECON. C. UNIT. C.UNIT.


US$/UNIDAD (guardias) POR TAREA C/ropa agua
Botas de Jebe Punta Acero Par 1.00 19.57 90.00 0.22 0.22
Casco Tipo Sombrero Portalampara con orejera Pza 0.00 51.47 300.00 0.00 0.00
Faja Ergonomica de proteccion lumbar Pza 0.00 7.11 180.00 0.00 0.00
Casco Tipo Sombrero Portalámpara Pza 1.00 11.32 360.00 0.03 0.03
Barbiquejo Elástico Gancho Metálico SEKUR Uni 1.00 0.68 90.00 0.01 0.01
Respirador Pza 1.00 23.13 365.00 0.06 0.06
Filtro Par 2.00 3.18 25.00 0.25 0.25
Cartucho para gases Par 1.00 4.52 25.00 0.18 0.18
Retenedor Par 2.00 2.63 150.00 0.04 0.04
Guante de cuero Par 1.00 3.30 15.00 0.22 0.22
Correa Portalámpara Faja Plana 1 1/2" Uni 1.00 3.63 365.00 0.01 0.01
Tapón de Oido Par 1.00 0.63 45.00 0.01 0.01
Mameluco Jean Uni 1.00 18.67 183.00 0.10 0.10
Pantalón de Jebe Uni 1.00 12.56 75.00 0.17
Casaca de Jebe Uni 1.00 12.56 75.00 0.17
Lámpara Uni 1.00 17.00 30.00 0.57 0.57
Anteojos Uni 1.00 5.20 120.00 0.04 0.04
Cordón Sujetador de Anteojos Uni 1.00 2.28 150.00 0.02 0.02
Tafilete de 4 Puntas (Suspensión ECO V) Uni 1.00 4.21 365.00 0.01 0.01
Zapato Seguridad Uni 1.00 30.57 365.00 0.08 0.08

SUB-TOTAL 1.86 2.19


HERRAMIENTAS

DESCRIPCION UNID. CANTIDAD PRECIO VIDA ECON. COSTO UNITARIO


$/UNIDAD (Disparos) POR DISPARO
Corvina Pzas 1.00 51.70 150.00 0.34
Lampa Pzas 2.00 9.39 50.00 0.38
Pico Pzas 2.00 10.90 50.00 0.44
Combo 6 Lbs Pzas 1.00 7.83 75.00 0.10
Llave Stilson de 8" Pzas 1.00 4.79 150.00 0.03
LLave Francesa 8" Pzas 1.00 5.90 150.00 0.04
Azuela Pzas 1.00 9.24 150.00 0.06
Chotana Pzas 2.00 11.18 100.00 0.22
1.62

DESCRIPCION UNIDAD VALOR


Herramientas Avances U.S.$/Disp 1.21
Herramientas Sostenimiento U.S.$/Disp 1.55
1.38
CALCULO COSTO TRANSPORTE MATERIAL CON SCOOP EN TODA LABOR SUBTERRANEA

TIEMPOS

DESCRIPCION UNIDAD CARGUIO IDA CARGADO


DESCARGA VUELTA VACIO CICLO OBSERVACION

Muestras:11 Minutos 0.75 1.00 0.40 0.74 2.89 100.00 MTS

TIEMPO VARIABLE
Velocidad Cargado (Espacio/Tie 100.00 Mts/Minuto 6.00 Km/Hr
Velocidad Vacio (Espacio/Tiempo 135.14 Mts/Minuto 8.11 Km/Hr

TIEMPOS FIJOS
CARGUIO Minutos 0.75
DESCARGA Minutos 0.40
TIEMPOS MUERTOS Minutos 0.50
SUB TOTAL 1.15

SIMULACION DE TIEMPOS Y COSTOS NO


DISTANCIA(Mts) 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00 500.00 550.00 600.00 650.00 700.00 750.00 800.00 850.00 900.00 950.00 1,000.00
Tiempo Ida (Cargado) 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 5.50 6.00 6.50 7.00 7.50 8.00 8.50 9.00 9.50 10.00
Tiempo Vuelta (Vacio) 0.37 0.74 1.11 1.48 1.85 2.22 2.59 2.96 3.33 3.70 4.07 4.44 4.81 5.18 5.55 5.92 6.29 6.66 7.03 7.40
Total CICLO (FIJO+VARIABLE)
Minutos 2.02 2.89 3.76 4.63 5.50 6.37 7.24 8.11 8.98 9.85 10.72 11.59 12.46 13.33 14.20 15.07 15.94 16.81 17.68 18.55
No Viajes Cucharas/Hora 29.70 20.76 15.96 12.96 10.91 9.42 8.29 7.40 6.68 6.09 5.60 5.18 4.82 4.50 4.23 3.98 3.76 3.57 3.39 3.23
M3/HORA (INSITU: Medido
Topograficamente) 61.32 42.86 32.94 26.75 22.52 19.44 17.11 15.27 13.79 12.57 11.55 10.69 9.94 9.29 8.72 8.22 7.77 7.37 7.01 6.68
COSTO SCOOP 4 Yds3 U.S.
$/Hr 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00 63.00
Petroleo 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16 17.16
COSTO SCOOP 4 Yds3 U.S.
$/Hr 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16 80.16
Operador 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88
Implementos de seguridad 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34 0.34
Total 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38 87.38
COSTO U.S.$/M3 1.43 2.04 2.65 3.27 3.88 4.49 5.11 5.72 6.34 6.95 7.56 8.18 8.79 9.40 10.02 10.63 11.25 11.86 12.47 13.09
COSTO U.S.$/TMS 0.48 0.68 0.88 1.09 1.29 1.50 1.70 1.91 2.11 2.32 2.52 2.73 2.93 3.13 3.34 3.54 3.75 3.95 4.16 4.36

CAPACIDAD CUCHARA SCOOPTRAM


Yds 4.00
1 Yda 3 de carguio = 0.764554 M3 0.76
M3 INSITU/CUCHARA 2.06
TMS POR CUCHARA 6.19
Empernador BOLTER 77 con Brazo enmallador
DATOS
DESCRIPCION UNID. 10 M3
PRECIO STOCK LIMA U.S.$ $393,500.00
VALOR RESCATE (20%) U.S.$ $78,700.00
VALOR NETO EQUIPO U.S.$ $314,800.00
VIDA ECONOMICA EN HORAS(12*25*60) HRS 18,000.00
HRS POR MES HRS 450.00
VIDA ECONOMICA EN AÑOS UNID 5.00

DEPRECIACION DE EQUIPOS

COSTO DE POSESION
DEPRECIACION U.S.$/HR 17.49
C.INTERESES,SEGUROS E IMPUESTOS U.S.$/HR 9.42

SUB-TOTAL COSTO POSECION U.S.$/HR 26.91

COSTO DE OPERACIÓN
Repuestos y Mantenimiento U.S.$/HR 16.00
Neumaticos U.S.$/HR 4.00
Petroleo (1 Gln x Hr) U.S.$/HR 4.90
Mecanico (30%) U.S.$/HR 1.25
SUB-TOTAL OPERACIONES U.S.$/HR 26.15

TOTAL (OPERACIÓN+DEPRECIACION) U.S.$/HR 53.06


RESEMIN
Galvani 356, Urb. Ind. Santa Rosa , Ate, Lima – Perú
Telf. 51-1-2034404
E-mail : james.valenzuela@resemin.com
Web: www.resemin.com
Rs-164-10
Lima, 12 de Marzo 2010

Señores
VOLCAN CIA MINERA S.A.A.
Presente
At. Mario de las Casas

Jumbo Empernador BOLTER 77


Equipo de perforación automatizado, para empernado y enmallado mecanizado en operaciones de sostenimiento
en minas subterráneas. Fabricado y probado en nuestros talleres en Lima. Ver catálogo adjunto.

Sistema de perforación
· Columna Empernación compuesta de dos vigas, una que perfora y otra que instala los pernos
· Ambas vigas rotan respecto a un Pivot central que ancla en la roca y, a su vez, sujeta la malla
· Powerpack de 50kW
· Brazo con extensión telescópica y Unid. Rotación 360° de alto torque Helac-USA
· Sistema hidráulico de perforación y empernado
· Una perforadora Montabert HC50 en la Viga de perforación
· Kit para pernos Hydrabolt
Carrier
· Chasis articulado, 4WD, eje trasero oscilante 16º
· Motor Deutz F5L912W con turbo
· Transmisión hidrostática marca Poclain-Francia: Una bomba, cuatro motores
de pistones radiales, uno en cada rueda.
· Bombas hidráulicas Rexroth A10V071 y Parker- Commercial
· Freno de servicio: a través del mismo sistema hidrostático
· Freno de parqueo: SAHR, accionado hidráulicamente
· Cuatro (4) gatos hidráulicos de estabilización, los delanteros con extensión lateral 0.60mts
· Llanta y aro de repuesto
· Incluye Manual de Partes, Operación y Mantenimiento (2 copias)
· Dimensiones:
Ancho: 1.68mts
Alto: 2.20mts
Largo: 8.80mts
Peso: 11,200 Kgs
Kits incluidos:
· Para pernos Hydrabolt exclusivamente
Precio unitario……………………………..……………………USD $393,500.00
Capacidades y Productividad:
· El equipo propuesto tiene la capacidad para realizar sostenimiento mecanizado en labores con alturas
de techo en el rango 3.00 hasta 5.50mts.
· Puede instalar pernos Split set y Mecánicos de 7 pies
· Para pernos con lechada de cemento, Hydrabolt y pernos de resina se requiere adquirir los
correspondientes Kits que se cotizan como opcionales más adelante.
· Su productividad puede ser hasta 7,000 pernos/ mes y enmallado mecanizado. Este rendimiento depende de las
condiciones de operación como lejanía de las labores entre sí, características de la roca, disponibilidad de servicios
en interior de mina, etc. Con todas estas limitaciones, lo normal es un rendimiento entre 2,500 a 5,000 pernos/ mes
Entrega del equipo y entrenamiento de operadores:
Durante 30 días, a través de un Técnico especializado. El cliente asume el alojamiento y alimentación
Tiempos de instalación: (pernos de 7 pies)
- Split set: 2 minutos
- Helicoidal: 4 minutos (con lechada de cemento y/ó resina)
- Hydrabolt: 2 minutos
OPCIONALES:

Perforadora HC20 (Para helichohida)…….……………………………………………USD 24,000


Para instalar Split set y helicoidales
Kit pernos con lechada de cemento…………………………………………………..USD 15,000
Incluye:
- Bomba de concreto, manguera y controles
- Extensión hidráulica para el inyector
Kit Lanzador de cartuchos de resina…….…………………………………………….USD 15,000
- Sistema inyector neumático –lanzador-
- Compresor de 45 cfm@100psi y pulmón de aire
Valores indicados no incluyen IGV
CONDICIONES:
· Forma de pago: 40% adelanto con su OC, saldo a la entrega del equipo
· Tiempo de Entrega: Primero. 100 días
Segundo: 130 días
Tercero: 150 días
Nota: Estos períodos de entrega se cuentan a partir de fecha recepción
Orden de compra y el adelanto
· Garantía: Un año de operación o 2,000 horas, lo que ocurra primero
No se incluye en la garantía los repuestos de común desgaste
James Valenzuela Murillo Director Gerente
· Validez Presupuesto Cel.9-9970-1296; Directo RESEMIN
de la Oferta: preparado 326-4569 james.valenzuela@resemi
30 días. por: n.com

You might also like