sand plant

ID Task Task Name Duration Start Finish Predecessors Feb '18 Mar '18 Apr '18 May '18 Jun '18 Jul '18
Mode 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16
1 Sand Plant Civil Work 120 days Wed 2/14/18Tue 6/26/18 74%
2 Phase-A 90 days Wed 2/14/18Wed 5/16/18 99%
3 Fixed Inertia Shaker 11 days Wed 2/14/18Sat 2/24/18 100%
4 Conveyor Tunnel 15 days Wed 2/14/18Wed 2/28/183SS 100%
5 Electrical Room Columns 15 days Thu 3/1/18 Thu 3/15/18 4 100%
6 Dust Collector-A Platform 60 days Fri 3/16/18 Wed 5/16/185 100%
7 Pneumatic Feeder 22 days Mon 3/5/18 Mon 3/26/186SS 100%
8 Muller-A Footing 27 days Sun 3/25/18 Fri 4/20/18 7 100%
9 Slope Conveyor Plates 27 days Tue 3/20/18 Sun 4/15/18 8 100%
10 Muller-A Columns 15 days Sun 4/1/18 Sun 4/15/18 9SS 100%
11 Muller A&B Discharge Conveyor
10 days Sun 4/15/18 Tue 4/24/18 10 100%
12 Phase-B 61 days Sat 4/14/18 Tue 6/26/18 28%
13 Demolition & Relocation 6 days Sat 4/14/18 Thu 4/19/18 11 100%
14 Elevator-A Pit 12 days Fri 4/20/18 Tue 5/1/18 13 75%
15 Muller-B Footing 12 days Tue 5/1/18 Mon 5/14/1814 50%
16 Muller-B Columns 25 days Tue 5/1/18 Wed 5/30/1815 50%
17 Dismantling Works 7 days Tue 5/15/18 Tue 5/22/18 13 0%
18 Dust Collector-B Platform 21 days Wed 5/23/18Wed 6/20/1817 0%
19 Elevator-B Pit 10 days Wed 5/23/18Tue 6/5/18 18SS 0%
20 Hexagone Sieve Hopper 7 days Wed 5/23/18Thu 5/31/18 19SS 0%
21 Sand Cooler 10 days Fri 6/1/18 Thu 6/14/18 20 0%
22 SK60 Cooler Fan 8 days Fri 6/15/18 Tue 6/26/18 21 0%
23 End of Civil Work 0 days Tue 6/26/18 Tue 6/26/18 22 6/26

Critical Manual Task Baseline Milestone External Tasks

Critical Split Start-only Milestone External Milestone

Critical Progress Finish-only Summary Progress Inactive Task

Task Duration-only Summary Inactive Milestone

Split Baseline Manual Summary Inactive Summary

Task Progress Baseline Split Project Summary Deadline

Page 1
sand plant
Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19 Jun '19 Jul '19 Aug '19 Sep '19 Oct '19
16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7

6/26

Critical Manual Task Baseline Milestone External Tasks

Critical Split Start-only Milestone External Milestone

Critical Progress Finish-only Summary Progress Inactive Task

Task Duration-only Summary Inactive Milestone

Split Baseline Manual Summary Inactive Summary

Task Progress Baseline Split Project Summary Deadline

Page 2

You might also like