Aρ2 + Bρ + C = 0
dimana :
0,6 x ( 1 - ∂ )2 x fy2
A =
fc'
= 944
B = - [ { (1-∂) x fy } + {∂ x fy x (1-d'/d) } ]
= -350
C = Mu
Ø x b x d2
= 0,290446
* tulangan tarik
As = ρ x b x d
= 58,21989 mm2
* tulangan tekan
As' = ∂ x ρ x b x d
= 29,10994 mm2
* tulangan tarik
n = As
As1
= 0,438626 ≈ 2 batang
* tulangan tekan
n' = As'
As1
= 0,219313 ≈ 2 batang
Diketahui:
Mu = 3,253 kN m
b = 350 mm
h = 250 mm
d' = 50 mm
d = 200 mm
fc' = 25 MPa
fy = 400 MPa
∂ = 0,5 (rasio tulangan tekan dan tarik untuk daerah rawan gempa)
D = 13 mm (diameter tulangan)
2
As1 = 132,732 mm
Aρ2 + Bρ + C = 0
dimana :
0,6 x ( 1 - ∂ )2 x fy2
A =
fc'
= 944
B = - [ { (1-∂) x fy } + {∂ x fy x (1-d'/d) } ]
= -350
C = Mu
Ø x b x d2
= 0,290446
* tulangan tarik
As = ρ x b x d
= 58,21989 mm2
* tulangan tekan
As' = ∂ x ρ x b x d
= 29,10994 mm2
* tulangan tarik
n = As
As1
= 0,438626 ≈ 1 batang
* tulangan tekan
n' = As'
As1
= 0,219313 ≈ 2 batang
Kolom
b = 400 mm
h = 400 mm
D = 13 mm (Diameter Tulangan)
f'c = 25 Mpa
fy = 400 MPa
d = 350 mm
d' = 50 mm
n.tul = 8 bh ( Jumlah Tulangan )
y = 200 mm
Pn(max) = 0,8 x Po
= 0,8 x 3802,17884
= 3041,74307 kN
eksentrisitas minimum
emin = 0,1 x h
= 0,1 x 400
= 40 mm
= 1517250 N
= 1517,25 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 350
600 + 400
= 210 mm
ab = 0,85 x Cb
= 0,85 x 210
= 178,5 mm
= 600 x 210 - 50
[ ]
210
= 457,142857
fs' ≥ fy → fs' = fy = 400
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 400
= 231746936,5 Nmm
= 231,7469365 kNm
eb = Mnb
Pnb
= 0,152741431 m
= 152,7414312 mm
ɸ x Pnb = 986,2125 kN
ɸ x Mnb = 185,39755 kN
Mn = As x fy ( d - 0,59 x As x fy )
fc' x b
= 71,6690805 kNm
8000
P M ɸP ɸM
7000
3802 0 2471 0
60003042 71,7 1977 57,3
1517 232 986,2 185
Mn Vs Pn
5000 0 71,7 0 57,3
PN,φPN
ɸMn vs ɸPn
4000
0 0 ɸMnb vs ɸPnb
986,2
3000
185 Data P vs M3
Data P vs M2
2000
1000
0
0 50 100 150 200 250
MN, φMN
KAPASITAS GESER KOLOM 40X40