Why?
° Heavy loading of production holes causes;
- heavy damage to rock
~ overbreak and loose rock
* Overbreak extends to quite a depth back into the
face
BEFORE AFTER
}- BLAST HOLE nn BACK DAMAGE
@ BURDEN tan
zo
|_ MUCK PILE
There are 6 Basic Perimeter
Blasting Techniques
Line drilling
Trim blasting
Smooth walling
Buffer blasting
. Pre-splitting
. Fracture control technique
Omar wns
We are going to concentrate on Pre-SplittingLine Drilling
The first type of overbreak control technique
developed
Holes drilled at close spacing, up to 3 or 4 times
the hole diameter
Drilled along a line
Theory - acts like the perforations in toilet paper
Rock breaks to a final face along the line of these
holes