You are on page 1of 28

CHAPTER 14

INVENTORY MANAGEMENT
QUESTIONS FOR WRITING AND DISCUSSION

1. Ordering costs are the costs of placing and 11. JIT manufacturing is a demand-pull ap-
receiving an order. Examples include clerical proach to manufacturing. It differs from tradi-
costs, documents, insurance, and unloading. tional manufacturing by significantly reduc-
2. Setup costs are the costs of preparing ing reliance on inventories, forming
equipment and facilities so that they can be manufacturing cells, using interdisciplinary
used for producing a product or component. labor, decentralizing services, and adopting
Examples include wages of idled production a philosophy of total quality management.
workers, lost income, and the costs of test 12. Manufacturing cells are collections of ma-
runs. chines and labor dedicated to the production
3. Carrying costs are the costs of carrying in- of a single product or subassembly. Each
ventory. Examples include insurance, taxes, cell is capable of performing a variety of op-
handling costs, and the opportunity cost of erations. This differs from the departmental
capital tied up in inventory. organization where a collection of the same
4. Stockout costs are the costs of insufficient machines is used to perform the same oper-
inventory (e.g., lost sales and interrupted ation on multiple products.
production). 13. By forming manufacturing cells that are
5. As ordering costs decrease, fewer and larg- dedicated to a single product, all costs as-
er orders must be placed. This, in turn, in- sociated with the cell are traceable to the
creases the units in inventory and, thus, in- product. Machinery and services that for-
creases carrying costs. merly belonged to several products now be-
long only to a single product. For example,
6. Reasons for carrying inventory include the depreciation, material handling, and main-
following: (a) to balance setup and carrying tenance become direct product costs.
costs; (b) to satisfy customer demand; (c) to
avoid shutting down manufacturing facilities; 14. JIT hedges against future price increases
(d) to take advantage of discounts; and (e) and obtains lower input prices (better usually
to hedge against future price increases. than quantity discounts) by the use of long-
7. The economic order quantity is the amount term contractual relationships with suppliers.
that should be ordered so as to minimize the Suppliers are willing to give these breaks so
sum of ordering and carrying costs. that they can reduce the uncertainty in the
demand for their products.
8. Reorder point = 3 × 12 = 36 units; Safety
stock = 3(15 – 12) = 9 units 15. EDI, or electronic data interchange, allows
suppliers to have access to a buyer’s data-
9. Safety stock is simply the difference be- base. Information on the buyer’s database is
tween maximum demand and average de- used to determine when supplies should be
mand, multiplied by the lead time. By reor- delivered. When supplies arrive, their receipt
dering whenever the inventory level hits the
is noted electronically, and payment is in-
safety stock point, a company is ensured of
itiated. No paperwork is involved. Conti-
always having sufficient inventory on hand
to meet demand. nuous replenishment is where suppliers are
given responsibility to replenish the buyer’s
10. JIT minimizes carrying costs by driving in- inventory stock. EDI facilitates this by pro-
ventories to insignificant levels. Ordering viding information (electronically) needed by
costs are minimized by entering into long- the supplier to make replenishment deci-
term contracts with suppliers (or driving se- sions.
tup times to zero).
16. Shutdowns in a JIT environment are avoided
by practicing total preventive maintenance

473
and total quality control and by developing tion spends in turning inventories into
close relationships with suppliers to ensure throughput. The objective is to maximize
on-time delivery of materials. Internally, a throughput and minimize inventory and op-
Kanban system is used to ensure the timely erating expenses.
flow of materials and components.
21. Lower inventories mean that a company
17. The Kanban system is used to ensure that must pay attention to higher quality — it can-
parts or materials are available when not afford to have production go down be-
needed (just in time). The flow of materials cause of defective parts or products. It also
is controlled through the use of markers or means that improvements can reach the
cards that signal production of the neces- customer sooner. Lower inventories mean
sary quantities at the necessary time. less space, less overtime, less equipment—
in short, lower costs of production and, thus,
18. Constraints represent limited resources or
lower prices are possible. Lower inventories
demand. Internal constraints are limiting fac-
also mean (usually) shorter lead times and
tors found within the firm. External con-
better ability then to respond to customer
straints are limiting factors imposed on the
requests.
firm from external sources.
22. Following are the five steps that TOC uses
19. Loose constraints are those where the prod-
to improve organizational performance: (1)
uct mix chosen does not consume all the
identify constraints, (2) exploit binding con-
available resources. A binding constraint is
straints, (3) subordinate everything else to
one where the product mix uses all the li-
decisions made in Step 2, (4) elevate bind-
mited resource.
ing constraints, and (5) repeat process.
20. Following are three measures of organiza-
23. The drum is the binding constraint that sets
tional performance used by the theory of
the production rate in the factory. The rope
constraints: throughput— the rate at which
simply means that the release of materials
an organization generates money; invento-
to the first process is tied to the rate of the
ry — the money an organization spends in
drummer constraint. The buffer is an amount
turning materials into throughput; and oper-
of inventory placed in front of the drummer
ating expenses — the money the organiza-
process to protect throughput.

474
EXERCISES

14–1

1. Annual ordering cost = PD/Q


= $600 × 30,000/6,000
= $3,000

2. Annual carrying cost = CQ/2


= $4 × 6,000/2
= $12,000

3. Cost of current inventory policy = Ordering cost + Carrying cost


= $3,000 + $12,000
= $15,000

14–2

1. EOQ = 2PD/C
= (2 × 40 × 800,000)/4
= 16,000,000
= 4,000

2. Number of orders = D/Q = 800,000/4,000 = 200

3. Ordering cost = P × Number of orders


= $40 × 200
= $8,000
4. Carrying cost = CQ/2
= $4 × 4,000/2
= $8,000
5. Total cost = $8,000 + $8,000
= $16,000

6. Ordering cost = P × Number of orders = $40 × (800,000/8,000) = $4,000

Carrying cost = CQ/2 = $4 × (8,000/2) = $16,000

Inventory cost savings at EOQ = ($ 4,000 + $16,000) − $16,000 = $4,000

475
14–3

1. EOQ = 2PD/C
= (2 ×100 × 6,250)/5
= 250,000
= 500

2. Carrying cost = CQ/2


= $5 × 500/2
= $1,250
Setup cost = PD/Q
= $100 × 6,250/500
= $1,250

14–4

1. Reorder point = Average rate of usage × Lead time


= 8,000 × 3
= 24,000 pounds

2. Maximum usage 12,000


Average usage 8,000
Difference 4,000
Lead time × 3
Safety stock 12,000
Reorder point = (Average rate of usage × Lead time) + Safety stock
= (8,000 × 3) + 12,000
= 36,000 pounds

476
14–5

1. Maximum daily usage 2,350


Average daily usage 2,000
Difference 350
Lead time × 4
Safety stock 1,400
Reorder point = (Average rate of usage × Lead time) + Safety stock
= (2,000 × 4) + 1,400
= 9,400 units
2. Maximum setup time in days 5
Average setup time in days 4
Difference in days 1
Average daily usage × 2,000
Safety stock 2,000
Reorder point = (Rate of usage × average lead time) + Safety stock
= (2,000 × 4) + 2,000
= 10,000 units

477
14–6

1. EOQ = 2PD/C
= (2 × 4,000 × 324,000)/2
= 1,296,000,000
= 36,000 (batch size for lawn mower engines)

2. Setup cost = PD/Q


= $4,000 × 324,000/36,000
= $36,000
Carrying cost = CQ/2
= $2 × 36,000/2
= $36,000
Total cost = $72,000 ($36,000 + $36,000)

3. ROP = Average daily sales × Lead time


ROP = 1,296 × 11 = 14,256 lawn mower engines

4. EOQ = 2PD/C
= (2 × 7,200 × 750,000)/3
= 3,600,000,000
= 60,000 (batch size for jet ski engines)
Setup cost = $7,200 × 750,000/60,000
= $90,000
Carrying cost = $3 × 60,000/2
= $90,000
Total cost = $180,000 ($90,000 + $90,000)
ROP = 1,500 × 12 = 18,000 jet ski engines

478
14–6 Concluded

5. Lawn mowers require 9 batches per year (324,000/36,000). Jet ski engines re-
quire 12.5 batches per year (750,000/60,000). The lead time for the lawn mower
engines is 11 days and that of the jet ski engines is 12 days. Thus, the total
work days needed to produce the annual demand is 249 [(11 × 9) + (12 ×
12.5)]. Since there are 250 work days available each year, it is possible to
meet the annual demand. Given the initial inventory levels of each product,
the daily and annual demand, and the lead times, Shields must build a sche-
dule that coordinates production, inventory usage, and sales. This is a push
system because production and inventory use anticipated demand rather
than current demand.

14–7

1. Cost for 2-day setup = $4,000


Cost for 0.5 day setup = 0.25 × $4,000 = $1,000
Cost of 0.05 day setup = 0.10 × $1,000 = $100

EOQ = (2 × 324,000 × 1,000)/2


= 324,000,00 0
= 18,000 lawn mower engines

EOQ = (2 × 324,000 × 100)/2


= 32,400,000
≈ 5,692 lawn mower engines

2. The batch size decreases as the setup time and cost decrease. If the setup
time is 0.05 day (about 1 hour), then the firm can produce 4,000 × 0.95 = 3,800
units per day, sufficient to meet the combined daily demand for the two en-
gines. This implies the ability to produce on demand and eliminates the need
to carry finished goods inventory, a JIT objective.

479
14–8

1. JIT does not accept setup (or ordering) costs as a given; rather, JIT at-
tempts to drive these costs to zero through reducing the time it takes to
set up and by developing long-term contracts with suppliers. Carrying
costs are minimized by reducing inventories to insignificant levels.
2. JIT reduces lead times, which increases a firm’s ability to meet requested
delivery dates. This is accomplished by (1) reduction of setup times, (2)
improved quality, and (3) cellular manufacturing.
3. The problems that usually cause shutdowns are (1) machine failure, (2) de-
fective material or subassembly, and (3) unavailability of a material or
subassembly, or (4) late delivery of parts. JIT attempts to solve each of the
four problems by emphasizing total preventive maintenance and total
quality control (strives for zero defects) and building the right kind of rela-
tionship with suppliers.
4. Unreliable production processes are addressed by total quality man-
agement. As fewer and fewer defective units are produced, there is less
and less need for inventory to replace nonconforming units.
5. The objective of taking advantage of discounts is to lower the cost of in-
ventory. JIT accomplishes the same objective by negotiating long-term
contracts with a few chosen suppliers and establishing more extensive
supplier involvement.
6. JIT emphasizes long-term contracts that stipulate prices and acceptable
quality levels.

2. JIT has the policy of stopping production if a problem is detected so that the
problem can be corrected (of course, the problem may also cause production
to stop, independent of a policy or practice of stopping so that the source of
the problem can be corrected). Since JIT produces on demand, any interrup-
tion of production means that throughput is lost. TOC uses a time buffer lo-
cated in front of the binding constraint to protect throughput. The time buffer
is designed to keep the constrained resource busy for a specified period of
time, a time long enough to overcome most disruptions in production.

480
14–9

1. The withdrawal Kanban controls movement of work among the manufacturing


processes. It specifies the quantity that a subsequent process should with-
draw from the preceding process.

2. The production Kanban also controls movement of work among the manufac-
turing processes. It specifies the quantity that the preceding process should
produce.

3. The vendor Kanban controls movement of parts between the processes and
outside suppliers. It is used to notify suppliers to deliver more parts.

14–10

The phrase “implementing JIT” conveys to many the notion that one day a com-
pany is conventional and the next day it is JIT with all of the benefits that are typ-
ically assigned to JIT. In reality, changing to a JIT environment takes time and pa-
tience. It is more of an evolutionary process than a revolutionary process. It takes
time to build a “partners-in-profits” relationship with suppliers. Many firms at-
tempt to force the JIT practices with suppliers by dictating terms, but this ap-
proach really runs counter to the notion of developing close relationships, some-
thing that is vital for the JIT purchasing side to work. There must be trust and
mutual benefits, not unilateral benefits, for JIT purchasing to become a success.

Also, management should be aware of the disequilibrium that workers may expe-
rience with JIT. Many workers may view JIT methodology as simply a way of ex-
tracting more and more work out of them with no compensating benefits. Others
may see JIT as a threat to their job security as the nonvalue-added activities they
perform are eliminated or reduced. Furthermore, management should be ready
and willing to place some current sales at risk with the hope of ensuring stronger
future sales, or with the hope of reducing inventory and operating costs to im-
prove overall profitability. How else can you justify lost sales due to production
stoppages that are designed to improve quality and efficiency?

481
14–11

1. e 4. e
2. a 5. c
3. d

14–12

1. Before JIT unit cost: $262,000/200,000 = $1.31


After JIT unit cost: $238,000/200,000 = $1.19
JIT costing is more accurate because there are more costs that are traceable
to each product.

2. Direct materials: Direct


Direct labor: Direct
Maintenance: Direct
Electricity: Direct
Depreciation: Direct (on cell equipment)
Material handling: Direct
Engineering: Driver tracing
Setups: Direct
Building and grounds: Allocated (driver tracing using square feet for the
building costs may be a reasonable possibility)
Supplies: Direct
Supervision (plant): Allocated
Cell supervision: Direct
Department Supervision: Allocated

482
14–13

1. Model A Model B
Price $20.00 $35.00
Variable cost 15.00 15.00
Contribution margin $ 5.00 $20.00
÷ Machine hours ÷ 0.5 ÷ 2.5
Contribution margin per machine hour $10.00 $8.00
The company should sell only the model A housing with contribution margin
per machine hour of $10. Gallard can produce 80,000 (40,000/0.5) of the model
A housings per year. These 80,000 units, multiplied by the $5 contribution
margin per unit, would yield a total contribution margin of $400,000.

2. Produce and sell 50,000 of the model A housings, which would use 25,000
machine hours. Then, produce and sell 6,000 of the model B housings, which
would use the remaining 15,000 machine hours.

Total contribution margin = ($5 × 50,000) + ($20 × 6,000)


= $370,000

14–14

1. Gear X Gear Y
Contribution margin $ 25.00 $10.00
÷ Machine hours ÷ 2.0 ÷ 0.5
Contribution margin per machine hour $12.50 $20.00
2. The company should sell only Gear Y with contribution margin per machine
hour of $20. Jorgenson can produce 20,000 (10,000/0.5) units of Gear Y per
year. These 20,000 units, multiplied by the $10 contribution margin per unit,
would yield a total contribution margin of $200,000.

3. Produce and sell 15,000 of the model A housings, which would use 7,500 ma-
chine hours. Then, produce and sell 1,250 units of Gear X, which would use
the remaining 2,500 machine hours.

Total contribution margin = ($25 × 1,250) + ($10 × 15,000)


= $181,250

483
14–15

1. Type I Type II Type III


Price $40.00 $60.00 $75.00
Variable cost 25.00 38.00 60.00
Contribution margin $15.00 $22.00 $15.00
÷ Machine hours ÷ 0.50 ÷ 0.80 ÷ 1.50
Contribution margin per machine hour $30.00 $27.50 $10.00
The company should sell only the Type I rod with contribution margin per
machine hour of $30. Perkins can produce 60,000 (30,000/0.5) Type I rods per
year. These 60,000 units, multiplied by the $15 contribution margin per unit,
would yield a total contribution margin of $900,000.

2. Produce and sell 20,000 Type I rods, which would use 10,000 machine hours.
Then, produce and sell 20,000 Type II rods, which would use 16,000 machine
hours. Finally, produce and sell 2,666 Type III rods, which would use the re-
maining 4,000 machine hours.

Total contribution margin = ($15 × 20,000) + ($22 × 20,000) + ($15 × 2,666)


= $779,990

14–16

1. The production rate is 600 regular bows per day and 200 deluxe bows per
day. The rate is set by the molding process. It is the drummer process since it
is the only one with a buffer inventory in front of it.

2. Goicoechea has 0.5 day of buffer inventory (400 bows/800 bows per day). This
time buffer is determined by how long it takes the plant to correct problems
that create production interruptions.

3. A is the rope, B is the time buffer, and C is the drummer constraint. The rope
ties the production rate of the drummer constraint to the release of raw mate-
rials to the first process. The time buffer is used to protect throughput. Suffi-
cient inventory is needed to keep the bottleneck operating if the first process
goes down. The drummer sets the production rate.

484
PROBLEMS

14–17

1. Ordering cost = PD/Q


= $40 × 14,000/400
= $1,400
Carrying cost = CQ/2
= $1.75* × 400/2
= $350
*10 percent of purchase price or 0.10 × $17.50
Total cost = $1,400 + $350 = $1,750

2. EOQ = 2PD/C
= (2 × 40 × 14,000 ) / 1.75
= 640,000
= 800
Ordering cost = PD/Q
= $40 × 14,000/800
= $700
Carrying cost = CQ/2
= $1.75 × 800/2
= $700
Total cost = $700 + $700 = $1,400
Savings = $1,750 – $1,400 = $350

485
14–17 Concluded

3. Rate of usage = 7 × 50 = 350 days


= 14,000/350 = 40 blocks per day
Reorder point = Average rate of usage × Lead time
= 40 × 5
= 200
This coincides with the current reorder policy.

4. The order quantity would have to be 600 instead of 800 (the EOQ). If so, the
following inventory costs would be incurred:
Ordering cost = $40 × 14,000/600
= $933
Carrying cost = $1.75 × 600/2
= $525
Total cost = $933 + $525
= $1,458
This restriction would mean an additional cost of only $58 ($1,458 – $1,400)
over the cost of using the EOQ.

5. The most cheese that should be kept on hand given the 10-day constraint is
400 blocks (40 × 10). Reorder would occur when inventory dropped to 200
units.

486
14–18

1. EOQ = 2PD/C
= (2 ×100 ×10,571) / 5.50
= 384,400
= 620
Reorder point = Average rate of usage × Lead time
= 30 × 4
= 120
Ordering cost = PD/Q
= $100 × 10,571/620
= $1,705
Carrying cost = CQ/2
= $5.50 × 620/2
= $1,705
Total cost = $1,705 + $1,705
= $3,410

2. Maximum usage 35
Average usage 30
Difference 5
Lead time ×4
Safety stock 20
Ordering cost = PD/Q
= $100 × 10,571/620
= $1,705
Carrying cost = CQ/2
= $5.50 × [(20 + 620)/2]
= $1,760
Total cost = $1,705 + $1,760
= $3,465
New reorder point = (Average usage × Lead time) + Safety stock
= (30 × 4) + 20
= 140

487
14–19

1. EOQ = 2PD/C
= (2 × 6,000 × 36,000 ) / 3
= 144,000,000
= 12,000 (batch size)
Geneva’s response was correct given its current production environment.
The setup time is two working days. The production rate possible is 750 units
per day after setup. Thus, the time required to produce the additional 9,000
units would be 14 working days [2 + (9,000/750)].

2. To have met the order’s requirements, Geneva could have produced 3,750
units within the 7-work-day window [(7 – 2)750] and would have needed 8,250
units in stock—5,250 more than available. Solving delivery problems like the
one described would likely require much more inventory than is currently car-
ried. If the maximum demand is predictable, then safety stock could be used.
The demand can be as much as 9,000 units per year above the expected de-
mand. If it is common for all of this extra demand to occur from one or a few
large orders, then protecting against lost sales could demand a sizable in-
crease in inventory, an approach that could be quite costly. Perhaps some
safety stock with expediting and overtime would be more practical. Or, per-
haps Geneva should explore alternative inventory management approaches
such as those associated with JIT or TOC.

3. EOQ = 2PD/C
= (2 × 94 × 36,000 ) / 3
= 2,256,000
≈ 1,502 (batch size)
The new lead time = (1.5 hours) + [(1,502/2,000) × 8 hours]
≈ 7.5 hours, or about one work day

488
14–19 Concluded

At a production rate of 2,000 units per day, Geneva could have satisfied the
customer’s time requirements in less than seven days, even without any fi-
nished goods inventory. This illustrates very forcefully that inventory may not
be the solution to meeting customer needs or dealing with demand uncertain-
ty. Perhaps paying attention to setup, moving, and waiting activities offers
more benefits. JIT tends to produce smaller batches and shorter cycle times
than conventional manufacturing environments. As the EOQ batch size com-
putation revealed, by focusing on improving the way production is done, the
batch size could be reduced to about 12.5 percent of what it was before the
improvements.

4. EOQ = 2PD/C
= (2 × 10 × 36,000) / 3
= 240,000
≈ 490 (batch size)
This further reduction in setup time and cost reduces the batch size even
more. As the setup time is reduced to even lower levels and the cost is re-
duced, the batch size becomes even smaller.
If the cost is $0.864, the batch size is 144:

EOQ = 2PD/C
= (2 × 0.864 × 36,000 ) / 3
= 20,736
= 144 (batch size)
Furthermore, with the ability to produce 2,000 units per day or 250 units per
hour, the day’s demand (36,000/250 = 144) can be produced in less than an
hour. This provides the ability to produce on demand. The key to this out-
come was the decrease in setup time and the reduction of wait and move
time—all nonvalue-added activities. This illustrates what is meant by refer-
ring to inventory management as an ancillary benefit of JIT.

489
14–20

1. a. The expected demand for the RJ47 battery during the lead time is calcu-
lated as the sum of the demand during the lead time times the demand
probability for all demand points:
Expected demand = (100 × 0.03) + (200 × 0.05) + (300 × 0.20) + (400 × 0.40)
+ (500 × 0.25) + (600 × 0.07)
= 400
b. The reorder point to minimize stockouts would be the maximum demand
during lead time, or 600 units.

2. The probability of a stockout at a special reorder point is the sum of the prob-
abilities for demand greater than the reorder point of 400 units:
Probability of 500 units 0.25
Probability of 600 units 0.07
Total 0.32

14–21

1. KEVCO can expect the following effects:


Planning:
• Production planning will change from a centralized batch function process
to a more decentralized activity. In some cases, production teams will be
responsible for the entire production process of a product.
• The method and timing of how the company prepares its production sche-
dules (including capacity requirements) will change to parallel the demand
pull approach as opposed to the push approach.
• The Purchasing Department will need production to have high-quality, reli-
able, and flexible suppliers who can quickly deliver orders of varying sizes
as needed.

490
14–21 Concluded

Operations:
• Setup time changes will reduce lead times significantly.
• A Kanban system will need to be implemented. A triggering device such as
a Kanban card is necessary so that the department or cell knows when to
begin production.
• Greater employee participation will result from cell production team ar-
rangements.

2. At least five benefits:


• Less rework and fewer defective units because of cell-level accountability
and control and product solving at the cell level.
• A lower cash investment in inventory and plant space. Handling, storage,
insurance, breakage, and obsolescence will all be lower.
• More satisfied customers should result because of shorter lead times and
higher quality.
• Improved labor productivity as a result of rearranging the production
process and the creation of manufacturing cell teams.
• A reduction of the number of suppliers leading to improved relationships
and communication.
• More accurate product costing because of the increase in direct tracing of
activities and their costs.

3. Behavioral effects:
• Higher team morale and motivation, since each cell team is responsible for
all cell production and will, therefore, have more control over its work and
an increased sense of ownership.
• Higher individual satisfaction, development, and motivation, as manage-
ment will encourage participation, training, and input on how to improve
the product and production process.
• A possible resistance to change by those employees who may feel inse-
cure or threatened by the change.
• A sense of partnership with management in achieving the goals and objec-
tives of the organization resulting in goal congruence.

491
14–22

1. The entire Kanban cycle begins with the need to produce a final product—a
product demanded by a customer. The demand for a product to be assembled
is known from the production schedule. Assume that a final product is
needed. The withdrawal Kanban controls movement of work between the as-
sembly process and the manufacturing processes. It specifies the quantity
that a subsequent process should withdraw from the preceding process. The
assembly process uses withdrawal Kanbans to notify the first process that
more subassemblies are needed. This is done by having an assembly worker
remove the withdrawal Kanban from the container in the withdrawal store and
place it on the withdrawal post. This W-Kanban signals that the assembly
process is using one unit of Subassembly A and that a replacement for it is
needed. The replacement activity is initiated by a carrier who removes the
production Kanban from the container of subassemblies in the SB stores area
and places this P-Kanban on the production post. The container in the SB
stores area is then moved to the withdrawal stores area with the W-Kanban
attached (taken from the withdrawal post). The production Kanban tells the
workers in the Subassembly A cell to begin producing another unit. The pro-
duction Kanban is removed and goes with the unit produced (which goes to
the SB stores area). This Kanban system ensures that the second process
withdraws subassemblies from the first process in the necessary quantity at
the necessary time. The Kanban system also controls the first process by al-
lowing it to produce only the quantities withdrawn by the second process. In
this way, inventories are kept at a minimum, and the components arrive just
in time to be used.

2. The second process uses a vendor Kanban to signal the supplier that another
order is needed. The process is similar to the internal flow described in Re-
quirement 1. However, for the process to work with suppliers, the suppliers
must be willing to make frequent and small deliveries. It also means that the
supply activity works best if the supplier is located in close proximity to the
buyer. The subassemblies must be delivered just in time for use. This calls
for a close working relationship with the supplier. The inventory function on
the materials side is largely assumed by the supplier. To bear this cost, there
must be some compensating benefits for the supplier. Long-term contracts
and the reduction of demand uncertainty are significant benefits for the sup-
plier. EDI can facilitate the entire arrangement. If the supplier has access to
the buyer’s on-line database, then the supplier can use the buyer’s produc-
tion schedule to determine its own production and delivery schedule, making
it easier to deliver parts just in time. In effect, the supplier and buyer almost
operate as one company.

492
14–23

1. ImmuneBoost: CM per machine hour = ($4.00 – $2.40)/1.60


= $1.00
MentaGrowth: CM per machine hour = ($4.80 – $3.60)/0.80
= $1.50
Since MentaGrowth provides the greatest contribution per machine hour, the
company should produce 800,000 bottles of MentaGrowth (640,000/0.8) and
zero bottles of ImmuneBoost. The total contribution margin is 800,000 × $1.20
(unit contribution margin) = $960,000

2. First, the company should produce 480,000 bottles of MentaGrowth. This


uses up 384,000 machine hours (480,000 × 0.8). The remaining hours can then
be used to produce 160,000 bottles of ImmuneBoost (256,000/1.6). Thus, the
optimal mix is 160,000 bottles of ImmuneBoost and 480,000 bottles of Menta-
Growth. The maximum total contribution margin is $832,000 [($1.60 × 160,000)
+ ($1.20 × 480,000)].

14–24

1. Dept. A Dept. B Dept. C Total


Component 12-L (1,000 units)
Test hoursa 2,000 3,000 3,000 8,000
Machine hoursb 1,000 1,000 2,000 4,000
Component 14-M (800 units)
Test hoursc 800 1,600 — 2,400
Machine hoursd 800 800 — 1,600
Component 40-S (2,000 units)
Test hourse 4,000 4,000 4,000 12,000
Machine hoursf 4,000 4,000 2,000 10,000
Total test hours 6,800 8,600 7,000 22,400
Total machine hours 5,800 5,800 4,000 15,600
a d
2 × 1,000; 3 × 1,000; 3 × 1,000 1 × 800; 1 × 800
b e
1 × 1,000; 1 × 1,000; 2 × 1,000 2 × 2,000; 2 × 2,000; 2 × 2,000
c f
1 × 800; 2 × 800 2 × 2,000; 2 × 2,000; 1 × 2,000
The demand can be met in all departments except for Department C. Produc-
tion requires 7,000 test hours in Department C, but only 5,500 hours are avail-
able.

493
14–24 Concluded

2. Component 12-L: CM per unit = $203 – $110 = $93


CM per test hour = $93/3 = $31
Test hours needed (Dept. C): 3 × 1,000 = 3,000
Component 14-M: CM per unit = $136 – $86 = $50
Requires no hours in Department C
Component 40-S: CM per unit = $184 – $114 = $70
CM per test hour = $70/2 = $35
Test hours needed (Dept. C): 2 × 2,000 = 4,000
Production should be equal to demand for Component 40-S because it has
the highest contribution margin per unit of scarce resource. After meeting
demand, any additional labor hours in Department C should be used to pro-
duce Component 12-L (5,500 – 4,000 = 1,500; 1,500/3 = 500 units of 12-L).
Contribution to profits:
Component 12-L: 500 × $93 = $ 46,500
Component 14-M: 800 × $50 = 40,000
Component 40-S: 2,000 × $70 = 140,000
Total contribution margin $226,500

14–25

1. Molding Grinding Finishing


Part A 6,000 12,000 18,000
Part B 20,000 30,000 40,000
Total requirements 26,000 42,000 58,000
Available time 23,040 48,000 67,200
Less: Setup time 5,760 — —
Net time available 17,280 48,000 67,200
Note: The time required is computed by multiplying the unit time required by
the daily demand. The available time is derived from the workers employed.
For example, molding has 48 workers, each supplying 480 minutes per day or
480 × 48 = 23,040 minutes. Assuming two setups, the molding production time
is reduced by 48 × 60 × 2 = 5,760 minutes per day (setup occupies one hour
and so ties up the 24 workers for one hour).
Molding is the major internal constraint facing Copeland Company.

494
14–25 Concluded

2. The contribution margin per unit for A is $100 ($180 – $80) and for B is $120
($220 – $100). The contribution margin per unit of scarce resource is $10
($100/10) for A and $6 ($120/20) for B. Thus, A should be produced first. If all
600 units of A are produced, Copeland would need 6,000 molding minutes. Af-
ter the setup for A, there are 23,040 – 2,880 = 20,160 minutes available. This
would leave 14,160 minutes to setup and produce B (20,160 – 6,000). After set-
ting up for B, there are 11,280 minutes left (14,160 – 2,880). Thus, 11,280/20 =
564 units of B can be produced. Producing 600 units of A and 564 units of B
will yield a daily contribution margin of $127,680 [($100 × 600) + ($120 × 564)].

3. Ten minutes to set up would tie up the 48 workers for only 10 minutes. Thus,
production time lost is 480 minutes per setup. After setting up and producing
all of A required (using 6,000 + 480 =6,480 minutes), this would leave 16,560
minutes to set up and produce Part B (23,040 minutes – 6,480). Setup time for
B would use up 480 minutes of molding’s resources, and this leaves 16,080
minutes for producing B (16,560 – 480). Thus, 16,080/20 = 804 units of B could
be produced each day. This will increase daily contribution margin by $28,800
[$120 × (804 – 564)].

14–26

1. The constraints are both labor constraints, one for fabrication and one for as-
sembly (let X = Units of Sub A and Y = Units of Sub B; hours are used to
measure resource usage and availability):
Assembly: (1/2)X + (2/3)Y ≤ 800 (1)
Fabrication: (1/3)X + (1/3)Y ≤ 800 (2)
Comparing the assembly constraint with the fabrication constraint, we see
that assembly uses more labor time per unit for each subassembly than fabri-
cation (1/2 hour of assembly for X vs. 1/3 hour of fabrication for X and 2/3
hour of assembly for Y vs. 1/3 hour of fabrication for Y), so only one binding
constraint is possible (assembly labor). Thus, the contribution margin per
unit of scarce resource will dictate the outcome. For Sub A, the CM per unit of
assembly labor is $40 ($20 × 2) and for Sub B it is $36 ($24 × 1.5). Therefore,
only Sub A should be produced. The optimal mix is 1,600 units per day of Sub
A and none of Sub B. The daily contribution margin is $32,000 ($20 × 1,600).

495
14–26 Concluded

2. The drummer constraint is the assembly constraint. The mix dictates a pro-
duction rate of 1,600 units of Part A per day. At this rate, all 800 hours availa-
ble of the drummer constraint are used up. The fabrication constraint would
use 533.33 hours at this rate, leaving 266.67 hours of excess capacity.
The drummer constraint sets the production rate for the entire factory—in
this case, 1,600 units of A per day. The rope concept simply means that the
production rate of the fabrication process is controlled by tying the release of
materials to the assembly’s rate of production. The daily release of materials
to the fabrication process should be enough to produce only 1,600 subas-
semblies. The 1.5-day buffer means that there should be a 1.5-day supply of
components in front of the drummer process (assembly) so that production
can continue if the supply of parts to the assembly process is interrupted.
Thus, a 2,400 component inventory is required. This protects throughput in
case production or supply is interrupted. The 1.5-day length reflects the time
thought necessary to restore most production interruptions.

3. The use of local labor efficiency measures would encourage the fabrication
process to produce at a higher rate than the drummer rate (it has excess ca-
pacity) and so would run counter to the TOC objectives. In fact, efficient use
of labor in fabrication would cause a buildup of about 800 (266.67 × 3) units
per day of work in process inventory—a very expensive outcome.

4. Adding a second shift of 50 workers for the assembly process creates an ad-
ditional 400 hours of assembly resource. There would now be 1,200 hours of
assembly resource available. The assembly constraint now appears as follows:
(1/2)X + (2/3)Y ≤ 1,200. Increasing the assembly resource allows us to in-
crease production of Sub A from 1,600 to 2,400 units (1,200/0.5 = 2,400 units).
Fabrication can handle the increase [(1/3) × 2,400 = 800 hours—exactly the
time available]. The contribution margin without the increase in the labor cost
of the second shift is $48,000 ($20 × 2,400). Thus, the daily contribution mar-
gin increases by $16,000 ($48,000 – $32,000). Since the cost of adding the
second shift of 50 workers is $2,800 (400 × $7), the improvement in profit per-
formance is $13,200 ($16,000 – $2,800).

496
14–27

1. Potential daily sales:


Small Large
Cylinder Cylinder
Sales $ 80 $ 110
Materials 40 50
CM per unit $ 40 $ 60
Daily demand × 200 × 100
Daily profit $ 8,000 + $ 6,000 = $14,000 potential

Process Resource Demands Resource Supply


Cutting Small: 30 × 200 = 6,000
Large: 20 × 100 = 2,000
8,000 9,600

Welding Small: 30 × 200 = 6,000


Large: 60 × 100 = 6,000
12,000 9,600

Polishing Small: 30 × 200 = 6,000


Large: 30 × 100 = 3,000
9,000 12,480

Painting Small: 20 × 200 = 4,000


Large: 30 × 100 = 3,000
7,000 9,600

Zaramar cannot meet daily demand. The welding process requires 12,000 mi-
nutes but has only 9,600 available. All other processes have excess capacity.
Thus, welding is the bottleneck.

497
14–27 Concluded

2. The contribution margin per unit of welding resource for each product is
computed below:
Small: $40/30 = $1.33
Large: $60/60 = $1.00
This suggests that Zaramar should first produce all that it can of the small cy-
linder. Thus, 30 × 200 = 6,000 minutes of welding will be dedicated to the
small cylinder. The remaining minutes (3,600) will be used to produce all that
is possible of the large cylinder: 3,600/60 = 60 units. The optimal mix is small
cylinder = 200 units and the large = 60 units, producing a daily contribution of
$11,600 [($40 × 200) + ($60 × 60)].

3. The welding process is the drummer. It sets the production rate for the entire
plant. Thus, the plant should produce 200 units of the small cylinder per day
and 60 units of the large per day. To ensure that the cutting process does not
exceed this rate, the release of materials is tied to the maximum production
rate of the welding process (materials for 200 units of the small cylinder and
materials for 60 units of the large cylinder would be released). This is the
rope. Finally, to protect throughput, a time buffer is set up in front of the weld-
ing process. This buffer would consist of 400 cut units for the small cylinder
and 120 cut units for the larger cylinder (a two-day buffer).

4. The redesign would increase the polishing time for the small cylinder from
6,000 minutes to 9,200 minutes and, at the same time, decrease the welding
time for the small cylinder from 6,000 minutes to 4,000 minutes. This frees up
2,000 minutes of scarce resource in welding and decreases the excess capac-
ity of polishing. The extra 2,000 minutes in welding can be used to produce an
additional 33 units of the large cylinder (2,000/60). This will increase daily
contribution margin by $1,980. It would take 10.1 work days to recover the
$20,000 needed for redesign ($20,000/$1,980). This step illustrates one way of
elevating constraints—the fourth step in the TOC methodology.

498
MANAGERIAL DECISION CASE

14–28

1. By discussing the amount by which his company and Piura have reduced
costs, Mac may have violated the confidentiality standard. Specifically, Mac
should: “Keep information confidential except when disclosure is authorized
or legally required.” (II-1) He may also be involved in a conflict of interest, al-
though he may not have realized this until the conversation of the evening un-
folded. (III-1) Finally, he must “refrain from engaging in any activity that would
prejudice carrying out duties ethically.” (III-2)
2. Mac would violate a host of standards: disclosing confidential information,
engaging in a conflict of interest, and engaging in conduct that would discre-
dit the profession. He would be well advised to refuse the offer and avoid any
disclosure of information.

RESEARCH ASSIGNMENT

14–29

Answers will vary.

499
500

You might also like