CHAPTER - 3
BEST PRACTICES IN PLANNING, DESIGNS & CONS-
TRUCTION OF CIVIL WORKS OF HYDRO POWER PROJECTS
“This chapter gives a detailed step by step procedural account of
various stages involved in planning, design and construction of civil
works of hydro power projects. Topics like types of hydro power
Projects, components, power house installation, types of dams and
the related geo-mechanics, instrumentation, measurements of features
like gates, barrages and tunnels, safety assurances, maintenance and
remedial measures for ensuring optimum performance levels have
been dealt in quite detail. Each step involved in setting up of a hydro
power project is elaborated with appropriate references and precise
mathematical formulae.”
3.1. INTRODUCTION
3.1.1 Hydro Power Projects harness the potential energy of the water at a
relatively higher elevation, which is converted first into mechanical energy
and then into electrical energy. This transformation of energy from one
form to another is facilitated by the water in motion. This journey from
120 MW Tanakpur Power Station (Uttaranchal) - Barrage
593.1.2
3.2
3.21
water to watts is through water conductor system, which may comprise of
intake structure, trash rack structure, desilting chamber, head race channel
/ tunnel, surge chamber / shaft, penstock, power house (spiral case,
turbine, draft tube ete.) & finally tail race channel / tunnel. This chapter
deals with the basic design philosophies & best practices in vogue in
planning, design & construction of these civil works, which facilitate the
journey from water to watts.
Hydel civil design is unique and depends primarily on site specific
features, viz., topology, geology, hydro-meteorology ete. No practice can,
therefore, be generalized in case of hydel civil design and presented as
best practice. As such, one has to begin with basic classification system
and their general characteristics to evolve best practice suitable for a
specific site condition.
STAGES OF IMPLEMENTATION
Best Practices in planning, design and construction of Civil works in
Hydro-Power Projects are taken care of at the following four stages:
Feasibility report stage
Detailed project report stage
Tender preparation stage
Construction stage design and implementation stage
These four stages are described as below:
Feasibility report stage
During basic planning of the project besides engineering issues,
environment, ecology and other socio - economic factors also play
important role. However here only the conceptual and engineering
issues are detailed
i) Detailed study of hydrology, which includes water availability
studies, flood studies and collection of historical hydrological data
and meteorological data.
ii) The installed capacity of the project along with design head and
the design discharge for the project.
ili) Fixation of location of the dam and the powerhouse.
603.2.2
iv)
vy)
vi)
vii)
viii)
ix)
Fixing of the height of the dam above riverbed.
Fixing the preliminary layout of the water conductor system:
Fixing the type of the power house
Working out the design energy for the project.
Evaluation of infrastructure works likely to be involved.
To work out the knowledge of civil design, electrical design,
hydrology, geology, construction and cost engineering is very
important to arrive at a good feasibility report,
Detailed Project Report stage
Detailed project report is the outcome of detailed investigations and
studies carried out at the site,
These detailed investigations essentially include the detailed information
on subsurface geology along with detailed hydrological studies based
upon the historical hydrological data available.
The following essential tasks are performed during the DPR stage design
vii)
vill)
ix)
xi)
xii)
xiii)
xiv)
xv)
xvi)
Precise study of hydrology.
Detailed investigation and study of geology.
Decision on the type of dam
Fixation of spillway design flood
Fixation of spillway system and the sizing of the same.
River diversion scheme.
Fixation of the layout of water conductor system.
Fixation of size of HRT.
Fixation of the type of intake and desilting arrangement.
To fix the location of the surge shaft based upon topographical
and geological information
To fix the size of the surge shatt, based upon transient studies.
Fixing the detailed layout of powerhouse complex including
location of access tunnels and ventilation tunnels
To work out powerhouse planning in consultation with E&M group.
To work out the details of TRT outlet and its joining with the river
To work out details of HM equipments proposed for the projects
Detailed assessment of infrastructure and construction machinery
requirement.
61