Q S H E P LA N

No. PKP
Halaman
Revisi
Tanggal
METODE KERJA BORED PILE Dibuat Oleh
Disetujui Oleh

7 . Metode Kerja
7.3 Pekerjaan Bored Pile
Distribution List
Daftar Isi
7.3.1 Umum
7.3.2 Spesifikasi
7.3.3 Target Quantity
7.3.4 Sumberdaya dan Alat
7.3.4.1 Tenaga
7.3.4.2 Alat
7.3.5 Material
7.3.6 Schedulle
7.3.7 Metode Konstruksi
7.3.7.1 Work Squence (Urutan Kerja)
7.3.7.2 Detail Of Work (Detail Pelaksanaan)
7.3.7.3 Construction Squence (Urutan Konstruksi)
7.3.7.4 Typical Cycle Time For Construction
7.3.8 Tabel Quality Control
7.3.9 Safety Work Analysis
S H E P LA N
: 984
: 1/2
:2
: 31 Januari 2011
: Tito Ari Bawono
: Surachman Ambar
Q S H E PL
No PKP
Halaman
Revisi

Tanggal

Dibuat oleh

METODE KERJA BORED PILE Disetujui

Revision Status

No. Revisi Uraian Tanggal


0 Pengajuan Awal :
1
2

Distribution List

No Penerima Dokumen Jabatan


1 Shafril Yinurullah Kepala Proyek
2 Wakil Kepala Proyek
3 Sunandar Koordinator Mutu
4 Shafril Yinurullah Koordinator Safety
5 Anto Hasudungan Kepala Operasi
6 Daniel Planning Schedulling
7 Adi Indrianto Pelaksana Struktur
8 Iskandar Quality Control
9 Suwarno General Affair
10
Q S H E P LA N
:
:
:
:

Keterangan

Tanggal terima
QSHE P
No PKP
Halaman
Revisi
Tanggal

Dibuat oleh

METODE KERJA BORED PILE Disetujui

7.2.1 Umum

Total Volume Pile cap 5800 m3 (264 Titik) dengan tebal 2.50-3.00 m, menggunakan beton dengan mutu k-350
Sesuai dokumen kontrak pile cap digunakan untuk seluruh pile cap struktural Fly Over dimana kondisi tanah pada umumny
1. Kedalaman 0 - 15 m : Clay
2. Kedalaman 15 - 30 m : Very Soft Silty Clay
3. Kedalaman 30 - 45 m : Dense Silty Sand
4. Kedalaman 45 - 60 m : cemented clay silty

Dengan muka air tanah dikedalaman 12 m. Dengan kondisi tanah diatas

7.2.2 Spesifikasi

Spesifikasi mengikuti pasal-pasal sebagai berikut:


1. Part 7 Specification, section 10. Concrete Structure
2. S10. 02 Reinforcing Steel
3. S10. 07 Cast In Place Concrete Piling

7.2.3 Target Quantity

Rekapitulasi Volume Pile cap, Galian Tanah, Beton, dan Besi Terlampir. Lihat Lampiran 01
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :

Dibuat oleh :

Disetujui :

on dengan mutu k-350


imana kondisi tanah pada umumnya sebagai berikut:
METODE KERJA BORE PILE

7.2.3 TARGET QUANTITY

Diameter Panjang (m)


Nomor Pier Jumlah
(mm) (soil test ref)

P 39 8 1500 25

P 38 8 1500 26

P 37 8 1500 26

P 36 10 1500 24

P 35 8 1500 25

P 34 9 1500 27

P 33 10 1500 23

P 32 8 1500 23

P 31 8 1500 21

P 30 8 1500 27

P 29 8 1500 25
P 28 10 1500 25

P 26 8 1500 25

P 25 A 7 1500 26

P 24 A 8 1500 25

P 23 A 7 1500 28

P 22 A 12 1500 25

P 21 A 12 1500 25

P 20 A 6 1500 25

P 19 A 6 1500 26

P 18 A 6 1500 24

P 17 A 10 1500 25

P 16 A 9 1500 25

P 15 A 9 1500 27

P 18 B 6 1500 25

P 19 B 6 1500 25

P 20 B 7 1500 28

P 21 B 12 1500 27

P 22 B 10 1500 25

P 23 B 7 1500 25
P 24 B 7 1500 29

P 25 B 6 1500 25

Total 264
Total Volume Galian Volume Beton
Panjang (m) Per Tiang Per Pile Cap Cut Of Kedalaman Per Tiang

200 49.10 392.81 - 2,8 -27.8 44.16

208 50.87 406.94 - 2,8 -28.8 45.92

208 50.87 406.94 - 2,8 -28.8 45.92

240 47.34 473.36 - 2,8 -26.8 42.39

200 49.10 392.81 - 2,8 -27.8 44.16

243 52.63 473.71 - 2,8 -29.8 47.69

230 45.57 455.69 - 2,8 -25.8 40.62

184 45.57 364.55 - 2,8 -25.8 40.62

168 42.04 336.29 - 2,8 -23.8 37.09

216 52.63 421.07 - 2,8 -29.8 47.69

200 49.10 392.81 - 2,8 -27.8 44.16


250 49.10 491.02 - 2,8 -27.8 44.16

200 49.10 392.81 - 2,8 -27.8 44.16

182 50.87 356.08 - 2,8 -28.8 45.92

200 49.10 392.81 - 2,8 -27.8 44.16

196 54.40 380.80 - 2,8 -30.8 49.46

300 49.10 589.22 - 2,8 -27.8 44.16

300 49.10 589.22 - 2,8 -27.8 44.16

150 49.10 294.61 - 2,8 -27.8 44.16

156 50.87 305.21 - 2,8 -28.8 45.92

144 47.34 284.01 - 2,8 -26.8 42.39

250 49.10 491.02 - 2,8 -27.8 44.16

225 49.10 441.92 - 2,8 -27.8 44.16

243 52.63 473.71 - 2,8 -29.8 47.69

150 49.10 294.61 - 2,8 -27.8 44.16

150 49.10 294.61 - 2,8 -27.8 44.16

196 54.40 380.80 - 2,8 -30.8 49.46

324 52.63 631.61 - 2,8 -29.8 47.69

250 49.10 491.02 - 2,8 -27.8 44.16

175 49.10 343.71 - 2,8 -27.8 44.16


203 56.17 393.17 - 2,8 -31.8 51.22

150 49.10 294.61 - 2,8 -27.8 44.16

6,691 13,124
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :

Dibuat oleh :

Disetujui :

me Beton Volume Besi


Per Pile Cap Per Tiang Per Pile Cap Ratio besi m3

353.25 6,181.88 49,455.00 140

367.38 6,429.15 51,433.20 140

367.38 6,429.15 51,433.20 140

423.90 5,934.60 59,346.00 140

353.25 6,181.88 49,455.00 140

429.20 6,676.43 60,087.83 140

406.24 5,687.33 56,873.25 140

324.99 5,687.33 45,498.60 140

296.73 5,192.78 41,542.20 140

381.51 6,676.43 53,411.40 140

353.25 6,181.88 49,455.00 140


441.56 6,181.88 61,818.75 140

353.25 6,181.88 49,455.00 140

321.46 6,429.15 45,004.05 140

353.25 6,181.88 49,455.00 140

346.19 6,923.70 48,465.90 140

529.88 6,181.88 74,182.50 140

529.88 6,181.88 74,182.50 140

264.94 6,181.88 37,091.25 140

275.54 6,429.15 38,574.90 140

254.34 5,934.60 35,607.60 140

441.56 6,181.88 61,818.75 140

397.41 6,181.88 55,636.88 140

429.20 6,676.43 60,087.83 140

264.94 6,181.88 37,091.25 140

264.94 6,181.88 37,091.25 140

346.19 6,923.70 48,465.90 140

572.27 6,676.43 80,117.10 140

441.56 6,181.88 61,818.75 140

309.09 6,181.88 43,273.13 140


358.55 7,170.98 50,196.83 140

264.94 6,181.88 37,091.25 140

11,818 1,654,517
METODE KERJA BORE PILE

7.2.4 Tenaga dan Peralatan

7.2.4.1 Sumber Daya

1. Sumber daya Pelaksana Pekerjaan (Sub Kontraktor)


Untuk melaksanakan pekerjaan ini ditunjuk PT.Indopora sebagai sub kontraktor. Struktur organisasi terlampir 02

Operator 2
Specialist 3
Harian 3
Welder 2
Surveyer 2
Total 12

7.2.4.2 Daftar Peralatan

Kapasitas
No Nama Alat Jumlah Satuan

1 Service Crane 55 Ton 1 unit


2 Drilling Rig (R412, RT3ST) Mait HR-150 C 1 unit
3 Excavator 0.8 m3 10 unit
4 Plat Kapal 1 unit
5 Mesin Las 1 unit
6 Drilling Auger Ø 150 cm 1 unit
7 Drilling Bucket Ø 150 cm 1 unit
8 Cleaning Bucket Ø 150 cm 1 unit
9 Casing Ø 150 cm @ 3m 2 unit
10 Container Office 1 unit
11 Tremie 60 m
12 Tremie Ø 20 cm 30 m
13 Container Penampung Lumpur 2 unit
14 Tanki Air 2 unit
15 Tanki Solar 1 unit
16 Bucket Cor 2 unit
17 Genset 1 unit
18 Tool Box 1 unit
19 Portable Toilet 2 unit
20 Pompa lumpur 1 unit
21 Pompa Air 1 unit
22 Sand Bag 300 unit
23 Lampu Penerangan 3 unit

7.2.5 Daftar Material

No Material Deskripsi Detail QTY

1 Beton K-300 Slump 18 ± 2,5 cm Bore Pile 11817.9788

2 Besi U-39 Bore Pile 1654517.03


3 Mud Slurry Polymer SC MUD P 0,5
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :

Dibuat oleh :

Disetujui :

organisasi terlampir 02
Unit Remaks

m3

Ton
kg/m3
METODE KERJA BORE PILE

7.2.6 SCHEDULLE

MONITORING PEKERJAAN BORE PILE

5/21/2018
P 39 P 38 P 37 P 36 P 35 P 34 33 32 31 30
JUMLAH TTK 8 8 8 10 8 9 10 8 8 8
PROGRESS 8 8 8 10 8 9 10 8 8 8
SISA VOLUME 0 0 0 0 0 0 0 0 0 0

Time Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri
07/02/11 25 13/02/11 25 20/02/11 25 27/02/11 25 08/03/11 25 15/03/11 25 22/03/11 25 31/03/11 25 07/04/11 25 14/04/11
07/02/11 25 14/02/11 25 21/02/11 25 28/02/11 25 08/03/11 25 15/03/11 25 23/03/11 25 31/03/11 25 07/04/11 25 14/04/11
08/02/11 25 15/02/11 25 22/02/11 25 01/03/11 25 09/03/11 25 16/03/11 25 24/03/11 25 01/04/11 25 08/04/11 25 15/04/11
09/02/11 25 16/02/11 25 23/02/11 25 01/03/11 25 10/03/11 25 17/03/11 25 24/03/11 25 02/04/11 25 09/04/11 25 16/04/11
09/02/11 25 16/02/11 25 23/02/11 25 02/03/11 25 11/03/11 25 18/03/11 25 25/03/11 25 03/04/11 25 10/04/11 25 16/04/11
10/02/11 25 17/02/11 25 24/02/11 25 03/03/11 25 11/03/11 25 18/03/11 25 26/03/11 25 03/04/11 25 10/04/11 25 17/04/11
11/02/11 25 18/02/11 25 25/02/11 25 04/03/11 25 12/03/11 25 19/03/11 25 27/03/11 25 04/04/11 25 11/04/11 25 18/04/11
11/02/11 25 18/02/11 25 25/02/11 25 04/03/11 25 13/03/11 25 20/03/11 25 27/03/11 25 05/04/11 25 12/04/11 25 19/04/11
05/03/11 25 20/03/11 25 28/03/11 25
06/03/11 25 29/03/11 25
5 200.000 5 200 200.00
250 200 225 250 200 200

START 1/24/2011 1/26/2011 2/1/2011 2/8/2011 2/15/2011 2/22/2011 3/3/2011 3/12/2011 3/22/2011 2/24/2011
FINISH 2/8/2011 2/15/2011 2/17/2011 2/19/2011 2/21/2011 3/3/2011 3/12/2011 3/21/2011 3/30/2011 3/3/2011

PROGRESS PRODUKSI BORE PILE

JUMLAH TOTAL TITIK BORE PILE 264 Titik

PROGRESS PRODUKSI BORE PILE 264 Titik 100%

SISA TITIK BORE PILE 0 Titik 0%


Ri H Ri H Ri H Ri H Ri H Ri H Ri
12/09/11 25 05/09/11 25 30/08/11 25 22/08/11 25 12/08/11 25 06/08/11 25 31/07/11
12/09/11 25 06/09/11 25 31/08/11 25 22/08/11 25 13/08/11 25 06/08/11 25 01/08/11
13/09/11 25 07/09/11 25 31/08/11 25 23/08/11 25 13/08/11 25 07/08/11 25 02/08/11
14/09/11 25 07/09/11 25 01/09/11 25 24/08/11 25 14/08/11 25 08/08/11 25 02/08/11
14/09/11 25 08/09/11 25 02/09/11 25 25/08/11 25 15/08/11 25 09/08/11 25 03/08/11
15/09/11 25 09/09/11 25 03/09/11 25 25/08/11 25 15/08/11 25 09/08/11 25 04/08/11
10/09/11 25 03/09/11 25 26/08/11 25 16/08/11 25 10/08/11 25
27/08/11 25 17/08/11 25
27/08/11 25 18/08/11 25
28/08/11 25 18/08/11 25
19/08/11 25
20/08/11 25

JUMLAH TTK 6 7 7 10 12 7 6
PROGRESS 6 7 7 10 12 7 6
SISA VOLUME 0 0 0 0 0 0 0
START 9/23/2011 9/15/2011 9/7/2011 8/27/2011 6/24/2011 8/9/2011 5/26/2011
FINISH 9/29/2011 9/22/2011 9/14/2011 9/6/2011 7/6/2011 8/6/2011 8/1/2011
MOB 9/9/2011 7/9/2011

25 24 23 22 21 20 19
30 29 28 26
TOTAL
8 8 10 8 111
8 8 10 8 111
0 0 0 0 0

H Ri H Ri H Ri H
25 21/04/11 25 28/04/11 25 06/05/11 25
25
25
21/04/11
22/04/11
25
25
28/04/11
29/04/11
25
25
07/05/11
07/05/11
25
25 P 25 24 23 22 21 20 19
25 23/04/11 25 30/04/11 25 08/05/11 25
25 23/04/11 25 30/04/11 25 09/05/11 25 7 8 7 12 12 6 6
25 24/04/11 25 01/05/11 25 09/05/11 25 7 8 7 12 12 6 6
25 25/04/11 25 02/05/11 25 10/05/11 25 0 0 0 0 0 0 0
25 26/04/11 25 03/05/11 25 11/05/11 25 4/22/2011 5/24/2011 5/21/2011 5/27/2011 6/8/2011 6/16/2011 5/14/2011
03/05/11 25 5/2/2011 5/17/2011 5/22/2011 6/3/2011 6/20/2011 6/22/2011 5/20/2011
04/05/11 25 6/6/2011

200 200 250 200 Ri H Ri H Ri H Ri H Ri H Ri H Ri


08/05/11 25 14/05/11 25 21/05/11 25 27/05/11 25 06/06/11 25 16/06/11 25 22/06/11
2/24/2011 3/4/2011 3/26/2011 4/5/2011 09/05/11 25 15/05/11 25 22/05/11 25 28/05/11 25 07/06/11 25 17/06/11 25 22/06/11
3/3/2011 3/24/2011 4/4/2011 4/11/2011 09/05/11 25 16/05/11 25 23/05/11 25 29/05/11 25 08/06/11 25 17/06/11 25 23/06/11
10/05/11 25 16/05/11 25 23/05/11 25 30/05/11 25 08/06/11 25 18/06/11 25 24/06/11
11/05/11 25 17/05/11 25 24/05/11 25 30/05/11 25 09/06/11 25 19/06/11 25 24/06/11
11/05/11 25 18/05/11 25 25/05/11 25 31/05/11 25 10/06/11 25 20/06/11 25 25/06/11
12/05/11 25 18/05/11 25 25/05/11 25 01/06/11 25 10/06/11 25
19/05/11 25 01/06/11 25 11/06/11 25
02/06/11 25 12/06/11 25
03/06/11 25 13/06/11 25
03/06/11 25 13/06/11 25
04/06/11 25 14/06/11 25
Q S H E P LA N
No PKP :
Halaman :
Revisi :
:
Tanggal

Dibuat oleh:

Disetujui :

H Ri H
25 26/07/11 25
25 26/07/11 25
25 27/07/11 25
25 28/07/11 25
25 28/07/11 25
25 29/07/11 25

TOTAL
6 6 61
6 6 61
0 0 0
5/26/2011 5/14/2011
8/1/2011 5/25/2011

19 18
17 16 15
TOTAL GRAND TOTAL
JUMLAH TTK 10 9 9 28 264
PROGRESS 10 9 9 28 264
SISA VOLUME 0 0 0 0 0
START 4/30/2011 4/19/2011 4/14/2011
FINISH 5/11/2011 4/26/2011 4/28/2011

19 18
TOTAL
6 6 64 JUMLAH TTK
6 6 64 PROGRESS
0 0 0 SISA VOLUME
5/14/2011 5/6/2011
5/20/2011 5/12/2011
5/14/2011 Ri H Ri H Ri H
03/07/11 25 10/07/11 25 18/07/11 25
H Ri H 03/07/11 25 11/07/11 25 19/07/11 25
25 27/06/11 25 04/07/11 25 12/07/11 25 19/07/11 25
25 28/06/11 25 05/07/11 25 12/07/11 25 20/07/11 25
25 28/06/11 25 05/07/11 25 13/07/11 25 21/07/11 25
25 29/06/11 25 06/07/11 25 14/07/11 25 21/07/11 25
25 30/06/11 25 07/07/11 25 15/07/11 25 22/07/11 25
25 01/07/11 25 08/07/11 25 15/07/11 25 23/07/11 25
08/07/11 25 16/07/11 25 24/07/11 25
Feb Mar Apr May Jun Jul Aug Sep Oct
Schdule Detail Jumlah Tiang Mulai Selesai Kapasitas Durasi
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 36 37 38 39 36
P 39 8 7-Feb 11-Feb 1.6 5
P 38 8 12-Feb 17-Feb 1.6 5
P 37 8 18-Feb 23-Feb 1.6 5
P 36 10 23-Feb 2-Mar 1.6 6
P 35 8 3-Mar 8-Mar 1.6 5
P 34 9 8-Mar 14-Mar 1.6 6
P 33 10 15-Mar 21-Mar 1.6 6
P 32 8 22-Mar 27-Mar 1.6 5
P 31 8 27-Mar 1-Apr 1.6 5
P 30 8 2-Apr 7-Apr 1.6 5
P 29 8 8-Apr 13-Apr 1.6 5
P 28 10 13-Apr 20-Apr 1.6 6
P 26 8 20-Apr 25-Apr 1.6 5
P 25 A 7 21-Apr 25-Apr 1.6 4
Schedule Detail

P 24 A 8 26-Apr 1-May 1.6 5


P 23 A 7 2-May 6-May 1.6 4
P 22 A 12 7-May 15-May 1.6 8
P 21 A 12 15-May 23-May 1.6 8
P 20 A 6 24-May 27-May 1.6 4
P 19 A 6 28-May 1-Jun 1.6 4
P 18 A 6 1-Jun 5-Jun 1.6 4
P 17 A 10 5-Jun 11-Jun 1.6 6
P 16 A 9 12-Jun 18-Jun 1.6 6
P 15 A 9 18-Jun 24-Jun 1.6 6
P 18 B 6 24-Jun 27-Jun 1.6 4
P 19 B 6 28-Jun 2-Jul 1.6 4
P 20 B 7 2-Jul 7-Jul 1.6 4
P 21 B 12 7-Jul 15-Jul 1.6 8
P 22 B 10 16-Jul 22-Jul 1.6 6
P 23 B 7 23-Jul 27-Jul 1.6 4
P 24 B 7 28-Jul 1-Aug 1.6 4
P 25 B 6 2-Aug 5-Aug 1.6 4
Total 264

Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Operator 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Manpower

Specialist 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Manpower
Harian 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Welder 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Surveyer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Total 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
Oct
37 38 39

1 1

2 2 72
3 3 108
3 3 108
2 2 72
2 2 72
12 12 432
METODE KERJA BORE PILE

7.2.7.1 SQUENCE PEKERJAAN

Flow Chart

Persiapan Lokasi - Pembersihan Daerah disekitar are


- Ratakan area kerja
- Perbaikan Tanah, jika diperlukan

- Cek Peralatan dan Alat-alat


Mobilisasi Peralatan - persiapan Batching Plant dan sa
- Pencampuran Beton

Pengiriman Besi Menentukan As Bore Pile - Memastikan Posisi Tiang

Pre-Boring & - meletakkan casing pipa pada pos


Pasang Casing Pipa - memastikan ketegakan casing

- Masukkan Slurry kedalam casing


Pelaksanaan Pengeboran dan pertahan level permukaannya
Fabrikasi Besi
- Pembuangan Tanah
- Mencocokka antara lapisan tana

1 st Pembersihan Pertama Dasar - Cek sedimen sebelum dan sesuda


Lubang galian bucket dan Air-lift - Pemeriksaan dengan ultra sonic

- Perhatikan overlap sambungan b


Pemasangan Besi Tulangan
- Pastikan Level besi

Pemasangan Pipa Tremie - Cek panjang pipa Tremie dan sam

1 st sesuai instruksi Pembersihan kedua Bagian dasar - Cek sedimen sebelum dan sesuda
konsultan lubang galian dengan Air -Lift 1)
1 st sesuai instruksi Pembersihan kedua Bagian dasar
konsultan lubang galian dengan Air -Lift 1)

- Cek slump dan segregasi beton s


Pengecoran Beton
- Panjang pipa tremi tertanam
minimal 2m, maksimal 10 m
Pembukaan Pipa casing

Urugan - Dengan Tanah bekas galian

Sonic Logging Test


Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :
Dibuat oleh :
Disetujui :

Pembersihan Daerah disekitar area kerja


Ratakan area kerja
Perbaikan Tanah, jika diperlukan

Cek Peralatan dan Alat-alat


persiapan Batching Plant dan saluran pipa beton
Pencampuran Beton

Memastikan Posisi Tiang

meletakkan casing pipa pada posisinya


memastikan ketegakan casing

Masukkan Slurry kedalam casing


dan pertahan level permukaannya
Pembuangan Tanah
Mencocokka antara lapisan tanah dengan sample

Cek sedimen sebelum dan sesudah pembersihan


Pemeriksaan dengan ultra sonic

Perhatikan overlap sambungan besi


Pastikan Level besi

Cek panjang pipa Tremie dan sambungan-sambungan

Cek sedimen sebelum dan sesudah pembersihan


Cek slump dan segregasi beton sebelum di cor
Panjang pipa tremi tertanam didalam beton
minimal 2m, maksimal 10 m

Dengan Tanah bekas galian


Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :

Dibuat oleh :

METODE PEKERJAAN BORE PILE Disetujui :

7.2.7.2 Tahapan Pekerjaan Bore Pile

1 2 3 4 5 6

Drilling
Machine

Crawler crane
Pipa
Casing Besi
Tulangan
Mata Bor

`
Pengeboran Pemasangan Casing Pemasangan Besi Tulangan Pengecoran Awal Pengecoran lanjutan (Tremie diangkat)
Pelepasan Casing
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :

Dibuat oleh :

METODE PEKERJAAN BORE PILE Disetujui :

7.2.7.3 Construction Squence (Urutan Konstruksi)


Untuk pelaksanaan pekerjaan bore pile, urutan titik pengeborannya harus dilakukan dengan cara melompat.
Artinya setelah titik ke-1 dilanjutkan ke titik ke-3 atau ke-4 , hal ini dimaksudkan agar bore pile yang baru
yang kemungkinan beton ready mixnya masih mengalami proses setting, tidak rusak atau terganggu oleh
pengeboran disampingnya .
LA N

cara melompat.
le yang baru
ganggu oleh
METODE PEKERJAAN BORE PILE

7.2.7.4 Typical Cycle Time for Bored Pile Construction


Aktivitas excavator

Boring Rig

Crawler Crane

Hari 2 Hari 3
No. Pile No Item Aktivitas Quantity Unit 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 16 17 18 19 20 21 22 23 24 1 2 3 4 5

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
1 Pabrikasi
3 Install Besi & Tremi Cor Pasang Besi
Pasang Pipa Tremi
2 jam
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
2
Pasang Pipa Tremi

2 Jam
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
3
Pasang Pipa Tremi
3

2 Jam
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
4
Pasang Pipa Tremi

4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
5
Pasang Pipa Tremi

4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
6
Pasang Pipa Tremi

4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
7
Pasang Pipa Tremi

4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan

1 Persiapan Pembersihan daerah kerja


Persiapan alat dan material
2 Pengeboran
3 Install Besi & Tremi Cor Pasang Besi
8
Pasang Pipa Tremi
8

4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
Q S H E P LA N
No PKP : 984
Halaman : 1/4
Revisi :0

Tanggal : 31 Januari 2011

Dibuat oleh : Tito Ari Bawono

Disetujui : Surachman Ambar

Hari 3 Hari 3 Hari 4


16 17 18 19 20 21 22 23 24 1 2 3 4 5 16 17 18 19 20 21 22 23 24 1 2 3 4 5 15 16 17 18 19 20 21 22 23 24
2 Jam

2 jam

2 jam

2 jam
2 jam
Pemeriksaan Oleh
Act. Main Activity Spesifikasi dan Referensi Kriteria Wika-Jakon JO
Ref. dokumen yang lain Penerimaan Construction ENG
SC Supervisor QC
Manager
5 Bored Pile Construction
5.1 Position of Bored Pile Shop Drawings Approval/Acceptable H S W - S/R
5.2 Position of Boring Method Statement 7.2 ± 25mm H S W - S/R
5.3 Drilling & Excavation
5.3.1 Excavation Record Method Statement 7.2 Approval/Acceptable - S R W S/R
5.3.2 Verticality of Bored Hole Method Statement 7.2 ≤1/100 S W R - S/R
5.3.3 Depth of Bored Hole Shop Drawings Approval/Acceptable H S R - S/R
5.3.4 Polymer Mixing Viscosity: V V ≥ 42 Sec H S W - W
PH Method Statement 7.2 PH ≥ 8 H S W - W
Density: D D < 1.03 g/cm3 H S W - W
5.3.5 Bottom Cleaning Sedimentation Method Statement 7.2 Less than 10 cm H ` W - S/R
5.4 Reinforcement Bar with Sonic Pipe `
5.4.1 Fabrication Shop Drawings Approval/Acceptable H H S/S - S/R
5.4.2 Splicing Joint Shop Drawings Approval/Acceptable H S W - S/R
5.4.3 Position of Re-Bar Cage Shop Drawings Approval/Acceptable H S W - S/R
5.5 Concreting
5.51 Casting Concrete Method Statement 7.2 Approval/Acceptable - S W - S/R
6 Laboratory Test
6.1 Compressive Concrete Strength Method Statement 7.2 σ 28 ≥ 30 mpa - H S/R W S/R

SC : Sub-Contractor H Hold Point


ENG : The Engineers Inspector W Witnees Point
S Surveillance
RDocument Review
Verifying Document
Remarks
Frequency (Self Certification)

Prior to Commencement Approved Shop Drawing


Each Pile Check List
`
Each Pile Check List
Each Pile Check List
Each Pile Check List

During Drilling Check List

After 2nd Bottom Cleaning Check List

Each Pile Check List


Each Pile Check List
Each Pile Check List
`
Each Pile Check List

16 Specimens/60 m3 Test Report


for σ7 & σ28
METODE KERJA BORE PILE

7.2.9 SAFETY OF ANALYSIS

IDENTIFIKASI BAHAYA ASPEK PENILAIAN DAN PENETAPAN PENGENDALIAN


PERIODE EVALUASI : SD 1 Pebruari 2011
KEGIATAN : BORE PILE
Aktivitas Bahaya (Fisika, Kimia, Biologi,Ergonomi, Penilaian Resiko Pengendalia
No Detail Kegiatan Radiasi, Psikologi) Faktor Penyebab/ Sumber Bahaya Resiko Legal/Persyaratan
R NR E S P TR C
1 2 3 4 5 6 7 8 9 10 11
1 Setting lokasi alat pancang NR F: Tenaga : `` 2

UU No. 1 tahun 1970

K: Alat : 3

B: Metode : Pekerja terlalu dekat alat pancang patah tulang,luka berat 4 1 H KEP.174/MEN/1986 4

E: tertabrak,terbentur Bahan : 5
2 Handling material spun pile NR F: Tenaga : patah tulang,luka berat 4 1 H Permenaker RI 04/MEN/1985 2
di lokasi kerja
K: Alat : Sling putus 3
B: Metode : Tidak ada kenek untuk membantu KEP.174/MEN/1986 4
tugas operator alat berat dalam
handling spun pile
E: Terjepit,tertimpa,terbentur Bahan :
3 Operasional Pemancangan R F: Getaran Tenaga : Gangguan kesehatan,aset warga 3 3 H 1
rusak UU No. 1 tahun 1970
K: Alat : Karakteristik alat Keputusan Menteri 2
Tenaga Kerja Kep.
51/MEN/1999
B: Metode : KEP.174/MEN/1986 3

E: Bahan : 4
5

F: Kebisingan Tenaga : Gangguan pendengaran 2 3 M UU No. 1 tahun 1970 1


K: Alat : Karakteristik alat Keputusan Menteri 2
Tenaga Kerja Kep.
51/MEN/1999
B: Metode : KEP.174/MEN/1986 3
E: Bahan : 4

4 Potong tiang pancang R F: Tenaga : Luka 1 3 L UU No. 1 tahun 1970 2


K: Alat : 3
B: Metode : metode bobok manual 4

E: terbentur,terjepit Bahan : 5

TR = Tingkat Resiko
Disetujui oleh, Disetujui oleh,
P2K3 Pusat Kadiv Operasi I

52-01-00-02-Rev 2 Hardjanto AP Suyono


Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :
Dibuat oleh :

Disetujui :

ILAIAN DAN PENETAPAN PENGENDALIAN RESIKO (IBAP3R)


NO. REVISI : 0
TANGGAL :
Pengendalian Saat Ini Waktu Pemenuhan Hasil Evaluasi Tindak Penanggung
Performa Indicator
Uraian Pengendalian Rencana Realisasi Efektif Tdk Efektif Lanjut jawab
12 13 14 15 16 17 18 19 20 21
Belum memungkinkan

barikade lokasi kerja Tidak ada laporan kecelakaan 1 5-Nov-10 SO

Safety Briefing,Instruksi Kerja Bukti hadir safety 1 5-Nov-10 SO


briefing,instruksi kerja sudah
dibagikan,tidak ada laporan
kecelakaan
Belum memungkinkan
Menggunakan Tenaga kenek untuk Kenek ada 0 5-Nov-10 Safety Officer
membantu operator
barikade lokasi kerja Barikade terpasang
Safety Briefing,Instruksi Kerja Safety briefing sudah 1 5-Nov-10 Safety Officer
dilakukan,Instruksi Kerja
sudah dibagikan
Safety Officer
Untuk saat ini belum memungkinkan tidak ada laporan gangguan Safety Officer
kesehatan
Belum memungkinkan tidak ada laporan aset warga Safety Officer
yang rusak

Untuk saat ini belum memungkinkan IK,briefing sudah 1 5-Nov-10


dilaksanakan
Instruksi kerja,safety briefing,rambu- Uji baku mutu memenuhi 1 5-Nov-10
rambu,sosialisasi+pendataan terhadap
warga sekitar
Belum memungkinkan Sosialisasi terhadap warga
sudah dilakukan
Untuk saat ini belum memungkinkan
Belum memungkinkan

Untuk saat ini belum memungkinkan Safety Officer


Instruksi kerja,safety briefing,rambu-rambu Safety briefing sudah 1 5-Nov-10 Safety Officer
dilakukan,Instruksi Kerja
sudah dibagikan
Menyediakan Ear Plug/ear muff ear plug/ear muff tersedia 1 5-Nov-10

Belum memungkinkan Safety Officer


Belum memungkinkan
Safety briefing,pembagian Instruksi Safety briefing sudah 1 5-Nov-10 Safety Officer
Kerja,rambu-rambu dilakukan,Instruksi Kerja
sudah dibagikan,rambu
terpasang
menyediakan Sarung tangan sarung tangan sudah tersedia 1 5-Nov-10

Jakarta, 12 Januari 2011 0 0


Dibuat oleh,
Koordinator K3L

Surachman Ambar