Metode Kerja Bored Pile
Metode Kerja Bored Pile
No. PKP
Halaman
Revisi
Tanggal
METODE KERJA BORED PILE Dibuat Oleh
Disetujui Oleh
7 . Metode Kerja
7.3 Pekerjaan Bored Pile
Distribution List
Daftar Isi
7.3.1 Umum
7.3.2 Spesifikasi
7.3.3 Target Quantity
7.3.4 Sumberdaya dan Alat
7.3.4.1 Tenaga
7.3.4.2 Alat
7.3.5 Material
7.3.6 Schedulle
7.3.7 Metode Konstruksi
7.3.7.1 Work Squence (Urutan Kerja)
7.3.7.2 Detail Of Work (Detail Pelaksanaan)
7.3.7.3 Construction Squence (Urutan Konstruksi)
7.3.7.4 Typical Cycle Time For Construction
7.3.8 Tabel Quality Control
7.3.9 Safety Work Analysis
S H E P LA N
: 984
: 1/2
:2
: 31 Januari 2011
: Tito Ari Bawono
: Surachman Ambar
Q S H E PL
No PKP
Halaman
Revisi
Tanggal
Dibuat oleh
Revision Status
Distribution List
Keterangan
Tanggal terima
QSHE P
No PKP
Halaman
Revisi
Tanggal
Dibuat oleh
7.2.1 Umum
Total Volume Pile cap 5800 m3 (264 Titik) dengan tebal 2.50-3.00 m, menggunakan beton dengan mutu k-350
Sesuai dokumen kontrak pile cap digunakan untuk seluruh pile cap struktural Fly Over dimana kondisi tanah pada umumny
1. Kedalaman 0 - 15 m : Clay
2. Kedalaman 15 - 30 m : Very Soft Silty Clay
3. Kedalaman 30 - 45 m : Dense Silty Sand
4. Kedalaman 45 - 60 m : cemented clay silty
7.2.2 Spesifikasi
Rekapitulasi Volume Pile cap, Galian Tanah, Beton, dan Besi Terlampir. Lihat Lampiran 01
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :
Dibuat oleh :
Disetujui :
P 39 8 1500 25
P 38 8 1500 26
P 37 8 1500 26
P 36 10 1500 24
P 35 8 1500 25
P 34 9 1500 27
P 33 10 1500 23
P 32 8 1500 23
P 31 8 1500 21
P 30 8 1500 27
P 29 8 1500 25
P 28 10 1500 25
P 26 8 1500 25
P 25 A 7 1500 26
P 24 A 8 1500 25
P 23 A 7 1500 28
P 22 A 12 1500 25
P 21 A 12 1500 25
P 20 A 6 1500 25
P 19 A 6 1500 26
P 18 A 6 1500 24
P 17 A 10 1500 25
P 16 A 9 1500 25
P 15 A 9 1500 27
P 18 B 6 1500 25
P 19 B 6 1500 25
P 20 B 7 1500 28
P 21 B 12 1500 27
P 22 B 10 1500 25
P 23 B 7 1500 25
P 24 B 7 1500 29
P 25 B 6 1500 25
Total 264
Total Volume Galian Volume Beton
Panjang (m) Per Tiang Per Pile Cap Cut Of Kedalaman Per Tiang
6,691 13,124
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :
Dibuat oleh :
Disetujui :
11,818 1,654,517
METODE KERJA BORE PILE
Operator 2
Specialist 3
Harian 3
Welder 2
Surveyer 2
Total 12
Kapasitas
No Nama Alat Jumlah Satuan
Dibuat oleh :
Disetujui :
organisasi terlampir 02
Unit Remaks
m3
Ton
kg/m3
METODE KERJA BORE PILE
7.2.6 SCHEDULLE
5/21/2018
P 39 P 38 P 37 P 36 P 35 P 34 33 32 31 30
JUMLAH TTK 8 8 8 10 8 9 10 8 8 8
PROGRESS 8 8 8 10 8 9 10 8 8 8
SISA VOLUME 0 0 0 0 0 0 0 0 0 0
Time Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri H Ri
07/02/11 25 13/02/11 25 20/02/11 25 27/02/11 25 08/03/11 25 15/03/11 25 22/03/11 25 31/03/11 25 07/04/11 25 14/04/11
07/02/11 25 14/02/11 25 21/02/11 25 28/02/11 25 08/03/11 25 15/03/11 25 23/03/11 25 31/03/11 25 07/04/11 25 14/04/11
08/02/11 25 15/02/11 25 22/02/11 25 01/03/11 25 09/03/11 25 16/03/11 25 24/03/11 25 01/04/11 25 08/04/11 25 15/04/11
09/02/11 25 16/02/11 25 23/02/11 25 01/03/11 25 10/03/11 25 17/03/11 25 24/03/11 25 02/04/11 25 09/04/11 25 16/04/11
09/02/11 25 16/02/11 25 23/02/11 25 02/03/11 25 11/03/11 25 18/03/11 25 25/03/11 25 03/04/11 25 10/04/11 25 16/04/11
10/02/11 25 17/02/11 25 24/02/11 25 03/03/11 25 11/03/11 25 18/03/11 25 26/03/11 25 03/04/11 25 10/04/11 25 17/04/11
11/02/11 25 18/02/11 25 25/02/11 25 04/03/11 25 12/03/11 25 19/03/11 25 27/03/11 25 04/04/11 25 11/04/11 25 18/04/11
11/02/11 25 18/02/11 25 25/02/11 25 04/03/11 25 13/03/11 25 20/03/11 25 27/03/11 25 05/04/11 25 12/04/11 25 19/04/11
05/03/11 25 20/03/11 25 28/03/11 25
06/03/11 25 29/03/11 25
5 200.000 5 200 200.00
250 200 225 250 200 200
START 1/24/2011 1/26/2011 2/1/2011 2/8/2011 2/15/2011 2/22/2011 3/3/2011 3/12/2011 3/22/2011 2/24/2011
FINISH 2/8/2011 2/15/2011 2/17/2011 2/19/2011 2/21/2011 3/3/2011 3/12/2011 3/21/2011 3/30/2011 3/3/2011
JUMLAH TTK 6 7 7 10 12 7 6
PROGRESS 6 7 7 10 12 7 6
SISA VOLUME 0 0 0 0 0 0 0
START 9/23/2011 9/15/2011 9/7/2011 8/27/2011 6/24/2011 8/9/2011 5/26/2011
FINISH 9/29/2011 9/22/2011 9/14/2011 9/6/2011 7/6/2011 8/6/2011 8/1/2011
MOB 9/9/2011 7/9/2011
25 24 23 22 21 20 19
30 29 28 26
TOTAL
8 8 10 8 111
8 8 10 8 111
0 0 0 0 0
H Ri H Ri H Ri H
25 21/04/11 25 28/04/11 25 06/05/11 25
25
25
21/04/11
22/04/11
25
25
28/04/11
29/04/11
25
25
07/05/11
07/05/11
25
25 P 25 24 23 22 21 20 19
25 23/04/11 25 30/04/11 25 08/05/11 25
25 23/04/11 25 30/04/11 25 09/05/11 25 7 8 7 12 12 6 6
25 24/04/11 25 01/05/11 25 09/05/11 25 7 8 7 12 12 6 6
25 25/04/11 25 02/05/11 25 10/05/11 25 0 0 0 0 0 0 0
25 26/04/11 25 03/05/11 25 11/05/11 25 4/22/2011 5/24/2011 5/21/2011 5/27/2011 6/8/2011 6/16/2011 5/14/2011
03/05/11 25 5/2/2011 5/17/2011 5/22/2011 6/3/2011 6/20/2011 6/22/2011 5/20/2011
04/05/11 25 6/6/2011
Dibuat oleh:
Disetujui :
H Ri H
25 26/07/11 25
25 26/07/11 25
25 27/07/11 25
25 28/07/11 25
25 28/07/11 25
25 29/07/11 25
TOTAL
6 6 61
6 6 61
0 0 0
5/26/2011 5/14/2011
8/1/2011 5/25/2011
19 18
17 16 15
TOTAL GRAND TOTAL
JUMLAH TTK 10 9 9 28 264
PROGRESS 10 9 9 28 264
SISA VOLUME 0 0 0 0 0
START 4/30/2011 4/19/2011 4/14/2011
FINISH 5/11/2011 4/26/2011 4/28/2011
19 18
TOTAL
6 6 64 JUMLAH TTK
6 6 64 PROGRESS
0 0 0 SISA VOLUME
5/14/2011 5/6/2011
5/20/2011 5/12/2011
5/14/2011 Ri H Ri H Ri H
03/07/11 25 10/07/11 25 18/07/11 25
H Ri H 03/07/11 25 11/07/11 25 19/07/11 25
25 27/06/11 25 04/07/11 25 12/07/11 25 19/07/11 25
25 28/06/11 25 05/07/11 25 12/07/11 25 20/07/11 25
25 28/06/11 25 05/07/11 25 13/07/11 25 21/07/11 25
25 29/06/11 25 06/07/11 25 14/07/11 25 21/07/11 25
25 30/06/11 25 07/07/11 25 15/07/11 25 22/07/11 25
25 01/07/11 25 08/07/11 25 15/07/11 25 23/07/11 25
08/07/11 25 16/07/11 25 24/07/11 25
Feb Mar Apr May Jun Jul Aug Sep Oct
Schdule Detail Jumlah Tiang Mulai Selesai Kapasitas Durasi
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 36 37 38 39 36
P 39 8 7-Feb 11-Feb 1.6 5
P 38 8 12-Feb 17-Feb 1.6 5
P 37 8 18-Feb 23-Feb 1.6 5
P 36 10 23-Feb 2-Mar 1.6 6
P 35 8 3-Mar 8-Mar 1.6 5
P 34 9 8-Mar 14-Mar 1.6 6
P 33 10 15-Mar 21-Mar 1.6 6
P 32 8 22-Mar 27-Mar 1.6 5
P 31 8 27-Mar 1-Apr 1.6 5
P 30 8 2-Apr 7-Apr 1.6 5
P 29 8 8-Apr 13-Apr 1.6 5
P 28 10 13-Apr 20-Apr 1.6 6
P 26 8 20-Apr 25-Apr 1.6 5
P 25 A 7 21-Apr 25-Apr 1.6 4
Schedule Detail
Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Operator 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Manpower
Specialist 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Manpower
Harian 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Welder 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Surveyer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Total 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
Oct
37 38 39
1 1
2 2 72
3 3 108
3 3 108
2 2 72
2 2 72
12 12 432
METODE KERJA BORE PILE
Flow Chart
1 st sesuai instruksi Pembersihan kedua Bagian dasar - Cek sedimen sebelum dan sesuda
konsultan lubang galian dengan Air -Lift 1)
1 st sesuai instruksi Pembersihan kedua Bagian dasar
konsultan lubang galian dengan Air -Lift 1)
Dibuat oleh :
1 2 3 4 5 6
Drilling
Machine
Crawler crane
Pipa
Casing Besi
Tulangan
Mata Bor
`
Pengeboran Pemasangan Casing Pemasangan Besi Tulangan Pengecoran Awal Pengecoran lanjutan (Tremie diangkat)
Pelepasan Casing
Q S H E P LA N
No PKP :
Halaman :
Revisi :
Tanggal :
Dibuat oleh :
cara melompat.
le yang baru
ganggu oleh
METODE PEKERJAAN BORE PILE
Boring Rig
Crawler Crane
Hari 2 Hari 3
No. Pile No Item Aktivitas Quantity Unit 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 16 17 18 19 20 21 22 23 24 1 2 3 4 5
2 Jam
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
2 Jam
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
4 Pengecoran
5 Pembuangan Lumpur
6 Pembersihan
Q S H E P LA N
No PKP : 984
Halaman : 1/4
Revisi :0
2 jam
2 jam
2 jam
2 jam
Pemeriksaan Oleh
Act. Main Activity Spesifikasi dan Referensi Kriteria Wika-Jakon JO
Ref. dokumen yang lain Penerimaan Construction ENG
SC Supervisor QC
Manager
5 Bored Pile Construction
5.1 Position of Bored Pile Shop Drawings Approval/Acceptable H S W - S/R
5.2 Position of Boring Method Statement 7.2 ± 25mm H S W - S/R
5.3 Drilling & Excavation
5.3.1 Excavation Record Method Statement 7.2 Approval/Acceptable - S R W S/R
5.3.2 Verticality of Bored Hole Method Statement 7.2 ≤1/100 S W R - S/R
5.3.3 Depth of Bored Hole Shop Drawings Approval/Acceptable H S R - S/R
5.3.4 Polymer Mixing Viscosity: V V ≥ 42 Sec H S W - W
PH Method Statement 7.2 PH ≥ 8 H S W - W
Density: D D < 1.03 g/cm3 H S W - W
5.3.5 Bottom Cleaning Sedimentation Method Statement 7.2 Less than 10 cm H ` W - S/R
5.4 Reinforcement Bar with Sonic Pipe `
5.4.1 Fabrication Shop Drawings Approval/Acceptable H H S/S - S/R
5.4.2 Splicing Joint Shop Drawings Approval/Acceptable H S W - S/R
5.4.3 Position of Re-Bar Cage Shop Drawings Approval/Acceptable H S W - S/R
5.5 Concreting
5.51 Casting Concrete Method Statement 7.2 Approval/Acceptable - S W - S/R
6 Laboratory Test
6.1 Compressive Concrete Strength Method Statement 7.2 σ 28 ≥ 30 mpa - H S/R W S/R
K: Alat : 3
B: Metode : Pekerja terlalu dekat alat pancang patah tulang,luka berat 4 1 H KEP.174/MEN/1986 4
E: tertabrak,terbentur Bahan : 5
2 Handling material spun pile NR F: Tenaga : patah tulang,luka berat 4 1 H Permenaker RI 04/MEN/1985 2
di lokasi kerja
K: Alat : Sling putus 3
B: Metode : Tidak ada kenek untuk membantu KEP.174/MEN/1986 4
tugas operator alat berat dalam
handling spun pile
E: Terjepit,tertimpa,terbentur Bahan :
3 Operasional Pemancangan R F: Getaran Tenaga : Gangguan kesehatan,aset warga 3 3 H 1
rusak UU No. 1 tahun 1970
K: Alat : Karakteristik alat Keputusan Menteri 2
Tenaga Kerja Kep.
51/MEN/1999
B: Metode : KEP.174/MEN/1986 3
E: Bahan : 4
5
E: terbentur,terjepit Bahan : 5
TR = Tingkat Resiko
Disetujui oleh, Disetujui oleh,
P2K3 Pusat Kadiv Operasi I
Disetujui :
Surachman Ambar