JDR OUTSTANDING ISSUE

No Issue Date issue Date


resolve
1 Water reticulation 18/04/2018 Pending
2 Revise structure drawing received 29 march 2018 29/03/2018 Complete
3 Instruction by architect on 4 April 2018 to hold swimming pool 04/04/2018 Pending
and part of RC wall still don’t have further instruction
4 Increasing size stump 7/04/2018 12/04/2018
5 Increasing size column 30/04/2018 03/05/2018
6 Referring to site memo epsb no 010, there is discrepancy 16/04/2018 25/04/2018
between new drawing and existing pad footing
7 Referring to site memo epsb no 006, we still don’t receive 07/04/2018 Pending
confirmation on rain water down pipe
8 Referring to site memo EPSB no 006, we still don’t receive 07/04/2018 13/04/2018
confirmation on level 2, level 3 and flat roof structure drawing
9 Instruction by architect on 18 April, to change building design 18/04/2018 Pending
drawing
10 Sub-contractor trade still not appoints 18/04/2018 Pending
11 Working time on site 20/02/2018 30/05/2018
12 Discrepancies existing structure 18/04/2018 29/03/2018
13 Detailed Staircase Drawing (Not Specified) 14/05/2018 Pending
14
15
16