resolve 1 Water reticulation 18/04/2018 Pending 2 Revise structure drawing received 29 march 2018 29/03/2018 Complete 3 Instruction by architect on 4 April 2018 to hold swimming pool 04/04/2018 Pending and part of RC wall still don’t have further instruction 4 Increasing size stump 7/04/2018 12/04/2018 5 Increasing size column 30/04/2018 03/05/2018 6 Referring to site memo epsb no 010, there is discrepancy 16/04/2018 25/04/2018 between new drawing and existing pad footing 7 Referring to site memo epsb no 006, we still don’t receive 07/04/2018 Pending confirmation on rain water down pipe 8 Referring to site memo EPSB no 006, we still don’t receive 07/04/2018 13/04/2018 confirmation on level 2, level 3 and flat roof structure drawing 9 Instruction by architect on 18 April, to change building design 18/04/2018 Pending drawing 10 Sub-contractor trade still not appoints 18/04/2018 Pending 11 Working time on site 20/02/2018 30/05/2018 12 Discrepancies existing structure 18/04/2018 29/03/2018 13 Detailed Staircase Drawing (Not Specified) 14/05/2018 Pending 14 15 16