Professional Documents
Culture Documents
BI BJ Kelompok R3 Dan R4 (Sawah) - Update
BI BJ Kelompok R3 Dan R4 (Sawah) - Update
BI = Mp/Vt
=(To-C)-C/ (¼ x 3,14 x d x d x t)
= 63,55-9,72 / (¼ x 3,14 x 5,1 x 5,1 x 4,65)
= 53,83 gram/ 94,94 cm3
BI = 0,57 gram /cm3
PERHITUNGAN BARU (KROSCEK) Commented [FK1]:
Perhitungan BI
1. Vt = ¼ x π x d2 x t
= 0,25 x 3,14 x 5,12 x 4,65
= 94,94
2. Kadar air sub-sampel (W) = Ma/Mp
= ((Tb + K) – (To+K)) / ((To+K) – K)
= (109,72-63,55) / (63,55-9,72)
= 46,17/53,83
= 0,86
3. Massa padatan (Mp) = Berat total / (1+ ka sub)
= 165,19 / (1+0,86)
= 88,81
4. BI = Mp/Vt
= 88,81 / 94,94
= 0,93 g/cm3
Perhitungan BJ
L L + To L + To + A
56,87 76,87 166,93
1. BJ = MP/VP
= ((L + To) – L) / (100 – ( L +To + A) – ( L + To))
= (76,87 – 56,87) / (100 – (166,93 – 76,87)
= 20 / (100-90,06)
= 20 / 9,94
= 2,01
Perhitungan Porositas
Porositas = (1-(BI/BJ))*100
= (1-(0,93/2,01))*100
= 53,73 %