You are on page 1of 2

PRE-CONCEPT INVESTIGATION REPORT REVIEW MEETING

PROPOSED WAREHOUSE BUILDING FOR LUISE MARINE EQUIPMENT SALE AT AL WAKRA (MANATEQ).
Project Reference: 16-511 Date: 08/08/2016

MEETING NO: 01
DATE: 06rd August 2016 Meeting Place: Louis Marine Equipment Office
Attendees:

R.A.Fernandez RF General Manager, Louis Marine Equipment.

Videsh VH Operational Manager, Louis Marine Equipment.

Sam Antony SA Project Manager, SAS


Ayman Elsheshtawy AE Head of Architect, KAYAN

Regan Jeyakumar RJ Sr. Civil / Structural Engineer, SAS


Sbri Ibrahim SI Sr. Mechanical Engineer, KAYAN
SM Contract Manager, SAS
Stalin Micheal Raj

Item Action
Matters Discussed Deadline Remarks
No by
A. General
Purpose of the Meeting

1.A.1 This meeting was called by SA, to understand and explain All - Note
the project to Architect team as well as structural team.

Review on Introduction

Mr.R.A.Fernandez (RF) took the team to visit the current


1.A.3 All -- Note
functions and explained in details. He explained the new
requirements.

Action
Item
Matters Discussed by Deadline Remarks
No

B. Architectural Design

Dune Building @ The Tornado Tower_16504 Page1


PRE-CONCEPT INVESTIGATION REPORT REVIEW MEETING
PROPOSED WAREHOUSE BUILDING FOR LUISE MARINE EQUIPMENT SALE AT AL WAKRA (MANATEQ).
Project Reference: 16-511 Date: 08/08/2016

As per Manateq 55% GF coverage of the total plot area but in


1.B.1 11-Aug-
the client concept drawing was differed, then AS asked to AN AN
2016
to be checked in MANATEQ specs.

Requirements of crane: RF said that the carne capacity 6.50


1.B.2 tonne for Boat Service Area, 5.50 tonne for Life Raft Service All --- Note
Area.
11-Aug-
1.B.3 Labour accommodation space was discussed with AN, and AN
2016
will check with Manateq and reply.
C. Structural Design
Floor height by the entrance where the trucks loading and
unloading. AS said that is cost effective, then it was decided
11-Aug-
1.C.1 to be discussed during final design. RF to be confirmed prior RF
2016
to final design.

Concept of drawing should be ready by a week. SA/AN 11-Aug-


1.C.2
2016

1.C.3 Ceiling height will be finalized during next meeting. AN -- Note

D. Mechanical Services
1.D.1 Ventilating system will be discussed during final design stage. AN --

--
E. Electrical Design
1.E.1 . -- --
F. Fire & Life Safety Design
1.F.1 --
G. Post Meeting Notes

SA asked to AN, as per Manateq requirements, any special


item to be submitted by us, other than the normal building
1.H.1 AN -- Note
submittal with in Doha. AN said that he will check in design
criteria and MANATEQ special requirements.

H. Next Meeting
Next Meeting
1.I.1 Next meeting shall be on Thursday 11th August 2016 @ 10:00 Note -- --
AM

Dune Building @ The Tornado Tower_16504 Page2

You might also like