Professional Documents
Culture Documents
Pre-Fat RH01 - D30 Distance Test Report PDF
Pre-Fat RH01 - D30 Distance Test Report PDF
1 D30 RELAY...................................................................................................................... 3
1.1 RELAY DATA .................................................................................................................................... 3
1.2 VISUAL INSPECTION & SYSTEM CHECK ........................................................................................... 3
1.3 COMMUNICATIONS ........................................................................................................................ 3
1.4 POWER SUPPLY............................................................................................................................... 3
1.5 CONTACT INPUTS............................................................................................................................ 4
1.6 CONTACT OUPUTS .......................................................................................................................... 5
1.7 TERMINAL BLOCKS V&I CONNECTIONS .......................................................................................... 6
1.8 VOLTAGE AND CURRENT INPUTS METERING ................................................................................. 6
1.8.1 CT/VT SETTINGS 6
1.8.2 SIGNAL SOURCES6
1.8.3 BREAKERS 7
1.8.1 79 - AUTORECLOSE ..................................................................................................................... 8
1.8.2 UNBALANCED SYSTEM TO IDENTIFY PHASES............................................................................. 9
1.8.3 BALANCED V&I SYSTEM.............................................................................................................. 9
1.9 PROTECTION ELEMENTS ............................................................................................................... 10
1.9.1 PHASE DISTANCE (21) Z1 3 PHASE FAULT ................................................................................ 10
1.9.2 PHASE DISTANCE (21) Z2 3 PHASE FAULT ................................................................................ 11
1.9.3 GROUND DISTANCE (21) Z1...................................................................................................... 12
1.9.4 GROUND DISTANCE (21) Z2...................................................................................................... 13
1.10 PROTECTION SUMMARY............................................................................................................... 14
1.11 OPERATION TABLE ........................................................................................................................ 15
2 ADDITIONAL COMMENTS/FACTS IMPACTING THE FIELD SERVICE/ETC.: ...................... 16
3 OPEN POINTS: .............................................................................................................. 16
2
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
1 D30 RELAY
MANUFACTURER GE MULTILIN
PANEL IDENTIFICATION H01+RH01
RELAY ORDER CODE D30-N03-HKH-F8L-H6N-M6N-P6C
SERIAL NUMBER AAAC16000152
SETTINGS DOCUMENT Customer propietary
FIRMWARE REVISION 6.0x
IP ADDRESS 192.168. 1. 57
MODBUS ADDRESS 254
PROTECTION ELEMENTS 21P, 21G, 79
TEST DATE
Equipment integrity: OK 18/3/17
LED test: OK 18/3/17
Frontal display: OK 18/3/17
Keypad: OK 18/3/17
Equipment grounding: OK 18/3/17
1.3 COMMUNICATIONS
TEST DATE
Ethernet communication: OK 18/3/17
Serial communication: OK 18/3/17
IRIG-B NA 18/3/17
SNTP NA 18/3/17
Configuration file download (Factory default.urs) NA 18/3/17
Configuration file upload (D30:
OK 18/3/17
D30_NdhiToHoma_13032017.urs)
MEASURE DATE
Supply type: DC 107.2Vdc 18/3/17
3
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
4
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
5
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
CT Feeder F1 VT BANK F5
CURRENTS VOLTAGES
A 1 1
B 2 2
XCT-1 VA VT-1
C 3 3
N 4 4
CT SETTINGS
PARAMETER CT F1
Phase CT Primary 250 OK
Phase CT Secondary 1 OK
Ground CT Primary 250 OK
Ground CT Secondary 1 OK
VT SETTINGS
PARAMETER VT F5
Phase VT Connection Wye OK
Phase VT Secondary 63.5 V OK
Phase VT Ratio 300 :1 OK
Auxiliary VT Connection Vbg OK
Auxiliary VT Secondary 63.5 V OK
Auxiliary VT Ratio 300 :1 OK
SIGNAL SOURCES
PARAMETER SCR 1 SRC2
Name Feeder BusSyc
Phase CT F1 None
Ground CT F1 None
Phase VT F5 None
Aux VT None F5
6
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
1.8.3 BREAKERS
BREAKERS
SETTING PARAMETER
Breaker 1 Function Enabled
Breaker 1 Push Button Control Disabled
Breaker 1 Name Bkr 1
Breaker 1 Mode 3-Pole
Breaker 1 Open OFF
Breaker 1 Block Open OFF
Breaker 1 Close ManualClsCMD On(H6c)
Breaker 1 Block Close OFF
Breaker 1 Phase A/3-Pole Closed CB CLOSED On(M5c)
Breaker 1 Phase A/3-Pole Opened CB OPEN On(M5a)
Breaker 1 Phase B Closed OFF
Breaker 1 Phase B Opened OFF
Breaker 1 Phase C Closed OFF
Breaker 1 Phase C Opened OFF
Breaker 1 Toperate 0.070 s
Breaker 1 External Alarm OFF
Breaker 1 Alarm Delay 0.000 s
Breaker 1 Manual Close Recal Time 0.000 s
Breaker 1 Out Of Service OFF
Breaker 1 Events Enabled
7
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
1.8.1 79 - AUTORECLOSE
AUTORECLOSE 1
SETTING PARAMETER
Function Enabled
Initiate AR INIT On (VO2)
Block 79 BLOCK/OUT On (VO3)
Max Number Of Shots 2
Reduce Max to 1 OFF
Reduce Max to 2 OFF
Reduce Max to 3 OFF
Manual Close ManualClsCMD On(H6c)
Manual Reset from LO OFF
Reset Lockout if Breaker Closed On
Reset Lockout On Manual Close On
Breaker Closed BREAKER 1 CLOSED
Breaker Open BREAKER 1 OPEN
Block Time Upon Manual Close 10.00 s
Dead Time Shot 1 0.50 s
Dead Time Shot 2 5.00 s
Dead Time Shot 3 3.00 s
Dead Time Shot 4 4.00 s
Add Delay 1 OFF
Delay 1 0.00 s
Add Delay 2 OFF
Delay 2 0.00 s
Reset Lockout Delay 25.00 s
Reset Time 25.00 s
Incomplete Sequence Time 10.00 s
Events Enabled
8
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
Vph-g Mag V Angle Vph-g Mag V Angle I Mag I Angle I Mag I Angle
METERING OK METERING OK
METERING OK METERING OK
9
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
10
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
11
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
12
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
13
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
14
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
D30
FUNCTIO CB
CB TRIP CB TRIP InitCBFt AR INIT
N BLOCK
TC1 TC2 oBCU On
BCU
21P X X X X
21G X X X X
79 X
21G Z1 X
21G Z2 X
15
Project Name: Sondu (Therdibuoro)- Homa Bay (Ndhiwa)-
Awendo Electrification Project
Customer: Republic of Kenya- Ministry of Energy
PO Number:
Commissioning Number:
GE MULTILIN Representative
Engineer Name: Organization: GE Power Management
3 Open points:
16