You are on page 1of 1

Ref. No.

: 012/SIL/SJICSR/CL/RA/2017-18/VOI-1/012
To,
The Project Coordinator,
Mukesh Associates,
Division- 2,
2/6, Ranganathar Avenue,
Pernmal Malai Main Road,
Narasothipatty,
Salem 636004

Project: Construction of 350 Bedded Hospital Complex for Sri Jayadeva


Institute of Cardiovascular Sciences and Research, Mysore

Sub: Submission of quantity variation beyond 125% & Extra Item Rate analysis
for Electrical Items
Dear Sir,

With reference to the above, we are pleased to submit the rate analysis for
quantity variation beyond 125% & extra item with summary sheet for your
reference & necessary approval at the earliest of below mentioned items.
1.Quantity variation beyond 125% as per SR analysis- Page No.-( 01 to 16 ).
2.Extra item as per SR analysis-Page No.-( ).
3.Extra item MR analysis for AHU starter Panel-Page No.-( ).
4.Extra item cable, Panel, Light Fixture & miscellaneous-page No.-( )
The rate analysis of the items has been prepared as per agreement clause no-
15.5 & 15.6.
Thanking you & assuring the best service always.