Perhitungan Alinyemen Horizontal
Perhitungan Alinyemen Horizontal
PERHITUNGAN KONSTRUKSI
- Koordinat
A (937,838 ; 2219,726)
𝑑1 = √(𝑥2 − 𝑥1 )2 + (𝑦2 − 𝑦1 )2
𝑑2 = √(𝑥3 − 𝑥2 )2 + (𝑦3 − 𝑦2 )2
𝑑3 = √(𝑥4 − 𝑥3 )2 + (𝑦4 − 𝑦3 )2
𝑑4 = √(𝑥5 − 𝑥4 )2 + (𝑦5 − 𝑦4 )2
𝑑 = 𝑑1 + 𝑑2 + 𝑑3 + 𝑑4
= 780,933 𝑚 + 826,929 𝑚 + 756,199 𝑚 + 696,574 𝑚
= 3060,635 𝑚
= 113,865°
𝑥3 − 𝑥2
𝛼𝑃𝐼1 = 𝑎𝑟𝑐 𝑡𝑔
𝑦3 − 𝑦2
2450,444 − 1652,002
= 𝑎𝑟𝑐 𝑡𝑔
1688,597 − 1903,774
= −74,91734 + 180°
= 105,083°
𝑥4 − 𝑥3
𝛼𝑃𝐼2 = 𝑎𝑟𝑐 𝑡𝑔
𝑦4 − 𝑦3
2899,445 − 2450,444
= 𝑎𝑟𝑐 𝑡𝑔
1080,128 − 1688,597
= −36,42433 + 180°
= 143,576°
𝑥5 − 𝑥4
𝛼𝑃𝐼3 = 𝑎𝑟𝑐 𝑡𝑔
𝑦5 − 𝑦4
3473,486 − 2899,445
= 𝑎𝑟𝑐 𝑡𝑔
685,550 − 1080,128
= −55,49657 + 180°
= 124,503°
∆2 = 𝛼𝑃𝐼2 − 𝛼𝑃𝐼1
= 143,576° − 105,083°
= 38,493° → 𝑆𝑝𝑖𝑟𝑎𝑙 − 𝑆𝑝𝑖𝑟𝑎𝑙
∆3 = 𝛼𝑃𝐼3 − 𝛼𝑃𝐼2
= 124,503° − 143,576°
= 19,073° → 𝑆𝑝𝑖𝑟𝑎𝑙 − 𝐶𝑖𝑟𝑐𝑙𝑒 − 𝑆𝑝𝑖𝑟𝑎𝑙
c. Alinyemen Tikungan
1) Alinyemen PI1 → Full Circle
Data tikungan :
Kecepatan rencana = 60 km/jam
en = 2%
emax = 10%
sudut bearing (Δ) = 8,782°
R = 850 m
e = 2,7% (tabel Bina Marga)
Ls = 40 m (tabel Bina Marga)
fm = 0,192 – (0,000625*60)
= 0,155
0,1 2 . 0,1
𝑒 = −( 2
𝑥 1,6852 ) + ( 𝑥 1,685)
12,886 12,886
= 0,024
= 2,4% → 𝑁𝑖𝑙𝑎𝑖 𝑒 𝑠𝑎𝑚𝑎 𝑠𝑒𝑝𝑒𝑟𝑡𝑖 𝑑𝑖 𝑇𝑎𝑏𝑒𝑙 𝐵𝑀 2,4%
Ambil e = 2,4%
′
𝑣3 𝑣. 𝑒
𝑏. 𝐿 𝑠 = 0,022 . − 2,727
𝑅. 𝑐 𝑐
603 60 .0,024
= 0,022 . − 2,727
850 . 0,4 0,4
= 4,159 𝑚
Tabel Bina Marga, L’s = 40 m, ambil L’s = 40 m
𝐿𝑐 = 0,01745 . ∆° . 𝑅
= 0,01745 . 8,782° .850
= 130,259 𝑚
1
𝑇𝑐 = 𝑅 . tan ∆
2
1
= 850 . tan .8,782°
2
𝑅
𝐸𝑐 = −𝑅
1
cos 2 ∆
850
= − 850
1
cos 2 . 8,782°
= 2,502 𝑚
Check Ec ->
∆
𝐸𝑐 = 𝑇𝑐 . tan
4
8,782°
= 65,270 . tan
4
= 2,502 → 𝑜𝑘𝑒!
𝑏 ′ = 𝑏 + 𝑅 − √𝑅 2 − 𝑃2
Td = √𝑅 2 + 𝐴(2𝑃 + 𝐴)-R
= 0,0095 m
60
= 0,105 .
√850
= 0,2161 m
B = n (b’ + c ) + ( n – 1 ). Td + Z
= 8,870 m
90.𝐽ℎ 90.𝐿𝑐
m = R . ( 1 - Cos. )+1/2.(Jh-Lc).Sin.
𝜋𝑅 𝜋𝑅
90.75 90.130,259
= 850.( 1 - Cos. )+ 1/2.(75-130,259).Sin.
𝜋.850 𝜋.850
= 2,250 m
fm = 0,192 – (0,000625*60)
= 0,155
0,1 2
2 . 0,1
𝑒 = −( 𝑥 8,953 ) + ( 𝑥 8,953)
12,8862 12,886
= 0,091
= 9,1% → 𝑁𝑖𝑙𝑎𝑖 𝑒 𝑠𝑎𝑚𝑎 𝑠𝑒𝑝𝑒𝑟𝑡𝑖 𝑑𝑖 𝑇𝑎𝑏𝑒𝑙 𝐵𝑀 9,1%
Ambil e = 9,1%
𝑣3 𝑣. 𝑒
𝑏. 𝐿′ 𝑠 = 0,022 . − 2,727
𝑅. 𝑐 𝑐
603 60 .0,091
= 0,022 . − 2,727
160 . 0,4 0,4
= 37,026 𝑚
Tabel Bina Marga, L’s = 70 m, ambil L’s = 70 m
1
𝜃𝑠 = .∆
2
1
= . 38,493°
2
= 19,247
𝑅 . 𝜃𝑠
𝐿𝑠 ∗ =
28,648
160 . 19,247
=
28,648
= 107,495 𝑚
𝐿𝑠 ∗ = 107,492 𝑚 > 𝐿𝑠 = 70 𝑚 → 𝑜𝑘𝑒!
X* = 0,98860 K* = 0,49809
Y* = 0,11194 P* = 0,02810
K = K* x Ls P = P* x Ls
= 0,49809 x 70 m = 0,02810 x 70 m
= 34,866 = 1,967
1
Ts = (R + P) tan 2 ∆ + 𝐾
1
= (160 + 1,124) tan 38,493° + 34,866
2
= 91,122
(𝑅 + 𝑃)
𝐸𝑠 = − 𝑅
1
cos 2 ∆
(160 + 1,967)
= − 160
1
cos 2 38,493°
= 11,555
𝑏 ′ = 𝑏 + 𝑅 − √𝑅 2 − 𝑃2
Td = √𝑅 2 + 𝐴(2𝑃 + 𝐴)-R
= 0,050 m
60
= 0,105 .
√160
= 0,498 m
B = n (b’ + c ) + ( n – 1 ). Td + Z
= 9,380 m
90 . 𝐽ℎ
𝑚 = 𝑅 (1 − cos )
𝜋. 𝑅
90 .75
= 160 (1 − cos )
𝜋. 160
= 4,374 𝑚
fm = 0,192 – (0,000625*60)
= 0,155
0,1 2 . 0,1
𝑒 = −( 2
𝑥 4,0932 ) + ( 𝑥 4,093)
12,886 12,886
= 0,053
= 5,3% → 𝑁𝑖𝑙𝑎𝑖 𝑒 𝑠𝑎𝑚𝑎 𝑠𝑒𝑝𝑒𝑟𝑡𝑖 𝑑𝑖 𝑇𝑎𝑏𝑒𝑙 𝐵𝑀 5,3%
Ambil e = 5,3%
𝑣3 𝑣. 𝑒
𝑏. 𝐿′ 𝑠 = 0,022 . − 2,727
𝑅. 𝑐 𝑐
603 60 .0,053
= 0,022 . − 2,727
350. 0,4 0,4
= 12,263 𝑚
Tabel Bina Marga, L’s = 40 m, ambil L’s = 40 m
28,648
𝜃𝑠 = 𝑥 𝐿𝑠
𝑅
28,648
= 𝑥 40
350
= 3,274°
∆′ = ∆ − 2𝜃𝑠
= 19,073° − 3,274°
= 15,799°
X* = 0,99965 K* = 0,49994
Y* = 0,01978 P* = 0,00494
K = K* x Ls P = P* x Ls
= 0,49994 x 40 m = 0,00494 x 40 m
= 19,998 = 0,198
𝐿𝑐 = 0,01745. ∆′ . 𝑅
= 0,01745. 15,799° ′ . 350
L = 2Ls + Lc
= (2 x40) +96,492
= 176,492 m
1
Ts = (R + P) tan 2 ∆ + 𝐾
1
= (350 + 0,198) tan 19,073° + 19,998
2
= 78,830 𝑚
(𝑅 + 𝑃)
𝐸𝑠 = − 𝑅
1
cos 2 ∆
(350 + 0,198)
= − 350
1
cos 2 19,073°
= 5,105 𝑚
𝑏 ′ = 𝑏 + 𝑅 − √𝑅 2 − 𝑃2
Td = √𝑅 2 + 𝐴(2𝑃 + 𝐴)-R
= 0,023 m
60
= 0,105 .
√350
= 0,337 m
B = n (b’ + c ) + ( n – 1 ). Td + Z
= 10,02 m
90 . 𝐽ℎ
𝑚 = 𝑅 (1 − cos )
𝜋. 𝑅
90 .75
= 350 (1 − cos )
𝜋. 350
= 2,007 𝑚
STA A = 0 + 000
STA TC = d1 – Tc
=780,933 m – 65,270 m
= 0 + 715,663 m
STA CT =STA TC + Lc
= 0 + 715,663 + 130,259ss
= 0 + 845,922
= 1 + 516,459
= 1 + 516,459 + 2.70
= 1+656,459
= 2 + 242,706
STA SC = STA TS + Ls
= 2 + 242,706 + 40
= 2+ 282,706
STA CS = STA SC + Lc
= 2+ 282,706 + 96,492
= 2 + 379,198
STA ST = STA CS + Ls
= 2 + 419,198
= 3 + 036,942
Kontrol Overlapping
Titik Awal proyek (A) dengan lengkung pertama (FC)
Tc + 30 m < d1
65,270 m + 30 m < 780,933 m
95,270 m < 780,933 m .. Ok!