Professional Documents
Culture Documents
“The financial world never stops, so having a dependable power source for our data center is critical. Our system was built to
be redundant so we can perform maintenance without interrupting power. Effective and efficient, our Cat® C32 diesel generator
sets give us 2 MW of power that seamlessly step in. We’ve had outages that didn’t slow us down for a second and went largely
unnoticed. Backed by Cat power, we’ve designed and built one of the most efficient data centers in North America.”
© 2015 Caterpillar. All Rights Reserved. CAT, CATERPILLAR, BUILT FOR IT, their respective logos, “Caterpillar Yellow,”
the “Power Edge” trade dress, as well as corporate and product identity used herein, are trademarks of Caterpillar
and may not be used without permission.
input #2 at www.csemag.com/information
input #3 at www.csemag.com/information
MARCH 2015
COVER STORY
26 | Integration: BIM design
Building information modeling (BIM) is used frequently
when working across multiple disciplines, including
mechanical, electrical, plumbing, and fire protection engi-
neering, and also with other stakeholders such as archi-
tects and contractors.
ED PAUL
FEATURES
32 | Energy performance in
mission critical facilities
ON THE COVER: This overall view of a building shows a single Mission critical facilities, such as data centers, are judged
mechanical, electrical, plumbing, and fire protection (MEP/ carefully on their energy use. Engineers should focus on
FP) design model representing accurate location and overall
the codes and standards that dictate energy performance
dimensions of equipment and systems. This image is rendered
from a single Revit model containing all MEP/FP disciplines. and how building energy performance can be enhanced.
Courtesy: Arup BILL KOSIK, PE, CEM, BEMP, LEED AP BD+C
DEPARTMENTS
07 | Viewpoint 19 | Codes & Standards 40 | Selecting fire pumps
The key for fire protection engineers is to understand the
Work smarter, not harder Piping arrangements for fire
requirements of both NFPA 20 and NFPA 70 to properly
pumps
09 | Research choose and configure a fire pump so that the fire protec-
tion systems can serve their intended use.
Seven key findings for the 25 | Digital Edition
fire and life safety industry Exclusives ALLYN J. VAUGHN, PE, FSFPE, and RICK REYBURN, PE
CONSULTING-SPECIFYING ENGINEER (ISSN 0892-5046, Vol. 52, No. 2, GST #123397457) is published 11x per year, monthly except in February, by CFE Media, LLC, 1111 W. 22nd Street, Suite
#250, Oak Brook, IL 60523. Jim Langhenry, Group Publisher /Co-Founder; Steve Rourke CEO/COO/Co-Founder. CONSULTING-SPECIFYING ENGINEER copyright 2015 by CFE Media, LLC. All rights reserved. CONSULTING-
SPECIFYING ENGINEER is a registered trademark of CFE Media, LLC used under license. Periodicals postage paid at Oak Brook, IL 60523 and additional mailing offices. Circulation records are maintained at CFE Media, LLC, 1111
W. 22nd Street, Suite #250, Oak Brook, IL 60523. E-mail: customerservice@cfemedia.com. Postmaster: send address changes to CONSULTING-SPECIFYING ENGINEER, 1111 W. 22nd Street, Suite #250,
Oak Brook, IL 60523. Publications Mail Agreement No. 40685520. Return undeliverable Canadian addresses to: 1111 W. 22nd Street, Suite #250, Oak Brook, IL 60523. Email: customerservice@
cfemedia.com. Rates for nonqualified subscriptions, including all issues: USA, $150/yr; Canada/Mexico, $180/yr (includes 7% GST, GST#123397457); International air delivery $325/yr. Except for special issues where price
changes are indicated, single copies are available for $30.00 US and $35.00 foreign. Please address all subscription mail to CONSULTING-SPECIFYING ENGINEER, 1111 W. 22nd Street, Suite #250, Oak Brook, IL 60523. Printed
in the USA. CFE Media, LLC does not assume and hereby disclaims any liability to any person for any loss or damage caused by errors or omissions in the material contained herein, regardless of whether such errors result from
negligence, accident or any other cause whatsoever.
Facebook:
Upcoming webcasts www.facebook.com/CSEmag
Register for upcoming webcasts and
earn American Institute of Architects Google+:
http://google.com/+csemag
accredited learning units (LU). Can’t watch
it live? Watch it on-demand at www.csemag.com/webcast.
LinkedIn:
March 19: Critical Power: Standby power for mission critical facilities http://tinyurl.com/CSElinkedin
Twitter:
Top articles of the week www.twitter.com/AmaraRozgus
Each week, Consulting-Specifying Engineer highlights the top www.twitter.com/CSEmag
articles from the previous week based on the feedback from the
website viewers. To see past articles from each week, search SlideShare:
“Top 5 Consulting-Specifying Engineer articles.” www.slideshare.net/ConsultingSpecifyingEngineer
Headquartered in Victoria, British Columbia, in a modern and environmentally constructed LEED Platinum-Certified
facility, we design and develop internet-connected building controls for a wide range of green buildings, including
schools, hospitals, universities, recreational and commercial facilities. To learn more about our solutions for
sustainability, and opportunities in the green buildings industry, please visit our website or sign-up for a facility tour at:
www.reliablecontrols.com/corporate/facility/tour.php
input #4 at www.csemag.com/information
PRESENTED BY:
Sponsored by:
CONTENT SPECIALISTS/EDITORIAL
AMARA ROZGUS, Editor in Chief/Content Manager
630-571-4070 x2211, ARozgus@CFEMedia.com
AMANDA PELLICCIONE, Director of Research
630-571-4070 x2209, APelliccione@CFEMedia.com
MICHAEL SMITH, Creative Director
630-779-8910, MSmith@CFEmedia.com
Amara Rozgus,
KEMMIE TURPIN, Digital Media and Circulation Coordinator
630-571-4070 x2223, KTurpin@CFEMedia.com Editor in Chief
Sign up today! Go to
www.csemag.com/newsletters
Electrical, power challenges
82%
71%
58%
research
2015 FIRE AND LIFE SAFETY STUDY:
Transair® powered by
SCOUT™ Technology
input #5 at www.csemag.com/information
Is an international assignment
right for you?
Consider these 5 questions if you’d like to work abroad.
A
former colleague recently asked me for foreign assignments, consider the fol- simple act of going to a grocery store to find
for help in identifying all the things lowing: the makings for your favorite chili recipe or
she needed to consider in deciding finding a family dentist can be a huge chal-
whether to accept an international proj- 1. Is the assignment in a country lenge. Consider asking your employer to
ect assignment. The position was a 2-year where you are comfortable working? allow you to take your family to the country
assignment in Paris that would be a nice step Examine your personal and professional before the assignment starts to experience
up in responsibility and pay. And as a mid- values and make sure the local business first-hand what life will be like. Don’t just
level team leader, this friend was hoping the practices and culture align with them. limit your trip to house hunting and visiting
assignment would advance her career path to your kids’ school options; spend time with
a more senior level position upon her return. 2. Where is your internal sponsor/ other expatriate families to really under-
And well, it was Paris—she was definitely mentor, and who will keep you top-of-mind stand what life is like there.
dazzled by the idea that weekends could be in the home office while on this assign-
spent traveling and exposing her children to ment? You do not want to suffer from “out 5. Consider how your life will change
the European lifestyle. of sight, out of mind” while slaying drag- with the international experience. Living
In the right circumstances, foreign ons for your company in a foreign market. and working abroad will change you, and
assignments can turbocharge your career are you OK with that? Everyone I know
path. The professional challenges that 3. What is the duration of the assign- with international experience has returned
come with prolonged project assignments, ment, and what are your expectations to the U.S. with a different perspective that
business development roles, or operations upon completion? Make sure you and your makes their views and decision-making
can put all your skills to the test and help employer are clearly in agreement on your multidimensional, myself included. But
you develop some new ones. Cultural specific career expectations when the assign- if you fear change or are uncomfortable
differences, language barriers, limited ment is complete. This is not just alignment with allowing a different professional and
local resources—especially in develop- on career advancement but also continued cultural experience to affect you, then an
ing countries—will force you to use both employment. I have seen multiple cases international assignment is probably not a
your technical as well as your softer skills. where a colleague returns from an overseas wise choice.
Success in these types of assignments can assignment to find there is not a position for
cast you in a different leadership light with him or her at home. This can especially be Jane Sidebottom is the owner of AMK
your company’s senior management, espe- the case in heavy project-based environ- LLC, a management and marketing con-
cially when you are able to demonstrate ments where there is not room for another sulting firm that provides market develop-
flexibility, adaptability, and the ability to billable individual on existing projects. ment and growth expertise to small- and
lead an often diverse team to success—all medium-size firms. She has more than 20
skills needed for senior management posi- 4. Consider the impact on your family. years of management and leadership expe-
tions. And in your company or field, such Ask yourself if your family can survive and rience in both consulting engineering and
an assignment may even be a prerequisite thrive in the assigned country. And don’t Fortune 100 organizations. Sidebottom is
for a senior position. assume that because the assignment is in a graduate of the University of Maryland.
But before you run out to get your a cosmopolitan, westernized country that Read the longer version of this online at:
passport renewed and start volunteering your family or spouse will do well. The www.csemag.com/careersmart.
ESL's TripleSwitch™ is designed to service critical CSE: What are some common
operations facilities that have an automatic
transfer switch and dedicated generator. The problems you encounter when work-
TripleSwitch uses three interlocked circuit ing on building automation sys-
breakers to isolate standby generator circuits
during load bank testing. This unique design also tems?
provides a quick, safe method to connect to a
portable generator for redundant backup
Ellis: Given the proprietary nature of
Wat
c
Loa h Simp
most control manufacturers’ architectural
approach, despite the drive toward open
d l
eslp Bank ify Ge
wr.c Te ne
om/T sting rator
systems, defining architecture is still sub-
rip V
leSw ideo:
itch
Vid
eo
ject to customization by each vendor.
800.922.4188 - 951.739.7020 - eslpwr.com - info@eslpwr.com
SWITCH
TM
input #7 at www.csemag.com/information
Ortiz: Some of the challenging prob- Construction Code (IgCC), pose a docu- Ellis: Energy performance and other
lems we have encountered with our mentation problem that code officials sustainability practices have been
expansion/renovation project are dealing want resolved by new documentation involved in the majority of K-12 projects
with modifications of existing systems that increases production effort. in the last few years, and going forward
or integrating them with new ones. The are to be a part of all projects based on
older systems are sometimes obsolete CSE: Energy efficiency and the implementation of the new codes, in
and need to be integrated with the new sustainability are often the No. 1 particular the IgCC.
system. To avoid further issues, the old request from building owners during
system will be upgraded as well. new building design. What is your CSE: What changes in fans, vari-
experience in this area? able frequency drives, and other
CSE: What codes, standards, or related equipment have you experi-
guidelines do you use as a guide as Palasz: My experience is that to enced?
you work on these facilities? achieve excellence in energy efficiency
and sustainability, the designers need to Ellis: The biggest change in the design
Palasz: ASHRAE has great reference work with building owners and approach approach has been the introduction of de-
information available to engineers. Spe- it as a team effort. Prior to building coupling of ventilation from conditioning
cifically, for the work we do with Chicago occupancy, new buildings are being fine- by the use of DOAS, and the application
Public Schools (CPS), the City of Chica- tuned to balance system controls and of VRF systems. DOAS allows for sub-
go code governs these projects. Likewise, flow rates to provide comfort with the stantial energy savings in the avoidance of
CPS publishes an HVAC design guide designed operation. Adjusting systems conditioning unnecessary ventilation air,
and provides details, specifications, and often needs to occur for months and and VRF allows for low-energy transport
invaluable input to optimize design main- of heat during periods of concurrent heat-
“
tain consistency and reduce cost. ing and cooling. Of course, improvements
Major components for
Ellis: In addition to current codes, in design and cost of variable frequency
each school district typically has its own designing integration monitoring drives (VFDs) allows for more opportuni-
design guidelines, and frequently LEED systems and controls are effi- ties for implementing the energy-saving
for Schools is employed. ciency and energy conservation. advantages associated with variable flow,
Ortiz: The current school project both air and water, and development of
For example, motion sensors
complies with the 2008 New York City inexpensive pressure independent constant
(NYC) building code, and some aspects are being used to shut off lights air regulators allows for the mixing of con-
of the 2014 codes. Many of the standards when there are no occupants in stant and variable flow ventilation on the
and guidelines are based on the needs of rooms, and mechanical equip- same variable air volume (VAV) DOAS,
the school in coordination with the New which allows for ventilation savings with
ment is designed using heat
York City Dept. of Education. highly variable occupancy classrooms
wheels to save energy and mini- with fixed makeup spaces, such as labs.
CSE: Which code/standard proves
to be most challenging in such
facilities?
mize heat loss.
”
—Nestor Ortiz
Palasz: Over the past few years, I have
experienced a change in the trend of using
a roof-mounted return fan in an insulated
housing (similar to a rooftop unit) to wrap-
Palasz: Meeting the prerequisites for requires adjusting for the heating season ping a mixed flow fan. This results in a
LEED certification is typically the most as well as the cooling season. I believe lighter and more efficient design, which
challenging. Because projects are trend- that striving for improved efficiency helps to decrease initial costs by reduc-
ing toward tighter budgets and shorter should be an ongoing effort that should ing the structural reinforcement require-
design and construction schedules, the not stop once the building is occupied. ments. It also helps to improve the return
addition of a requirement to exceed the To do this, it is necessary to have ener- on investment with a very efficient fan
energy code while providing quiet ven- gy meters to establish a baseline and (up to 85% efficient). In regard to VFDs,
tilation presents a challenge. to track the system operation improve- they have become less expensive and more
Ellis: Given the typical approach of ments or denigration from year to year. widely used to provide system flexibility
decoupling ventilation from condition- This information is also critical in deter- and soft-start capability in addition to diag-
ing, acoustic performance is the biggest mining corrective actions for equipment nostic alarms.
design challenge. New codes, especially replacement and/or operational adjust- Read the longer version of this online at:
the IECC and the International Green ments to achieve cost savings. www.csemag.com/archives.
www.csemag.com/webcast
Codes & Standards
Piping arrangements
for fire pumps
NFPA 20 provides fire protection engineers with guidance on
design and installation of fire pumps and related components.
E
ffective fire pump installations require fire the suction pipe and associated devices need
protection engineers to consider numerous to be arranged in such a manner so as to mini-
components, and correctly apply a range mize the likelihood of turbulent and imbalanced
of design and installation standards. In addition water flow entering the pump. Such conditions
to addressing the more obvious components that decrease overall pump performance, can result in
comprise a fire pump installation—such as the a sudden system failure and can cause premature
fire pump, driver, controller, and pump room— wear of system components.
careful attention also needs to be given to the The size of the suction pipe is influenced NFPA 20
piping leading to, from, and around the pump mostly by the fire protection system’s hydraulic
and the equipment associated with that piping. demand as determined in accordance with the addresses the
While NFPA 20: Standard for the Installation appropriate system installation standards, such
of Stationary Pumps for Fire Protection serves as as NFPA 13 or NFPA 14, and the size of the fire arrangement
the principal standard addressing the sizing and pump selected. NFPA 24 provides guidance on of the suction
installation of the associated piping, the next edi- suction pipe sizes and generally states that for
tion being the 2016, other codes and standards any system, the pipe should be at least 6 in. in pipe and
such as NFPA 13, NFPA 14, NFPA 22, NFPA 24, nominal diameter. Smaller pipe sizes are permit-
NFPA 25, and NFPA 291, as well as the applicable ted provided hydraulic calculations verify that associated
building and fire codes, also need to be reviewed the pipe can supply the necessary system demand devices.
and correctly applied depending on the type of at the corresponding required pressure.
fire protection systems served by the fire pump. NFPA 22 provides specific guidance with
regard to suction piping connecting a water tank
Suction piping with the fire pump. For instance, if the suction
The piping connecting the water supply to the tank exceeds 100,000 gal, the size of the suction
fire pump is referred to as suction piping. It com- pipe must be at least 10 in. in diameter (nominal
prises all piping, valves, and fittings that feed dimensions). The smaller the pipe, the faster
water to the pump’s suction flange. The selection the water flow, and therefore more turbulent
and installation of such suction pipe material is flow will occur. Increasing the pipe size lowers
addressed by NFPA 24, which specifies the use the flow velocity and reduces the occurrence
of certain types of iron, steel, concrete, plastic, of turbulence.
and copper. In addition, NFPA 24 addresses how NFPA 20 includes more specific provi-
the pipe and fittings are to be joined together, sions about suction pipe where fire pumps are
depth of cover if the pipe is buried, protection installed, and specifies certain pipe sizes. The
of the pipe from freezing and other damaging philosophy is that suction pipe be sized so that
events, joint restraint, and acceptance testing when the pump is operating at its maximum flow
including flushing and hydrostatic tests. rate, which is 150% of its rated capacity or the
NFPA 20 addresses the arrangement of the maximum flow available from the water supply,
suction pipe and associated devices. Generally, the gauge pressure at the pump suction flange
www.csemag.com Consulting-Specifying Engineer • MARCH 2015 19
Codes & Standards
does not drop below -3 psi (-0.2 bar). where the requirements of NFPA 20 and present concern with water-based fire
Furthermore, the suction pipe is to be NFPA 22 do not take precedence. protection systems. The control valve is
sized such that with the pump operating permitted to be any type of valve listed
at 150% of its rated capacity, also referred Discharge piping for fire protection service, including a but-
to as pump’s overload point, the velocity NFPA 20 defines discharge pipe and terfly valve, because turbulence is not as
in that portion of the suction pipe located equipment as the pipe, valves, and fit- critical on the discharge side of the pump.
within 10 pipe diameters upstream of the tings that extend from the pump discharge A check valve is also to be installed
pump suction flange does not exceed 15 flange to the system side of the discharge on the discharge piping, between the fire
ft/sec (4.57 m/sec). Pipe flows in excess control valve. Practically, any pipe, valve pump and the discharge control valve.
of this velocity are more prone to turbu- or fitting downstream of the fire pump’s The discharge check valve traps the high-
lence. Where the suction pipe differs in discharge control valve is no longer con- er pressure in the fire protection system
size from the pump suction flange, reduc- sidered to be part of the discharge piping. after the fire pump operation stops. The
ers or increasers are permitted to be used Such pipe, valves, and fittings are con- check valve also prevents other sources
but must be of the eccentric tapered type sidered part of the supply piping for the of water flow into the system, such as
and installed in such a way so through a fire department con-
as to avoid air pockets. The size of the discharge pipe has an nection, from flowing back into
In addition to specifying the fire pump.
suction pipe sizes based on the effect on friction loss, but that effect NFPA 20 requires that the
rated capacity of the fire pump, can be accounted for though hydraulic pressure rating of the dis-
NFPA 20 also addresses other charge components, includ-
system attachments that could analysis. As with suction pipe sizes, ing all piping, fittings, and
cause turbulent or imbalanced valves, be adequate for the
flow into the fire pump. Where NFPA 20 specifies minimum discharge maximum total discharge
backflow preventers or check pipe diameters based on the capacity pressure with the pump oper-
valves are being considered, ating at churn conditions at
they are to be located a mini- rating of the fire pump. the pump’s rated speed.
mum of 10 pipe diameters from
the pump suction flange. If the backflow fire protection system being served by the Pump bypass piping
device incorporates butterfly valves, the fire pump. In the case of a sprinkler sys- A bypass is an arrangement of piping
device is to be installed at least 50-ft tem riser, the requirements of NFPA 13 around the fire pump that can be used to
from the pump’s suction flange. In fact, would apply from the point of the pump supply water to the fire protection system
the 50-ft criterion applies to any valve, discharge control valve. should the pump fail or be taken out of
other than an outside screw and yoke gate NFPA 20 addresses the size of the dis- service. Such bypass piping is to be sized
valve, installed in the suction pipe. charge pipe and associated fittings, and as required for the discharge pipe.
Elbows and tees in the suction pipe requires all of the aboveground discharge Bypass piping is required where the
also warrant special consideration. Such piping to be composed of steel. In certain water supply is considered to be of “mate-
devices are to be located and positioned cases the discharge pipe is permitted to be rial value” to the fire protection system
with respect to the orientation of their smaller in diameter than the suction pipe without the use of the fire pump. While
centerline plane. Where the centerline because the water flow velocity is not of this is a rather subjective requirement,
plane is parallel to a horizontal split-case the same concern on the discharge side bypass lines are usually required where
fire pump shaft, the elbow or tee needs of the pump. The size of the discharge the water supply is provided by a pressur-
to be located a distance at least 10 pipe pipe has an effect on friction loss, but ized fire service main such as municipal
diameters from the suction flange of the that effect can be accounted for though waterworks or private fire service main.
fire pump. If the centerline plane is per- hydraulic analysis. As with suction pipe Where the water supply for the building
pendicular to the horizontal split-case sizes, NFPA 20 specifies minimum dis- is from a private stand-alone fixed sup-
pump shaft, no limitations are placed on charge pipe diameters based on the capac- ply such as the suction tank, a minimum
the location of the elbow or tee. ity rating of the fire pump. pressure due to the elevation head of the
It is important to recognize that NFPA A control valve is to be installed on the stored water in the tank is available but is
20 only addresses the size of the suction discharge piping so that the pump can be not usually considered to be of material
pipe within 10 pipe diameters of the pump isolated for service and repairs. Additional value. However, this should be verified
suction flange, while NFPA 22 addresses valves are discouraged to minimize the through hydraulic analysis, and needs to
the size of the pipe connected to the tank. possibility that a valve will be inadver- be confirmed with the respective authori-
The provisions of NFPA 24 would apply tently shut and not reopened—an ever- ties having jurisdiction.
Go to www.csemag.com/digitaledition today
W
hen we think of the Lean design and construction is a process
Learning best way to deliver that focuses on these areas to deliver a
objectives a product, some of better product.
Understand the key aspects us might think of
of integrated project delivery the UPS slogan, Lean: Is this IPD?
(IPD) as it relates to building “We Love Logistics.” But how often do Often, we use the concepts of inte-
construction. you think about the logistics involved grated project delivery (IPD) and Lean
Learn how incorporating with delivering building projects more interchangeably. While they are con-
Lean can eliminate waste in
effectively? cepts that partner well together, they
the engineering process.
Many of us think about the manufactur- are not the same. IPD is a contracting
Know how to combine
IPD and Lean processes to
ing industry as a way to streamline pro- method. This sets the rules for a project.
streamline building engineer- duction. The Toyota Production System Lean, on the other hand, is a mind-set.
ing. focuses on the elimination of waste. It is It’s the mind-set you adopt on a project
not important how many cars are produced, or in your daily work that focuses on the
but rather that the best car is produced. elimination of waste.
Another place to look is in the kitchen. IPD is a building trend in design and
Chefs learn mise-en-place during train- construction communities. Many owners
ing at places like the Culinary Institute have heard about IPD and are requiring
of America. There, they learn to gather it for their projects. The American Insti-
and arrange the ingredients to help them tute of Architects (AIA) has developed
focus on the meal preparation. In some a multi-party agreement that can be
cases, chefs will spend 6 hours prepping used to contractually join together sev-
for 3 hours of meal production. eral entities, rather than the traditional
When you look at the engineering owner-architect agreement. The AIA has
industry, it seems the focus has turned also published a guide on IPD that can
away from these practices and is solely be referenced for additional information.
on the speed of production, not the qual- Lean practices can be used on a proj-
ity of the work. Imagine if the schematic ect and are even valuable as a way to
phase of the project was twice as long as better manage your personal workload.
the production phase. A trend is building The Lean Construction Institute (LCI)
to reorient our processes and use other has formed Communities of Practice
industries as a guide to produce better around the country that bring together
building design and construction proj- Lean practitioners to develop skills and
ects with fewer errors and less waste— share knowledge within their business
and that deliver better value to the owner. community.
provides the
latest knowledge
on commercial
and institutional facility construction
and management.
Visit www.csemag.com
delivers a wide
array of strategies
and solutions to
help control system designers create a
more efficient process.
Visit www.controleng.com
delivers plant-floor
knowledge and
expertise to help
manufacturers operate smarter, safer
and more efficiently.
Visit www.plantengineering.com
LCCA for
HVAC systems
Lifecycle cost analysis (LCCA) is a tool used to determine the most
cost-effective option among HVAC system alternatives.
BY DAVID J. MACKAY, BEMP, CPMP, LEED AP, Kohler Ronan, New York City
P
ractically speaking, there ultimately disposing of a project are
Learning are multiple building design considered to be potentially important
objectives options that can meet program- to that decision. LCCA is particularly
Understand basic lifecycle matic needs and achieve accept- suitable for the evaluation of build-
cost analysis (LCCA) concepts able levels of performance. ing design alternatives that satisfy a
and best practices. From a purely financial perspective, required level of building performance
Learn to incorporate LCCA the only appropriate design alternative (including occupant comfort, safety,
into an HVAC system selec- is the solution that satisfies the owner’s adherence to building codes and engi-
tion process.
project requirements for the lowest total neering standards, and system reliabil-
Identify tools that simplify cost of ownership. Lifecycle cost analy- ity), but may have different operating,
LCCA calculation and results
documentation.
sis (LCCA) is a powerful tool used to maintenance, and repair (OM&R) costs,
determine the most cost-effective option and potentially different useful lives.
among competing alternatives. Although Project-related costs that occur at dif-
LCCA has been ferent points in time cannot be directly
used for decades combined for meaningful economic
to reliably identify analysis because the dollars spent at
cost-optimal design different times have different values to
solutions, many the investor. LCCA provides a rational
building owners means to weigh the value of first costs
and architecture and versus future (e.g., operating) costs (see
engineering profes- Equation 1).
sionals still rely on
simple payback to Adjusting to present value
make project invest- Most individuals intuitively recog-
ment decisions. nize that a dollar today does not have
LCCA is an eco- the same value as a dollar in the distant
nomic method of future. This concept, referred to as the
project evaluation time value of money, results from two
Equation 1: This simplified lifecycle cost formula is adapted in which all costs considerations: 1) general inflation,
from the NIST Handbook 135 (HB 135), “Lifecycle Costing arising from own- which is the erosion of future purchas-
Manual for the Federal Energy Management Program.” All i n g , o perating, ing power; and 2) opportunity cost,
graphics courtesy: Kohler Ronan LLC maintaining, and which for existing capital is the cost of
If the client decided to take advantage of the DES, over a Incremental pump power 19 W/gpm
30-year period the client would avoid approximately $1 million Lifecycle costing
worth of initial construction, future equipment maintenance, Base year 2017
and replacement costs. However, over a 30-year period, energy Service year 2017
costs through the DES would likely total $8.6 million in net Study length 30 years
present value Discount rate 3%
Although installation of an on-site central plant would Discounting convention Year-end
increase initial investment and future capital costs by approxi- Discount and escalation rate types Real
mately $1 million, compared to the DES alternative the central Treatment of inflation Constant dollar
plant option would save the client approximately $2.4 million
30-year incremental cost data
in energy expenditures over 30 years (not discounted)
Based on total cost of ownership during the 30-year Capital cost $775,000
analysis period, the central plant option is the most economi- Maintenance cost $232,500
cally viable alternative. Initial investment costs are likely to be Replacement cost $540,000
recovered within a 9-year period (discounted payback period); Residual equipment value ($396,540)
over a 30-year period the central plant would likely provide Total investment cost $1,150,960
the client with $1.4 million net savings (NS) compared to the
30-year annualized lifecycle costs
DES alternative.
Initial capital cost $39,543
Energy cost $312,633
Maintenance cost $7,750
Capital replacements $13,651
Residual value ($8,337)
Annualized lifecycle cost $365,242
Compared to DES option
30-year net savings $1,421,861
Savings-to-investment ratio 2.62
Adjusted internal rate of return 6.36%
Simple payback period (years) 8
Discounted payback period (years) 9
Figure 3: The design team agreed that the invest- Table 1: The LCCA is calculated for both building a new central plant
ment decision of whether to build an on-site plant and for using the district energy system option. The central plant
or use the local energy options should be deter- option turned out to be the most economically viable alternative.
mined using LCCA.
www.csemag.com
Cover story
Integration:
BIM design
Building information modeling (BIM) is used
frequently when working across multiple disciplines, including mechanical,
electrical, plumbing, and fire protection engineering, and also with other
stakeholders such as architects and contractors.
BY ED PAUL, Arup, Los Angeles
I
s it possible for BIM to be done cor- tectural models are detailed and dimen-
Learning rectly for mechanical, electrical, sioned to a high level of accuracy, and it is
objectives plumbing, and fire protection (MEP/ expected that MEP/FP models will match
Understand the require- FP) design? Numerous factors come that accuracy, an attitude also shared by
ments for a BIM model. into play when integrating BIM into the client/owner. This sets the precedence
Learn the key components the MEP/FP engineering and design pro- in architectural and structural models,
of a BIM execution plan. cess. It is up to the design team to take the which are required to provide dimensional
Understand the nuances of best from each variation of modeling and control for the contractor as an element
smart data, content, and other apply the appropriate elements to create of design. MEP/FP design work rarely, if
details within a model.
a successful process. ever, has the same level of detailing. How-
Expectations are never the same on any ever, as MEP modeling software became
engineering project. Everyone has various mature enough to be used on major proj-
ideas of how BIM will be incorporated, ects, expectations were already set for
and quite a few of them are unrealistic. similarly detailed MEP/FP models.
The MEP/FP engineering team needs Contractors have also become accus-
to set appropriate expectations with the tomed to using architectural/structural
architect and owner at the onset of the models directly to create their 3-D
project. Before defining these expecta- coordination models; increasingly, they
tions, we need to understand why diver- expect the MEP/FP models to have the
gent expectations exist. same detail and accuracy. For example,
When we say or hear BIM, it is often a general contractor was completely sur-
interpreted to mean 3-D modeling using prised by my “negative” response when
Autodesk Revit. While other platforms are he asked about modeling all the conduit
available, most architects use Revit, which runs in the electrical model. MEP/FP
sets the expectation that MEP/FP models design models are created primarily to
will also use Revit. The main concern is show design intent. While support mod-
related to the detail and accuracy that an eling and constructability are secondary
architect or owner might expect because drivers, they are still important, as the
he or she doesn’t completely understand subcontractors make a substantial invest-
the MEP/FP software or process. Archi- ment in the trade coordination exercises
A
overall equipment-specific groups like large private university in Southern California recently completed a technologically complex retrofit
fans, pumps, chillers, transformers, and of an existing 1950s building for its mechanical, electrical, plumbing, and fire protection (MEP/
more, that can share the same subgroup FP) system design. This owner is quite sophisticated in rolling over engineering design data generated
parameters as the base parameters will be by BIM Autodesk Revit models to be used for facility management purposes with minimal modifications
consistent. Certain equipment objects like at project closeout.
air handling units or fan coil units can have Given the large effort to compile data after the fact, this owner requires the design team to set up
100 or more parameter fields. Accurately families to accommodate the collection of design and construction data during the process within the
managing this type of content metadata is BIM model. To facilitate this effort, the owner hosted BIM collaboration meetings to share goals and
better handled by add-on utilities than the requested the design teams to create a plan and process to capture the necessary data as part of the
default functionality offered by the main design process. The design team worked together with the client and the contractor to develop a joint BIM
software package. execution plan (JBEP) that will deliver on the client’s request. The JBEP includes such items as explicitly
Special attention is needed to decide defined families with prescribed sets of university-required parameters, coordination review processes
between “type based” and “instance based” by owner-contracted third-party BIM reviewers, and file exchange workflows.
parameters. Consider two scenarios: Because the design team in collaboration with the construction team reached an early agreement on
Scenario 1: Five pumps in a building the JBEP, the MEP engineers were able to start creating Revit families that met the necessary criteria
and they all have the same specifications, and were able to avoid rework. A predetermined scheduled was added to JBEP for model exchange
three are in the mechanical room level one and additional workshops for model coordination with the contractor. Data from models was exported
and two are in the basement. This can be at milestones and verified against facility management checklists to ensure that model objects carried
scheduled three different ways. all pertinent engineering data that a facility engineer can use as needed in the future. Proper and early
Scenario 2: Five pumps in a build- planning can address the issues and challenges that MEP/FP engineers face when asked to integrate
ing and each is a different manufacturer BIM into design and use model-generated data for facility management.
model. Three are in the mechanical room
M
ission critical facilities and laboratory equipment; and monitor-
Learning support a wide vari- ing , communications, and surveillance
objectives ety of vital operations systems, will have high power require-
Understand the various where facility failure ments that translate into heat gain and
ways to measure energy use will result in compli- energy use.
in mission critical facilities. cations that range from serious disrup- Putting these hallmarks together,
Learn about the codes and tions to business operations, to circum- mission critical facilities need to run
standards that dictate energy stances that can jeopardize life safety continuously, providing less efficient
performance.
of the general public. To minimize or power and cooling to technical equip-
Learn about the codes,
eliminate the chance of facility system ment that has very high electrical
standards, and organizations
that govern energy perfor- failure, mission critical facilities have requirements, all without failure or
mance. three hallmarks that make them dif- impacts from standard maintenance
ferent from other type of commercial procedures. This is why energy use (and
buildings: ways to reduce it) in mission critical
1. The facility must support opera- facilities has been, and will continue
tions that run continuously without to be, of great concern. This is true
shutdowns due to equipment failure or whether the mission critical facility is a
maintenance. Seasonal or population laboratory, hospital, data center, police/
changes within the facility have a small fire station, or another type of essential
impact on the energy use profile; gen- operation.
erally, the facility is internally loaded And due to constant advances in
with heavy electrical consumption. the design of technical equipment, the
2. Redundant power and cooling strategies and tactics used for reduc-
systems are required to support the ing facility energy consumption need
24/7/365 operation. Depending on the to anticipate how future changes will
level of redundancy, there will be addi- impact building design, codes, stan-
tional efficiency losses in the power and dards, and other guidelines. Fortu-
cooling systems brought on by running nately, the technical equipment will
the equipment at small percentages of generally become more energy-efficient
the capacity. over time with improvements in design.
3. The technical equipment used in This can reduce facility energy use in
the facility, such as computers; medical two ways: the equipment will use less
energy, and the energy of the power and For data centers and the broader energy efficiency initiatives is the 1977
cooling systems will also decrease. range of commercial buildings, there U.S. National Energy Plan. This was
Data centers are one segment of the are myriad programs, guidelines, and developed as a blueprint identifying
mission critical facility industry that codes intended to keep energy use as energy efficiency as a priority because
arguably see the highest rate of change low as possible. Publications from “conservation is the quickest, cheapest,
in how the facilities are designed, pri- ASHRAE, Lawrence Berkeley Nation- most practical source of energy.” This
marily based on the requirements of al Laboratory, U.S. Green Building plan became the basis for many other
technical equipment, servers, storage Council, and the U.S. Environmental building energy use reduction programs
devices, and networking gear. Data Protection Agency are good examples that would typically start out at the fed-
centers will have the highest concen- of technical but practical resources aid- eral level and eventually trickle down
tration of technical equipment on a sq ing in data center strategy. to state and local government.
ft or percentage of total power demand But how did all of these come about? During this time, one of the most
as compared to other mission critical To understand the path forward, it is widely used building efficiency stan-
facilities. A change in the specifica- equally important to know how we dards was published for the first time:
tions or operating conditions of the got here. Similar to the rapid evolu- ASHRAE Standard 90-1975: Energy
computers in a data center facility will tion of power and cooling systems in Conservation in New Building Design.
have a ripple effect that runs through data centers, many of thedocuments Because no comprehensive national
all aspects of the power and cooling released by these groups were devel- standard existed at the time, this was
systems (see Figure 1). Moreover, IT oped in response by changes and new the first opportunity for many architects
equipment manufacturers are develop- thinking in the data center design and and engineers to objectively calculate
ing next generation technology that can construction industry. the energy costs of their designs and
significantly reduce overall energy use to increase energy efficiency. Since its
and environmental impact of data cen- Energy-efficiency programs initial release, the standard has been
ters. This is a good thing, but with it for buildings renamed ASHRAE Standard 90.1:
brings new design challenges that need In the United States, one of the first Energy Standard for Buildings Except
to be addressed in codes, standards, and programs developed by the federal gov- Low-Rise Residential Buildings and
guidelines. ernment that spawned several broader has been put on a 3-year maintenance
stay
The bottom line: In the next few years the data center design
and construction industry will have to continue to be an active
member in the evolution of IT equipment and will need to
informed
come up with creative design solutions for revising codes and
standards, such as ASHRAE 90.1, making sure there is a clear
understanding of the ramifications of the IT equipment to the
data center facility. As developments in computing technology
research begin to manifest into commercially available prod-
ucts, it is likely that the most advanced computing platforms
Stay current won’t immediately replace standard servers; a specific type
of workload, such as very big data or real-time analytics will
with technology and trends require a new type of computing architecture. And even though
this technology is still in the development phase, it gives us
in electrical, mechanical, a good indication that a breakthrough in server technology is
coming in the near future. And this technology could rewrite
lighting, and fire/life safety. today’s standards for data center energy efficiency.
SAFETY
PLUGS
PROTECT FROM ARC FLASH
OFF BUTTON
Safely breaks load
UL Switch-Rated
Earn continuing
education credits
by attending
Rated up
our 1-hour-long to 200A
webcasts. 600V
Stay current
with technology
and trends in
electrical, mechanical,
lighting, and Update your subscription,
fire/life safety. and get our digital edition,
on a more interactive and
user-friendly platform, 7 to 37 contacts
in your email in-box. 4mA to 150A per contact
Easy-to-wire contact terminals
To subscribe, visit
Update now at:
meltric.com
www.csemag.com/subscribe www.csemag.com 800.433.7642
Input #103 at www.csemag.com/information Input #104 at www.csemag.com/information Input #105 at www.csemag.com/information
XXXDTFNBHDPN $POTVMUJOH4QFDJGZJOH&OHJOFFSt.0/5)
$POTVMUJOH4QFDJGZJOH&OHJOFFSt."3$) 39
Selecting fire pumps
The key for fire protection engineers is to understand the requirements of
both NFPA 20 and NFPA 70 to properly choose and configure a fire pump
so that the fire protection systems can serve their intended use.
BY ALLYN J. VAUGHN, PE, FSFPE, and RICK REYBURN, PE, JBA Consulting Engineers Inc., Las Vegas
P
ower for fire pumps is critical in the which includes frequent run tests. Some-
Learning design of a properly operating fire times it is just too difficult to locate a die-
objectives protection system. Without power, sel-driven pump inside a building due to
Understand the two pri- the building loses the ability to have an these considerations, especially when the
mary types of fire pumps: effective fire suppression system. The design requires pumps be installed within
electric and diesel. building’s fire/life safety system also can- a tower due to pressure zone requirements.
Learn about the codes and not control or extinguish a fire, thereby Diesel-driven pumps are a good choice
standards and define specifi- negating the benefits of the fire protection when the pump is located at the base of
cation of these systems.
system. Therefore, careful consideration the building near the exterior wall or in a
Determine how to select
in the selection of pumps and power sup- separate pump house to accommodate the
the best pump to meet the
intended usage. plies is critical to the operation of the fire refueling operations and the ventilation of
protection systems. combustion exhaust. When installed inside
As fire protection engineers, our team a building or midway up a high-rise tower,
often selects fire pumps for various they are difficult to design and install.
designs. Due to the size, magnitude, and An electric-driven pump does not
building height of the projects, municipal require a combustion-driven engine to start
water supplies often are not capable of to operate the pump. As long as power is
providing the required pressures to meet available to the pump, when the pressure
fire protection system (automatic sprin- drops in the system, the electric-driven
klers and standpipes) demand. Therefore, pump will start. The key is to provide
fire pumps are specified to boost pres- a reliable source of power to the pump,
sures that are needed for these systems under both normal and emergency condi-
to protect the building and its occupants. tions. For an electric-driven pump, power
This team’s first choice in selecting is the key to the reliability of the pump
fire pumps is to use an electric-driven and therefore the fire protection system.
pump. An electric-driven pump is easier Electric power is easier to run through the
to design, is easier to maintain on a regu- building, especially within high-rise tow-
lar basis, and does not require external ers where multiple pressure zone pumps
fuel to operate the pump. It lends itself are located. Getting the power there is
to a cleaner and more efficient system. easier than getting diesel fuel.
Diesel-driven pumps are very reliable
and have their place in the design and Codes and standards
installation of fire protection systems. Codes and standards governing fire
However, they require fuel storage tanks pumps recognize the importance power
of combustible liquids to be stored in or plays in the operation of these electric-
near the pump room, and require ventila- driven fire pumps. NFPA develops many
tion of combustion products and a means standards and guides on how to design
to replenish fuel used during operation, and install fire protection systems. NFPA
20: The Standard for the Installation of A feeder connection that is part of a Power requirements
Stationary Pumps for Fire Protection out- multi-building campus-style arrange- One of the things that often gets over-
lines the requirements for the design and ment meeting certain conditions looked when dealing with emergency
installation of fire pumps. When a fire A dedicated transformer connection power to fire pumps is the power require-
pump is required due to system demands, directly from the service meeting ments for the controller and pump from
often NFPA 20 is the referenced standard. Article 695 of NFPA 70: National the backup source. The backup source is
NFPA 20 provides specific details for Electrical Code. typically an on-site generator. NFPA 20
the use of both diesel and electric-driv- requires the pump to run at up to a locked
en pumps, including the power supply NFPA 20 requires an alternate source rotor current, which can be up to six times
requirements for electric pumps. of power when the height of the build- the full load current. If the generator is
Chapter 9 of the 2013 edition of NFPA ing is beyond the pumping capacity of sized to handle only the full load, there
20 provides specific requirements for fire department apparatus or where the is not sufficient power available to drive
electric drives for fire pumps. It outlines normal source is not reliable. If a backup the pump to meet NFPA 20 requirements.
the requirements for both normal and diesel-driven or steam-driven pump is Because most pumps are of a significant
alternate power. It is clear that the nor- provided, an alternate source of power size (150 to 250 hp), this oversight can be
mal power source be continually avail- is not required. Also, many of the model drastic in the overall performance of the
able and arranged in one of five methods. building and fire codes require an alter- system. The generator needs to be sized
These include: nate or secondary source of power be to handle the required start-up load, not
A utility service connection dedi- provided for all pumps serving systems just the running load.
cated to the pump in high-rise buildings. Per NFPA, this Most electric-driven pumps that require
An on-site power production facility source of power is considered emergency backup power will have transfer switches
dedicated to the fire pump and should be available within 10 sec- specified that are integral with the control-
A dedicated feeder connection onds of loss of normal power. The emer- ler itself. The transfer switch is a compo-
derived directly from the dedicated gency source of power is required to be nent of the controller, and the two act in
fire pump service available for at least 8 hours. unison to operate the pump under both nor-
Figure 2: This shows one possible method of providing power for both pumps.
Figure 3: In this case, multiple fire pumps connected to three parallel generators/switchgear in a large complex facility are shown.
Figure 4: A vertical fire pump and its associated controllers serve a high-rise complex.
fire pumps as a prioritized breaker from (1) when routing through the building, dictate the type of pump to use and the
the paralleling system for normal power either 2 in. concrete encasement or a quantity needed. When using electric-
with emergency power coming from the 2-hour rated enclosure because 2-hour driven pumps, consideration should be
emergency distribution system (priority listed electrical circuit protective sys- given to how the primary and emergen-
1 system). tems are not available. The downstream cy power supplies are to be arranged
feeders at standard voltages (i.e., 208 or and distributed. NFPA standards pro-
Details to note 480 V) would be allowed to comply with vide various options to the designer on
When sizing the transformers on the all three options. how to configure the power supplies to
NEC 700 emergency system, care must There are some medium-voltage ensure the power feeding fire pumps is
be given by the engineer to allow for all designs that implement 480 V genera- reliable and is protected. The key for
loads plus the locked rotor current of the tors, and step-up transformers are used to all is to understand the requirements of
fire pump. Some drawbacks to increasing parallel with a 12,470 V system and then both NFPA 20 and NFPA 70 to properly
the size of the emergency system trans- step-down transformers used to serve choose and configure a fire pump so that
former are the fault currents increase on fire pump loads. Inrush current must be the fire protection systems can serve
the secondary side, which must be con- applied for both the step-up and the step- their intended use.
sidered for equipment ratings as well as down transformers to meet the minimum
arc flash considerations. requirements of 15% voltage drop per Allyn J. Vaughn is president at JBA
All three applications will require NEC 695.7(A). Consulting Engineers. He has more
compliance for the normal power sup- Single buildings with medium-voltage than 30 years providing fire protec-
ply conductors to be routed outside distribution systems have challenges to tion system design and code consult-
of the building or routed through the comply with the NEC and will require ing services, including design and
building in a 2 in. concrete envelope discussions with the authority hav- commissioning of fire protection sys-
installed per NEC 230.6(1) and (2) as ing jurisdiction (AHJ) to apply custom tem for large complex facilities. Rick
per NEC 695.6(A)(1). The standby gen- designs and applications of equal or bet- Reyburn is director of electrical engi-
erator supply conductors are considered ter than the code defined requirements. neering and has more than 30 years of
feeders and must meet the requirements There are many options to providing experience in development and design
of NEC 695.6(A)(2), which give three fire pumps for buildings and facilities. of electrical systems and is a licensed
options. For the medium-voltage feeders The size and configuration of the facil- professional engineer in more than 30
there are two options per NEC 695.6(A) ity as well as the intended use will often states.
Brian Gross, Marketing Consultant Bilco Company ................................ 23 ....................10 ..............800-366-6530................. www.bilco-colt.com ................................
630-571-4070 x2217, BGross@CFEMedia.com
Michael Smith, Creative Director BITZER US, Inc. ................................ 38 ....................14 ..............770-503-9226................. www.bitzerus.com ..................................
630-779-8910, MSmith@CFEMedia.com
CaptiveAire, Inc............................... 30 ....................12 ..............800-334-9256................. www.captiveaire.com .............................
Paul Brouch, Director of Operations
630-571-4070 x2208, PBrouch@CFEMedia.com Caterpillar, Electric
Rick Ellis, Audience Management Director Power Division ................................ 1 ......................2 ........................................................ www.cat.com/globalrelay ......................
303-246-1250, REllis@CFEMedia.com
CSE E-newsletters ........................... 8 .........................................630-571-4070................. www.csemag.com/newsletters .............
Michael Rotz, Print Production Manager
717-766-0211 x4207, Fax 717-506-7238 CSE HVAC and BAS Research ........ 10 .......................................630-571-4070................. www.csemag.com/2014HVACBAS .........
mike.rotz@frycomm.com
Maria Bartell, List Rental Account Director CSE Webcasts .................................. 18 .......................................630-571-4070................. www.csemag.com/webcast
Infogroup Targeting Solutions
847-378-2275, maria.bartell@infogroup.com EMERSON Network Power ............ C-4...................16 ...................................................... EmersonNetworkPower.com/WhatsCool .......
Claude Marada, List Rental Manager
402-836-6274, claude.marada@infogroup.com ESL Power Systems......................... 16 ....................7 ................800-922-4188................. www.eslpwr.com.....................................
Letters to the Editor Fujitsu General America, Inc .......... 2 ......................3 ................973-575-0380................. www.airstagevrf.com .............................
Please e-mail your letters to
ARozgus@CFEMedia.com Janus Fire Systems .......................... 22 ....................8 ................219-663-1600................. www.janusfiresystems.com ...................
Letters should include name, company, and
address, and may be edited for space and clarity. MEP GIANTS 2015
Information Sponsored by Eaton ....................... 6 .........................................630-571-4070................. www.csemag.com/giants .......................
For a Media Kit or Editorial Calendar,
e-mail Trudy Kelly at: TKelly@CFEMedia.com. Mitsubishi Electric
Cooling & Heating .......................... 14, 15 ..............6 ................800-433-4822................. www.mitsubishipro.com ........................
REPRINTS MTU Onsite Energy ........................ 16A-16L .............................507-625-7973................. www.mtuonsiteenergy.com...................
For custom reprints or electronic usage, contact:
Nick Iademarco, Wright’s Media
877-652-5295 x102, niademarco@wrightsmedia.com
Onicon Incorporated ...................... 31 ....................13 ..............727-447-6140................. www.onicon.com ....................................
West, TX, OK
Tom Corcoran TCorcoran@CFEMedia.com
1111 W. 22nd St., Suite 250 215-275-6420 Need More Info? FAX this page to: 630-214-4504
Oak Brook, IL 60523 Fax 484-631-0598
or mail to Consulting-Specifying Engineer magazine, 1111 W. 22nd Street, Suite 250, Oak Brook, IL 60523
Northeast
Richard A. Groth Jr. RGroth@CFEMedia.com Name Title
12 Pine Street 774-277-7266
Franklin, MA 02038 Fax 508-590-0432
Company Address
International
Stuart Smith stuart.smith@ssm.co.uk City State Zip
SSM Global Media Ltd. +44 208 464 5577
Fax +44 208 464 5588
Phone Fax e-mail
Consulting-Specifying Engineer does not assume and hereby disclaims any liability to any person for any loss or damage caused by errors
or omissions in the Advertiser contacts regardless of whether such errors result from negligence, accident, or any other cause whatsoever.
T
he Republican takeover of Con- as more mechanical engineers figure out U.S. cumulatively. As of mid-2014 only
gress in November means that how to design low energy use intensity about 0.5% of the 5 million U.S. non-
we’re unlikely to see new fed- (EUI, or thousands of Btus per sq ft per residential buildings had been certified
eral legislation affecting or mandating year) buildings on conventional budgets. to either Green Globes or LEED, indi-
green building. That is good news for Green buildings, especially larger cating that there are significant market
those who believe in free choice in the commercial and institutional building headwinds to certification at current
marketplace for green building certifi- portfolios, will increasingly be man- costs. As the new construction market
cation. However, the November 2014 aged by cloud-based big data plat- continues to grow, private building
release of the fifth report of the UN forms. This trend is reflected by a large owners may begin to see the increased
Intergovernmental Panel on Climate number of new entrants and new prod- value of having a third-party rating
Change, with its ever more dire predic- ucts in fields of building automation, assessment on their buildings, since
tions of massive disruption from global facility management, wireless controls, it doubles as a quality assurance pro-
warming, will likely move some states and building services information man- gram for the increasingly busy building
and many cities to start taking matters agement during the past 3 years. owner and as a differentiator to the pub-
into their own hands, particularly with For green building certification, lic marketplace and to investors. But
regard to incentives, ordinances, and the federal government (General Ser- this must be done at significantly lower
rules around the subject of increasing vices Administration, or GSA; Dept. of overall costs than at present.
energy efficiency in buildings. Defense, or DOD; and Dept. of Energy, Green building performance disclo-
In the past 3 years, concerns over or DOE) have put two building certifi- sure also continues as a major trend.
climate change and new financing cations on an equal footing for govern- In the U.S., this trend is highlighted by
mechanisms have led to continued ment projects, Green Globes and U.S. disclosure requirements enacted in 2013
growth in energy-efficiency green Green Building Council’s LEED. This by more than 30 major cities around the
building retrofits. This trend appears to trend was reinforced by DOE’s new country, and laws that require commer-
be strongest in corporate and commer- rule for federal projects, announced in cial building owners to disclose actual
cial real estate, along with municipal October 2014. The rule said, in summa- green building performance to all new
buildings, universities, schools, and ry, if any government agency is going tenants and buyers and, in some places,
hospitals (the MUSH market), where to use a green building rating system, it to the public. This trend will spread
energy service companies (ESCOs) are has to be one of the designated two or rapidly, as it is the easiest way to secure
looking for sustainable investments. any other that has an open consensus and monitor reductions in carbon emis-
Along with the growth of the energy process, and these systems must provide sions from commercial and governmen-
retrofit market, net-zero energy buildings ongoing monitoring and reporting of tal buildings.
are seeing increasing market interest. energy and water use. Offering agencies
Developers of commercial and even resi- free choice among competing rating Jerry Yudelson is president of the
dential buildings have begun to show- systems gives engineers and building Green Building Initiative, a green
case net-zero energy designs to gain owners greater control. building nonprofit. A professional
competitive advantage. This trend has Green building is experiencing rapid engineer, Yudelson is the author of 13
been developing for about 5 years and expansion globally, but certification books on green building, water conser-
now seems ready for takeoff, especially commitment has slowed down in the vation, and sustainable development.
EXPECT LESS
LESS HARMONICS
LESS ENERGY DEMAND
LESS FOOTPRINT
THAT’S THE
CRITICAL DIFFERENCE.
Emerson. Consider it Solved., Emerson Network Power and the Emerson Network Power logo are trademarks and service marks of Emerson Electric Co. ©2015 Emerson Electric Co. All rights reserved.