Curso : Programación de obras

Id EDT Nombre de tarea Duración Comienzo Fin Predecesoras 19 oct '14 26 oct '14 02 nov '14 09 nov '14 16 nov '14 23 nov '14 30 nov '14 07 dic '14 14 dic '14 21 dic '14 28 dic '14 04 ene '15 11 ene '15 18 ene '15 25 ene '15 01 feb '15 08 feb '15 15 feb '15 22 feb '15 01 mar '15 08 mar '15 15 mar '15 22 mar '15 29 mar '15 05 abr '15 12 abr '15 19 abr '15 26 abr '15 03 may '15 10 may '15 17 may '15 24 may '15 31 may '15 07 jun '15 14 jun '15 21 jun '15 28 jun '15 05 jul '15 12 jul '15 19 jul '15 26 jul '15
J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X
1 1 INICIO 0 días lun 20/10/14 lun 20/10/14 20/10

2 01 AULAS + SUM 199 días lun 20/10/14jue 23/07/15

3 01.01 OBRAS PROVISIONALES 13 días lun 20/10/14mié 05/11/14

4 01.01.01 OBRAS PRELIMINARES 3 días lun 20/10/14mié 22/10/14

5 01.01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m 1 día lun 20/10/14 mar 21/10/141 20/10 21/10

6 01.01.01.02 ENERGIA ELECTRICA 1 día lun 20/10/14 lun 20/10/14 1 20/10 20/10

7 01.01.01.03 CASETA ADICIONAL P/GUARDIANIA Y/O DEPOSITO 3 días lun 20/10/14 mié 22/10/141 20/10 22/10

8 01.01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 1 día lun 20/10/14 lun 20/10/14 1 20/10 20/10

9 01.01.01.05 FLETE (TRANSPORTE DE MATERIALES Y AGREGADO) 1 día lun 20/10/14 lun 20/10/14 1 20/10 20/10

10 01.01.02 LIMPIEZA DE TERRENO 8 días jue 23/10/14lun 03/11/14

11 01.01.02.01 LIMPIEZA DE TERRENO MANUAL 8 días jue 23/10/14 lun 03/11/14 7 23/10 03/11

12 01.01.03 TRAZO NIVEL Y REPLANTEO 2 días mar 04/11/14mié 05/11/14

13 01.01.03.01 TRAZO Y REPLANTEO PRELIMINAR 2 días mar 04/11/14mié 05/11/1411 04/11 05/11

14 01.02 MOVIMIENTO DE TIERRAS 58 días jue 06/11/14lun 26/01/15

15 01.02.01 EXCAVACIÓN 17 días jue 06/11/14vie 28/11/14

16 01.02.01.01 EXCAVACION EN FORMA MANUAL PARA ZAPATAS 17 días jue 06/11/14 vie 28/11/14 13 06/11 28/11

17 01.02.01.02 EXCAVACION EN FORMA MANUAL PARA VIGAS DE CIMENTACION Y 6 días jue 06/11/14 jue 13/11/14 13 06/11 13/11
CIMIENTOS
18 01.02.02 NIVELACION DEL TERRENO 2 días mié 07/01/15jue 08/01/15

19 01.02.02.01 NIVELACION INTERIOR APISONADO MANUAL 2 días mié 07/01/15jue 08/01/15 21 07/01 08/01

20 01.02.03 RELLENO 8 días vie 26/12/14 mar 06/01/15

21 01.02.03.01 RELLENO COMPACTADO CON MATERIAL PROPIO EN ZANJAS 8 días vie 26/12/14 mar 06/01/1533 26/12 06/01

22 01.02.04 ELIMINACION DE MATERIAL EXCEDENTE 12 días vie 09/01/15 lun 26/01/15

23 01.02.04.01 ACARREO DE MATERIAL EXCEDENTE CON BUGGIE D=30M. 11 días vie 09/01/15 vie 23/01/15 19 09/01 23/01

24 01.02.04.02 ELIMINACION DE MATERIAL EXCEDENTE (2km) 1 día lun 26/01/15 lun 26/01/15 23 26/01 26/01

25 01.03 OBRAS DE CONCRETO SIMPLE 19 días lun 01/12/14jue 25/12/14

26 01.03.01 SOLADOS 1 día lun 01/12/14lun 01/12/14

27 01.03.01.01 SOLADO PARA ZAPATAS 4" 1:12 C:H 1 día lun 01/12/14 lun 01/12/14 16 01/12 01/12

28 01.03.01.02 SOLADO PARA VIGAS DE CIMENTACION DE 4" 1:12 C:H 1 día lun 01/12/14 lun 01/12/14 16;17 01/12 01/12

29 01.03.02 CIMIENTOS 1 día mar 02/12/14mar 02/12/14

30 01.03.02.01 CIMIENTOS CORRIDOS 1:10 + 30% PG 1 día mar 02/12/14mar 02/12/1417;28 02/12 02/12

31 01.03.03 SOBRECIMIENTOS 10 días vie 12/12/14 jue 25/12/14

32 01.03.03.01 SOBRECIMIENTOS: ENCOFRADO Y DESENCOF 9 días vie 12/12/14 mié 24/12/1440;30 12/12 24/12

33 01.03.03.02 SOBRECIMIENTOS: CONCRETO 1:8 + 25% PM 1 día jue 25/12/14 jue 25/12/14 32 25/12 25/12

34 01.04 OBRAS DE CONCRETO ARMADO 68 días mar 02/12/14jue 05/03/15

35 01.04.01 ZAPATA 3 días mar 02/12/14jue 04/12/14

36 01.04.01.01 ZAPATA: ACERO DE REFUERZO FY=4200 KG/CM2 2 días mar 02/12/14mié 03/12/1427 02/12 03/12

37 01.04.01.02 ZAPATA: CONCRETO F'C=210 KG/CM2 1 día jue 04/12/14 jue 04/12/14 36 04/12 04/12

38 01.04.02 VIGAS DE CIMENTACION 5 días vie 05/12/14 jue 11/12/14

39 01.04.02.01 VIGA DE CIMENTACION: ACERO DE REFUERZO FY=4200 KG/CM2 4 días vie 05/12/14 mié 28;37 05/12 10/12
10/12/14
40 01.04.02.02 VIGA DE CIMENTACION: CONCRETO F'C=210 KG/CM2 1 día jue 11/12/14 jue 11/12/14 39 11/12 11/12

41 01.04.03 COLUMNA 14 días mar 27/01/15vie 13/02/15

42 01.04.03.01 COLUMNA: ACERO DE REFUERZO FY=4200 KG/CM2 5 días mar 27/01/15lun 02/02/15 60 27/01 02/02

43 01.04.03.02 COLUMNA: ENCOFRADO Y DESENCOFRADO 8 días mar 03/02/15jue 12/02/15 42 03/02 12/02

44 01.04.03.03 COLUMNA: CONCRETO F'C=210 KG/CM2 1 día vie 13/02/15 vie 13/02/15 43 13/02 13/02

45 01.04.04 VIGAS 14 días lun 16/02/15jue 05/03/15

46 01.04.04.01 VIGAS: ACERO DE REFUERZO FY=4200 KG/CM2 5 días jue 26/02/15 mié 04/03/1547 26/02 04/03

47 01.04.04.02 VIGAS: ENCOFRADO Y DESENCOFRADO 8 días lun 16/02/15 mié 25/02/1544 16/02 25/02

48 01.04.04.03 VIGAS: CONCRETO F'C=210 KG/CM2 1 día jue 05/03/15 jue 05/03/15 46 05/03 05/03

49 01.05 ESTRUCTURA DE MADERA Y COBERTURA 26 días jue 05/03/15jue 09/04/15

50 01.05.01 ARMADURA DE TECHO 9 días jue 05/03/15mar 17/03/15

51 01.05.01.01 APOYO PARA ANCLAJE DE TIJERAL 4 días jue 05/03/15 mar 10/03/1546 05/03 10/03

52 01.05.01.02 TIJERAL T-1 L=9.65M 3 días mié 11/03/15vie 13/03/15 51;48 11/03 13/03

53 01.05.01.03 CORREAS DE MADERA 3"X2" 2 días lun 16/03/15 mar 17/03/1552 16/03 17/03

54 01.05.02 COBERTURA 17 días mié 18/03/15jue 09/04/15

55 01.05.02.01 COBERTURA CON CALAMINON TIPO T DE 50MM 15 días mié 18/03/15mar 07/04/1553 18/03 07/04

56 01.05.02.02 CUMBRERA DENTADA CALAMINON 2 días mié 08/04/15jue 09/04/15 55 08/04 09/04

57 01.06 MUROS Y TABIQUES DE ALBAÑILERIA 127 días vie 26/12/14 lun 22/06/15

58 01.06.01 MUROS DE LADRILLO KK DE ARCILLA DE SOGA CON MEZCLA 1:4 X 1.5 7 días vie 26/12/14 lun 05/01/15 33 26/12 05/01
cm
59 01.06.02 MUROS DE LADRILLO KK DE ARCILLA DE CABEZA CON MEZCLA 1:4 X 21 días vie 26/12/14 vie 23/01/15 58CC 26/12 23/01
1.5 cm
60 01.06.03 REFUERZO DE AMARRE EN MUROS 1 día lun 26/01/15 lun 26/01/15 59 26/01 26/01

61 01.06.04 TABIQUERIA DE MELAMINE CON ESTRUCTURA DE ALUMINIO EN 2 días vie 19/06/15 lun 22/06/15 102 19/06 22/06
CUBICULOS DE SS.HH.
62 01.07 REVOQUES Y REVESTIMIENTOS 54 días mié 08/04/15lun 22/06/15

63 01.07.01 EN MUROS 26 días mié 08/04/15mié 13/05/15

64 01.07.01.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO CON MORTERO 1:5 4 días mié 08/04/15lun 13/04/15 55 08/04 13/04

65 01.07.01.02 TARRAJEO EN MUROS INTERIORES Y EXTERIORES 26 días mié 08/04/15mié 13/05/1555 08/04 13/05

66 01.07.02 EN COLUMNAS 5 días mié 08/04/15mar 14/04/15

67 01.07.02.01 TARRAJEO DE SUPERFICIE DE COLUMNAS 5 días mié 08/04/15mar 14/04/1555 08/04 14/04

68 01.07.03 EN VIGAS 15 días jue 14/05/15mié 03/06/15

69 01.07.03.01 TARRAJEO DE SUPERFICIES DE VIGAS 15 días jue 14/05/15 mié 03/06/1565 14/05 03/06

70 01.07.04 VESTIDURA DE DERRAMES 13 días jue 04/06/15lun 22/06/15

71 01.07.04.01 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS 7 días jue 04/06/15 vie 12/06/15 65;67;69 04/06 12/06

72 01.07.04.02 BRUÑAS 6 días lun 15/06/15 lun 22/06/15 71 15/06 22/06

73 01.08 CIELORRASOS 38 días vie 10/04/15 mar 02/06/15

74 01.08.01 CIELO RASO CON BALDOSAS DE FIBROCEMENTO TEXTURADO DE O.61 30 días vie 10/04/15 jue 21/05/15 56 10/04 21/05
x 0.61M E=4MM (INC. SUM. Y COLOCACION)
75 01.08.02 CIELORASO EXTERIOR SISTEMA DRYWALL CON PLANCHA DE 8 días vie 22/05/15 mar 74 22/05 02/06
FIBROCEMENTO E=6MM (INC. SUM. Y COLOCACION) 02/06/15
76 01.09 PISOS Y PAVIMENTOS 64 días mar 14/04/15vie 10/07/15

77 01.09.01 EN PISOS 64 días mar 14/04/15vie 10/07/15

78 01.09.01.01 FALSO PISO 4" MEZCLA 1:8 3 días mar 14/04/15jue 16/04/15 64 14/04 16/04

79 01.09.01.02 PISO DE MADERA MACHIHEMBRADO 16 días vie 19/06/15 vie 10/07/15 102 19/06 10/07

80 01.09.01.03 PISO DE CERAMICO 40CM X 40CM ANTIDESLIZANTE 4 días vie 17/04/15 mié 22/04/1578 17/04 22/04

81 01.09.02 EN VEREDAS 5 días jue 14/05/15mié 20/05/15

82 01.09.02.01 VEREDAS: CONCRETO F'C=175 KG/CM2 E=10CM ACABADO 1 día mar mar 83 19/05 19/05
COLOREADO 19/05/15 19/05/15
83 01.09.02.02 VEREDAS: ENCOFRADO Y DESENCOFRADO 3 días jue 14/05/15 lun 18/05/15 87 14/05 18/05

84 01.09.02.03 VEREDAS: JUNTA ASFALTICA 1 día mié 20/05/15mié 20/05/1582 20/05 20/05

85 01.10 ZOCALOS Y CONTRAZOCALOS 67 días mar 14/04/15mié 15/07/15

86 01.10.01 CONTRAZOCALOS 49 días vie 08/05/15 mié 15/07/15

87 01.10.01.01 CONTRAZOCALO DE CEMENTO E=2 cm H=30cm (EXTERIORES) 4 días vie 08/05/15 mié 13/05/1565FF 08/05 13/05

88 01.10.01.02 CONTRAZOCALO DE MADERA AGUANO DE 3/4" X 3" RODON 3/4" 3 días lun 13/07/15 mié 79 13/07 15/07
15/07/15
89 01.10.02 ZOCALOS 12 días mar 14/04/15mié 29/04/15

90 01.10.02.01 ZOCALO DE MAYOLICA DE COLOR DE 40X40CM 12 días mar 14/04/15mié 29/04/1564 14/04 29/04

91 01.11 CARPINTERIA DE MADERA 5 días vie 19/06/15 jue 25/06/15

92 01.11.01 PUERTA DE MADERA TABLERO REBAJADO 5 días vie 19/06/15 jue 25/06/15 102 19/06 25/06

93 01.12 CERRAJERIA 2 días mié 24/06/15jue 25/06/15

94 01.12.01 BISAGRAS 2 días mié 24/06/15jue 25/06/15

95 01.12.01.01 BISAGRA 3 1/2" X 3 1/2" 2 días mié 24/06/15jue 25/06/15 92FF 24/06 25/06

96 01.12.02 CERRADURAS 1 día jue 25/06/15jue 25/06/15

97 01.12.02.01 CERRADURA PRINCIPAL 1 día jue 25/06/15 jue 25/06/15 92FF 25/06 25/06

98 01.12.02.02 MANIJA DE BRONCE PARA PUERTAS 1 día jue 25/06/15 jue 25/06/15 92FF 25/06 25/06

99 01.13 VIDRIOS, CRISTALES Y SIMILARES 25 días vie 19/06/15 jue 23/07/15

100 01.13.01 VIDRIO SISTEMA MODUGLASS 6 mm 25 días vie 19/06/15 jue 23/07/15 102 19/06 23/07

101 01.14 PINTURA 47 días jue 14/05/15vie 17/07/15

102 01.14.01 PINTURA EN INTERIORES, EXTERIORES MUROS 11 días jue 04/06/15 jue 18/06/15 69 04/06 18/06

103 01.14.02 PINTURA EN COLUMNAS Y VIGAS 5 días jue 04/06/15 mié 10/06/1569 04/06 10/06

104 01.14.03 PINTURA EN PUERTAS CON BARNIZ 2 MANOS 2 días vie 26/06/15 lun 29/06/15 92;61 26/06 29/06

105 01.14.04 PINTURA DE CONTRAZOCALO CON BARNIZ 2 días jue 16/07/15 vie 17/07/15 88 16/07 17/07
106 01.14.05 PINTURA DE CONTRAZOCALO DE CEMENTO 2 días jue 14/05/15 vie 15/05/15 87 14/05 15/05

107 01.15 INSTALACIONES SANITARIAS 14 días mar 07/04/15vie 24/04/15

108 01.15.01 SALIDAS DE PVC SAL PARA DESAGUE DE 2" 3 días mar 14/04/15jue 16/04/15 78FF 14/04 16/04

109 01.15.02 SALIDAS DE PVC SAL PARA DESAGUE DE 4" 2 días mié 15/04/15jue 16/04/15 78FF 15/04 16/04

110 01.15.03 TUBERIA DE DESAGUE PVC SAL 2" 1 día jue 16/04/15 jue 16/04/15 78FF 16/04 16/04

111 01.15.04 TUBERIA DE DESAGUE PVC SAL 4" 2 días mié 15/04/15jue 16/04/15 78FF 15/04 16/04

112 01.15.05 SUMIDERO CROMADO 2" 2 días jue 23/04/15 vie 24/04/15 80 23/04 24/04

113 01.15.06 REGISTRO ROSCADO DE BRONCE 4" 2 días mié 15/04/15jue 16/04/15 78FF 15/04 16/04

114 01.15.07 TRAMPA "P" DE PVC SAL PARA DESAGUE DE 2" 6 días jue 09/04/15 jue 16/04/15 78FF 09/04 16/04

115 01.15.08 YEE DE PVC 4" X 2" 8 días mar 07/04/15jue 16/04/15 78FF 07/04 16/04

116 01.15.09 CAJA DE REGISTRO DE DESAGUE 12" X 24" 1 día jue 16/04/15 jue 16/04/15 78FF 16/04 16/04

117 01.15.10 YEE DE PVC 4" X 4" 2 días mié 15/04/15jue 16/04/15 78FF 15/04 16/04

118 01.15.11 REDUCCION DE PVC 4" X 2" 1 día jue 16/04/15 jue 16/04/15 78FF 16/04 16/04

119 01.15.12 CODO PVC SAL 2" X 45° 1 día jue 16/04/15 jue 16/04/15 78FF 16/04 16/04

120 01.16 APARATOS SANITARIOS Y ACCESORIOS 3 días jue 23/04/15lun 27/04/15

121 01.16.01 INODOROS DE TANQUE BAJO PARA BABY 2 días jue 23/04/15 vie 24/04/15 80 23/04 24/04

122 01.16.02 LAVATORIO DE LOZA PARA BABY 2 días jue 23/04/15 vie 24/04/15 80 23/04 24/04

123 01.16.03 COLOCACION DE APARATOS SANITARIOS 3 días jue 23/04/15 lun 27/04/15 121CC 23/04 27/04

124 01.16.04 INSTALACION DE ACCESORIOS SANITARIOS 2 días jue 23/04/15 vie 24/04/15 121CC 23/04 24/04

125 01.17 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 4 días lun 13/04/15jue 16/04/15

126 01.17.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" 4 días lun 13/04/15 jue 16/04/15 78FF 13/04 16/04

127 01.17.02 TUBERIA DE AGUA PVC SAP 1/2" 2 días mié 15/04/15jue 16/04/15 78FF 15/04 16/04

128 01.17.03 VALVULA DE COMPUERTA 1 1/2" 1 día jue 16/04/15 jue 16/04/15 78FF 16/04 16/04

129 01.18 SISTEMA DE AGUA DE LLUVIA 15 días mié 08/04/15mar 28/04/15

130 01.18.01 CANALETA PARA AGUAS PLUVIALES DE F°G° 3 días mié 08/04/15vie 10/04/15 55 08/04 10/04

131 01.18.02 BAJADA DE AGUA PLUVIALES TUBERIA PVC SAP DIAM. 3" 1 día lun 13/04/15 lun 13/04/15 130 13/04 13/04

132 01.18.03 ENCOFRADO Y DESENCOFRADO TUBERIA DE BAJADA 1 día mar 14/04/15mar 14/04/15131 14/04 14/04

133 01.18.04 CONCRETO F'C= 140 KG/CM2 PROTECCION DE TUBERIA 1 día mar 14/04/15mar 14/04/15132FF 14/04 14/04

134 01.18.05 TARRAJEO EN PROTECCION DE TUBERIA 1 día mié 15/04/15mié 15/04/15133 15/04 15/04

135 01.18.06 ABRAZADERA DE PLATINA DE 1"X1/8" 12 días lun 13/04/15 mar 28/04/15131CC 13/04 28/04

136 01.19 INSTALACIONES ELECTRICAS 52 días mié 13/05/15jue 23/07/15

137 01.19.01 SALIDA DE TECHO (CENTRO DE LUZ) 5 días vie 15/05/15 jue 21/05/15 74FF 15/05 21/05

138 01.19.02 INTERRUPTOR UNIPOLAR SIMPLE 2 días mié 20/05/15jue 21/05/15 74FF 20/05 21/05

139 01.19.03 INTERRUPTOR UNIPOLAR DOBLE 1 día jue 21/05/15 jue 21/05/15 74FF 21/05 21/05

140 01.19.04 TOMACORRIENTE DOBLE CON PUESTA A TIERRA ADOSADO EN PARED 4 días lun 18/05/15 jue 21/05/15 74FF 18/05 21/05

141 01.19.05 TABLERO DE DISTRIBUCION 1 día mié 13/05/15mié 13/05/1565FF 13/05 13/05

142 01.19.06 FLUORESCENTE LINEAL 2x36W TIPO HERMETICO IP 55 P/ADOSAR EN TECHO


1 día jue 21/05/15 jue 21/05/15 74FF 21/05 21/05

143 01.19.07 FLUORESCENTE CIRCULAR 32W C/PANTALLA REFRACTORIA P/ADOSAR 1EN


díaTECHO jue 21/05/15 jue 21/05/15 74FF 21/05 21/05

144 01.19.08 SPOT LIGT 1 día mar 02/06/15mar 02/06/1575FF 02/06 02/06

145 2.19.9 FIN 0 días jue 23/07/15 jue 23/07/15 100;105;104;134;135 23/07

Tarea División Hito Resumen Resumen del proyecto Agrupar por síntesis Tarea resumida Tarea crítica resumida Hito resumido Progreso resumido Tareas externas Hito externo Tarea inactiva Hito inactivo Resumen inactivo Tarea manual solo duración Informe de resumen manual Resumen manual solo el comienzo solo fin Fecha límite Tarea crítica Tareas críticas División crítica Progreso

Proyecto: MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS DE LA I.E.I. QUILLISANI EN EL CENTRO POBLADO DE QUILLISANI, DISTRITO DE PARATIA, PROVINCIA DE LAMPA - PUNO Alumna: Ely Condori Pacoricona ---- Página 1