You are on page 1of 3

 

1. Fixing Gabion – Labour & Material Cost  
‐ 17 pieces ( 1m x 3m: Gabion ) x RM 180/pcs     = RM 3,060 
‐ 6m x 9m Hard core: RM x 77mt        = RM 2,772 
‐ Hiring Labour – Fixing Gabion: RM100/pcs x 17 pcs  = RM 1,700 
‐ Hiring Backhoe: RM 50/pcs x 17pcs      = RM    850 
   RM 8,382 

2. Foundation (1 Layer Hard core 6” x 9”) – 12” Thickness 
‐ 50m (Length) x 2.4m (Width) x 0.3m (Thickness)   = 36m3 
‐ 36m3 / 8m3 (Trip)          = ± 5 trips 
‐ 5 trips x ± 18mt/trip          = 90 mt 
‐ 90 mt x RM 36/mt          = RM 3,240 

3. Laterite (1 Layer Laterite on top of Hard Core) 
‐ 6” Thickness of laterite 
‐ 50m (length) x 2.4m (width) x 0.183m (thickness: 6”)  =± 22m3 
‐ 22m3/3m3 per trip ( 6 tonne lorry)      = ± 7 trips 
‐ ± 7 trips x RM 40/trip          = RM 280 

4. Drain 
‐ Drain length     = 170 ft @ 
‐ V Shape Drain    = 2 ft (length) x 1 ft (width)    
‐ 170 ft/ 2 ft/mt    = 85 units V shape drain 
 
V Shape Drain Cost & Labour 
‐ V Shape Drain : RM 25/unit x 85 units      = RM 2,125 
‐ Labour : RM 20/unit x 85 units        = RM 1,750 
‐ Cost of Cement & Bricks : RM 10/unit x 85 units    = RM    850 
   RM 4,725 
 
5. Loading Soil – Transport & Hiring Machine 
(Top up soil to original level – Land Slide Area) 
‐  RM 21/trip x 200 trip          = RM 4,200 

 
Total Cost :‐ 

1. Gabion    = RM 8,382 
2. Foundation  = RM 3,240 
3. Laterite   = RM    280 
4. Drain    = RM 4,725 
5. Loading Soil  = RM 4,200 
   RM 20,827 @ RM 21,000 