Professional Documents
Culture Documents
1. Fixing Gabion – Labour & Material Cost
‐ 17 pieces ( 1m x 3m: Gabion ) x RM 180/pcs = RM 3,060
‐ 6m x 9m Hard core: RM x 77mt = RM 2,772
‐ Hiring Labour – Fixing Gabion: RM100/pcs x 17 pcs = RM 1,700
‐ Hiring Backhoe: RM 50/pcs x 17pcs = RM 850
RM 8,382
2. Foundation (1 Layer Hard core 6” x 9”) – 12” Thickness
‐ 50m (Length) x 2.4m (Width) x 0.3m (Thickness) = 36m3
‐ 36m3 / 8m3 (Trip) = ± 5 trips
‐ 5 trips x ± 18mt/trip = 90 mt
‐ 90 mt x RM 36/mt = RM 3,240
3. Laterite (1 Layer Laterite on top of Hard Core)
‐ 6” Thickness of laterite
‐ 50m (length) x 2.4m (width) x 0.183m (thickness: 6”) =± 22m3
‐ 22m3/3m3 per trip ( 6 tonne lorry) = ± 7 trips
‐ ± 7 trips x RM 40/trip = RM 280
4. Drain
‐ Drain length = 170 ft @
‐ V Shape Drain = 2 ft (length) x 1 ft (width)
‐ 170 ft/ 2 ft/mt = 85 units V shape drain
V Shape Drain Cost & Labour
‐ V Shape Drain : RM 25/unit x 85 units = RM 2,125
‐ Labour : RM 20/unit x 85 units = RM 1,750
‐ Cost of Cement & Bricks : RM 10/unit x 85 units = RM 850
RM 4,725
5. Loading Soil – Transport & Hiring Machine
(Top up soil to original level – Land Slide Area)
‐ RM 21/trip x 200 trip = RM 4,200
Total Cost :‐
1. Gabion = RM 8,382
2. Foundation = RM 3,240
3. Laterite = RM 280
4. Drain = RM 4,725
5. Loading Soil = RM 4,200
RM 20,827 @ RM 21,000