LISTA CANTITATI INFRASTRUCUTURA 18.04.

2018 unitati cantitati


1 Decopertare/evacuare beton simplu, pietris si teren natural pana la cota -7.10 mc 532.40
2 volum umplutura din depozit local si compactare mc 108.78
3 compactare umplutura mc 108.78
4 Transport rutier pamant 10km t 677.79
pietris indesat prin vibrare in umplutura in lungul axelor A, F/1-12 intre cotele -8.00 si -
5 6.80, pe o latime de 1.5m
mc 107.25
6 refacere strat pietris 15cm mc 166.65
7 folie PVC mp 1444.30
8 Beton simplu C8/10 egalizare sub radier mc 149.72
9 Beton in radier general C30/37 mc 833.66
10 Beton in pereti de subsol C30/37 mc 691.00
11 Beton in plansee peste Ssol 1 si Ssol 2 C30/37 mc 447.34
12 Armatura BST500S in radier general t 85.99
13 Armatura BST500S in pereti de subsol t 56.41
14 Armatura BST500S stalpi aferenti subsol t 39.38
15 Armatura BST500S in plansee peste Ssol 1 si Ssol 2, rampa, t 45.94
16 Armatura BST500S in scari Ssol 1 si Ssol 2 t 1.48
17 Cofraje in radier general mp 196.41
18 Cofraje in pereti de subsol mp 3504.32
19 Cofraje in plansee peste Ssol 1 si Ssol 2 mp 2486.49
20 beton simplu intre subsol si incinta C8/10 mc 400 ~ 600

Atentie: In cantitatile de mai sus sunt incluse si pierderile tehnologice.