Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev.

00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
CRITICAL MILESTONES
MILE 116 31-Aug-18 14-Jan-19 0

Critical Milestone
Mileston (OOK) 136 31-Aug-18 14-Jan-19 0

0000MO021 Complete Spare Part Data Packages 0 31-Aug-18 136 Complete Spare Part Data Packages

0000MO023 Complete AS BUILT drawings 0 14-Jan-19 0 Complete AS BUILT drawings

Critical Milestone
Mileston (IK) 88 13-Sep-18 10-Dec-18 35

0000MI006 Energize J10/J11 Substation 0 13-Sep-18 123 Energize J10/J11 Substation

0000MI011 Complete installation of Large Bore Pipe 0 21-Sep-18 93 Complete installation of Large Bore Pipe

0000MI007 Energize J12/J14 Substation 0 04-Oct-18 73 Energize J12/J14 Substation

0000MI013 Complete all piping Pressure testing. 0 07-Oct-18 77 Complete all piping Pressure testing.

0000MI008 Energize J10/J11 PIB 0 11-Oct-18 95 Energize J10/J11 PIB

0000MI019 Complete Benzene Extraction (J14) and Achieve MCAN 0 13-Oct-18 71 Complete Benzene Extraction (J14) and Achieve MCAN

0000MI018 Complete Isomerisation (J11) Achieve MCAN 0 22-Oct-18* 0 Complete Isomerisation (J11) Achieve MCAN

0000MI009 Energize J12/J14 PIB 0 07-Nov-18 68 Energize J12/J14 PIB

0000MI017 Complete NHT and CCR (J10) Unit Achieve MCAN 0 04-Dec-18* 0 Complete NHT and CCR (J10) Unit Achieve MCAN

0000MI020 Complete Paraxylene Complex (J12) and Achieve MCAN 0 10-Dec-18* 0 Complete Paraxylene Complex (J12) and Achieve MC

0000MI021 Issue Final Mechanical Completion Acceptance Notification 0 10-Dec-18 13 Issue Final Mechanical Completion Acceptance Notifi

Interface Milestone
Milesto by Others 0 15-Sep-18 15-Sep-18 104

0000MF024 Electric Power Available (information from EPC#13) 0 15-Sep-18 104 Electric Power Available (information from EPC#13)

CONSTRUCTION 114 15-Sep-15 A 06-Dec-18 32

A000 100 23-Jan-18 A 20-Nov-18 11

A000HB829S010 Motor Solo Run at A000 (236 nos) (For LV Moto rs) 17 23-Jan-18 A 15-Aug-18 94 Motor Solo Run at A000 (236 nos) (For LV Moto rs)

A000HB829S010-1 Motor Solo Run at A000 (25 nos) (For MV/HV Motors Subject for 40 06-Oct-18 20-Nov-18 6 Motor Solo Run at A000 (25 nos) (For MV/HV Motors Subject for P
Permanent Power)

A100 - Main Pipe Rack 92 15-Sep-15 A 11-Nov-18 20

A100HB782S010 Branch Cable at A100 8 01-Jul-17 A 05-Aug-18 52 Branch Cable at A100

A100HB621S010 A/G Piping on Pipe Rack at A100 36 15-Sep-15 A 06-Sep-18 -6 A/G Piping on Pipe Rack at A100

A100HB680S010 Piping Pressure Test at A100 48 12-Jun-17 A 22-Sep-18 -6 Piping Pressure Test at A100

A100HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A100 60 02-Jan-18 A 07-Oct-18 37 Main Cable & Branch Cabling Te rminati on Works for A100

A100HB792S010 Loop Test at A100 75 31-Dec-17 A 22-Oct-18 37 Loop Test at A100

A100HBA20S010 Finish Painting for A/G Piping at A100 75 27-Jul-17 A 22-Oct-18 10 Finish Painting for A/G Piping at A100

A100HB650S010 Steam Tracing at A100 78 01-Apr-18 A 27-Oct-18 0 Steam Tracing at A100

A100HB832S010 Lighting Work at A100 82 01-Sep-16 A 30-Oct-18 29 Lighting Work at A100

A100HB880S010 Electrical Heat Tracing at A100 82 27-Jan-18 A 30-Oct-18 0 Electrical Heat Tracing at A100

A100HB900S010 Insulation for Piping at A100 90 21-Aug-17 A 11-Nov-18* 0 Insulation for Piping at A100

A210 95 15-Feb-16 A 14-Nov-18 17

A210HB782S010 Branch Cable at A210 8 27-Jul-17 A 05-Aug-18 78 Branch Cable at A210

A210HB621S010 A/G Piping on Pipe Rack at A211 36 15-Feb-16 A 06-Sep-18 11 A/G Piping on Pipe Rack at A211

A210HB623S010 A/G Piping around Equipment at A212 36 01-Oct-16 A 06-Sep-18 11 A/G Piping around Equipment at A212

A210HB623S020 A/G Piping around Equipment at A213 36 22-Nov-16 A 06-Sep-18 11 A/G Piping around Equipment at A213

A210HB680S010 Piping Pressure Test at A210 48 15-Jun-17 A 22-Sep-18 11 Piping Pressure Test at A210

A210HB513S060-1 Box Up of Columns / Drums at A210 (11 Nos) 22 28-Jun-18 A 29-Sep-18 39 Box Up of Columns / Drums at A210 (11 Nos)

A210HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A210 60 02-Jan-18 A 07-Oct-18 37 Main Cable & Branch Cabling Te rminati on Works for A210

A210HB792S010 Loop Test at A210 75 30-Dec-17 A 22-Oct-18 37 Loop Test at A210

A210HBA20S010 Finish Painting for A/G Piping at A210 76 06-Aug-17 A 24-Oct-18 11 Finish Painting for A/G Piping at A210

A210HB880S010 Electrical Heat Tracing at A210 82 31-Mar-18 A 30-Oct-18 3 Electrical Heat Tracing at A210

A210HB830S010 Lighting Work at A210 82 29-Jan-17 A 30-Oct-18 29 Lighting Work at A210

A210HB912S010 Insulation for Piping at A210 95 21-Aug-17 A 14-Nov-18* 0 Insulation for Piping at A210

A220 100 08-Dec-15 A 20-Nov-18 12

A220HB782S010 Branch Cable at A220 8 15-Jul-17 A 09-Aug-18 74 Branch Cable at A220

A220HB621S010 A/G Piping on Pipe Rack at A221 36 03-Mar-16 A 06-Sep-18 8 A/G Piping on Pipe Rack at A221

A220HB623S020 A/G Piping around Equipment at A223 36 06-Nov-16 A 06-Sep-18 12 A/G Piping around Equipment at A223

A220HB623S010 A/G Piping around Equipment at A222 36 08-Dec-15 A 11-Sep-18 8 A/G Piping around Equipment at A222

A220HB582S030 Lube Oil Testi ng & Flush in g for J10 -K-020 0 (J10-U-020 6) a t A220 20 21-Aug-18 12-Sep-18 0 Lube Oil Testi ng & Flush in g for J10 -K-020 0 (J10-U-020 6) a t A220 (Crew 1)
(Crew 1)

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 1 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
A220HB582S030-2 Special cleaning for J10-K-0200 (J10-U-0206) at A220 (HJ 8 13-Sep-18 22-Sep-18 31 Special cleaning for J10-K-0200 (J10-U-0206) at A220 (HJ Sqn4=>n/a)
Sqn4=>n/a)

A220HB680S010 Piping Pressure Test at A220 48 18-Jun-17 A 26-Sep-18 8 Piping Pressure Test at A220

A220HB513S020-1 Box Up of Columns / Drums at A220 (5 Nos) 10 10-Jul-18 A 03-Oct-18 37 Box Up of Columns / Drums at A220 (5 Nos)

A220HB650S010 Steam Tracing at A220 52 09-Aug-18 08-Oct-18 27 Steam Tracing at A220

A220HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A220 63 02-Jan-18 A 11-Oct-18 33 Main Cable & Branch Cabling Te rminati on Works for A220

A220HB582S20 Assembly of Recycle Gas Compressor (J10-K-0200) - 2nd at A220 20 23-Sep-18 15-Oct-18 31 Assembly of Recycle Gas Compressor (J10-K-0200) - 2nd at A220 (Final Alignment)
(Final Alignment)

A220HB792S010 Loop Test at A220 78 30-Dec-17 A 27-Oct-18 33 Loop Test at A220

A220HB830S010 Lighting Work at A220 82 31-Dec-16 A 30-Oct-18 29 Lighting Work at A220

A220HBA20S010 Finish Painting for A/G Piping at A220 80 08-Aug-17 A 03-Nov-18 8 Finish Painting for A/G Piping at A220

A220HB912S010 Insulation for Piping at A220 100 03-Dec-17 A 20-Nov-18* 0 Insulation for Piping at A220

A230 99 07-Jan-16 A 19-Nov-18 13

A230HB730S010 Local Instrument Installation at A230 29 07-Aug-17 A 30-Aug-18 50 Local Instrument Installation at A230

A230HB621S010 A/G Piping on Pipe Rack at A231 36 07-Jan-16 A 06-Sep-18 0 A/G Piping on Pipe Rack at A231

A230HB623S020 A/G Piping around Equipment at A233 36 05-Dec-16 A 06-Sep-18 3 A/G Piping around Equipment at A233

A230HB782S010 Branch Cable at A230 35 16-Jul-17 A 06-Sep-18 50 Branch Cable at A230

A230HB623S010 A/G Piping around Equipment at A232 38 16-May-16 A 10-Sep-18 0 A/G Piping around Equipment at A232

A230HB680S010 Piping Pressure Test at A230 50 17-Aug-17 A 25-Sep-18 0 Piping Pressure Test at A230

A230HB513S020-1 Box Up of Columns / Drums at A230 (3 Nos) 12 19-Sep-18 02-Oct-18 38 Box Up of Columns / Drums at A230 (3 Nos)

A230HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A230 63 02-Jan-18 A 10-Oct-18 34 Main Cable & Branch Cabling Te rminati on Works for A230

A230HB792S010 Loop Test at A230 77 30-Dec-17 A 25-Oct-18 34 Loop Test at A230

A230HB830S010 Lighting Work at A230 82 18-Apr-17 A 30-Oct-18 29 Lighting Work at A230

A230HBA20S010 Finish Painting for A/G Piping at A230 90 07-Sep-17 A 11-Nov-18 0 Finish Painting for A/G Piping at A230

A230HB912S010 Insulation for Piping at A230 98 25-Sep-17 A 19-Nov-18* 0 Insulation for Piping at A230

A240 94 01-May-16 A 13-Nov-18 18

A240HB782S010 Branch Cable at A240 8 17-May-17 A 05-Aug-18 78 Branch Cable at A240

A240HBB00S10 Fire Proofing for Equipment at A240 15 16-Apr-17 A 13-Aug-18 70 Fire Proofing for Equipment at A240

A240HB621S010 A/G Piping on Pipe Rack at A241 36 01-May-16 A 06-Sep-18 7 A/G Piping on Pipe Rack at A241

A240HB623S010 A/G Piping around Equipment at A242 36 10-Oct-16 A 06-Sep-18 7 A/G Piping around Equipment at A242

A240HB623S020 A/G Piping around Equipment at A243 36 01-Nov-16 A 06-Sep-18 7 A/G Piping around Equipment at A243

A240HB680S010 Piping Pressure Test at A240 48 15-Jun-17 A 22-Sep-18 7 Piping Pressure Test at A240

A240HB513S030-1 Box Up of Columns / Drums at A240 (13 Nos) 26 30-Aug-18 29-Sep-18 41 Box Up of Columns / Drums at A240 (13 Nos)

A240HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A240 60 02-Jan-18 A 07-Oct-18 37 Main Cable & Branch Cabling Te rminati on Works for A240

A240HB792S010 Loop Test at A240 74 30-Dec-17 A 22-Oct-18 37 Loop Test at A240

A240HBA20S010 Finish Painting for A/G Piping at A240 79 01-Aug-17 A 28-Oct-18 7 Finish Painting for A/G Piping at A240

A240HB830S010 Lighting Work at A240 82 31-Dec-16 A 30-Oct-18 29 Lighting Work at A240

A240HB880S010 Electrical Heat Tracing at A240 82 31-Mar-18 A 30-Oct-18 2 Electrical Heat Tracing at A240

A240HB912S010 Insulation for Piping at A240 94 29-Aug-17 A 13-Nov-18* 0 Insulation for Piping at A240

A250 93 29-Mar-17 A 12-Nov-18 19

A250HB680S010 Piping Pressure Test at A250 42 10-Jul-17 A 15-Sep-18 5 Piping Pressure Test at A250

A250HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A250 55 02-Jan-18 A 30-Sep-18 43 Main Cable & Branch Cabling Te rminati on Works for A250

A250HB792S010 Loop Test at A250 69 14-Jan-18 A 15-Oct-18 43 Loop Test at A250

A250HBA20S010 Finish Painting for A/G Piping at A250 80 14-Aug-17 A 29-Oct-18 5 Finish Painting for A/G Piping at A250

A250HB830S010 Lighting Work at A250 82 29-Mar-17 A 30-Oct-18 29 Lighting Work at A250

A250HB912S010 Insulation for Piping at A250 93 05-Dec-17 A 12-Nov-18* 0 Insulation for Piping at A250

A310 95 31-Dec-15 A 14-Nov-18 16

A310HBB00S10 Fire Proofing for Equipment at A310 30 20-Apr-17 A 30-Aug-18 55 Fire Proofing for Equipment at A310

A310HB730S010 Local Instrument Installation at A310 30 06-Mar-17 A 30-Aug-18 37 Local Instrument Installation at A310

A310HB860S010 Communication System Installation at A310 30 01-May-17 A 30-Aug-18 29 Communication System Installation at A310

A310HB623S020 A/G Piping around Equipment (after A31E10-3 finish) at A313 36 21-Apr-17 A 06-Sep-18 23 A/G Piping around Equipment (after A31E10-3 finish) at A313

A310HB621S010 A/G Piping on Pipe Rack at A311 36 31-Dec-15 A 06-Sep-18 23 A/G Piping on Pipe Rack at A311

A310HB623S010 A/G Piping around Equipment at A312 36 14-Aug-16 A 06-Sep-18 23 A/G Piping around Equipment at A312

A310HB782S010 Branch Cable at A310 37 02-Aug-17 A 08-Sep-18 37 Branch Cable at A310

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 2 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
A310HB680S010 Piping Pressure Test at A310 48 01-Jul-17 A 22-Sep-18 23 Piping Pressure Test at A310

A310HB911S010 Insulation for Equipment at A310 50 25-Feb-17 A 23-Sep-18 19 Insulation for Equipment at A310

A310HB513S60-1 Box Up of Columns / Drums at A310 (37 Nos) 30 26-Aug-18 29-Sep-18 39 Box Up of Columns / Drums at A310 (37 Nos)

A310HBB00S010 Fire Proofing for Steel Structure around Equipment at A310 56 04-Apr-18 A 30-Sep-18 49 Fire Proofing for Steel Structure around Equipment at A310

A310HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A310 63 15-Feb-18 A 08-Oct-18 24 Main Cable & Branch Cabling Te rminati on Works for A310

A310HB650S010 Steam Tracing at A310 69 31-Mar-18 A 15-Oct-18 13 Steam Tracing at A310

A310HB792S010 Loop Test at A310 75 30-Dec-17 A 23-Oct-18 24 Loop Test at A310

A310HB830S010 Lighting Work (except CCR Str) at A310 82 01-Dec-16 A 30-Oct-18 29 Lighting Work (except CCR Str) at A310

A310HB830S020 Lighting Work (around CCR Str) at A310 82 01-Dec-16 A 30-Oct-18 29 Lighting Work (around CCR Str) at A310

A310HB880S010 Electrical Heat Tracing at A310 82 27-Jan-18 A 30-Oct-18 3 Electrical Heat Tracing at A310

A310HBA20S010 Finish Painting for A/G Piping at A310 84 19-Aug-17 A 01-Nov-18 4 Finish Painting for A/G Piping at A310

A310HB912S010 Insulation for Piping at A310 95 29-Aug-17 A 14-Nov-18* 0 Insulation for Piping at A310

A320 112 13-Jan-16 A 04-Dec-18 34

A320HB582S40 Lube Oil Testi ng & Flush in g for J10 -K-050 0A (J10-U-0506A) at A320 13 14-Jun-18 A 11-Aug-18 6 Lube Oil Testi ng & Flush in g for J10 -K-050 0A (J10-U-0506A) at A320 (Crew 1)
(Crew 1)

A320HB582S160 Lube Oil Testi ng & Flush in g for J10 -K-050 0B (J10-U-05 06B) a t A320 25 18-Jul-18 A 25-Aug-18 0 Lube Oil Testi ng & Flush in g for J10 -K-050 0B (J10-U-05 06B) a t A320 (Crew 1)
(Crew 1)

A320HB582S50 Lube Oil Testi ng & Flush in g for J10 -K-056 0 (J10-U-056 6) a t A320 25 01-Jul-18 A 25-Aug-18 20 Lube Oil Testi ng & Flush in g for J10 -K-056 0 (J10-U-056 6) a t A320 (Crew 2)
(Crew 2)

A320HB860S010 Communication System Installation at A320 30 13-May-17 A 30-Aug-18 29 Communication System Installation at A320

A320HB582S50-2 Special cleaning for J10-K-0560 (J10-U-0566) at A320 HJ (HJ 7 26-Aug-18 02-Sep-18 59 Special cleaning for J10-K-0560 (J10-U-0566) at A320 HJ (HJ Sqn10=>n/a)
Sqn10=>n/a)

A320HB582S40-2 Special cleaning for J10-K-0500A/B (J10-U-0506A/B) at A320 (HJ 8 26-Aug-18 03-Sep-18 47 Special cleaning for J10-K-0500A/B (J10-U-0506A/B) at A320 (HJ Sqn8=>n/a)
Sqn8=>n/a)

A320HB621S010 A/G Piping on Pipe Rack at A321 36 13-Jan-16 A 06-Sep-18 0 A/G Piping on Pipe Rack at A321

A320HB623S010 A/G Piping around Equipment at A322 36 25-Apr-16 A 06-Sep-18 0 A/G Piping around Equipment at A322

A320HB623S020 A/G Piping around Equipment at A323 36 01-Oct-16 A 06-Sep-18 0 A/G Piping around Equipment at A323

A320HB782S010 Branch Cable at A320 37 19-Aug-17 A 08-Sep-18 49 Branch Cable at A320

A320HB680S010 Piping Pressure Test at A320 48 18-Jun-17 A 22-Sep-18 0 Piping Pressure Test at A320

A320HB582S30 Lube Oil Testi ng & Flush in g for J10 -K-040 0A (J10-U-0406A) at A320 20 02-Sep-18 24-Sep-18 0 Lube Oil Testi ng & Flush in g for J10 -K-040 0A (J10-U-0406A) at A320 (Crew 1)
(Crew 1)

A320HB582S120 Assembly/Erection of Refrigerant Compressor (J10-K-0560) - 2nd at 20 03-Sep-18 25-Sep-18 59 Assembly/Erection of Refrigerant Compressor (J10-K-0560) - 2nd at A320 (Final Alignment)
A320 (Final Alignment)

A320HB582S100 Assembly of H2 Rich Gas Compressor (J10-K-0500A) - 2nd at A320 20 04-Sep-18 26-Sep-18 47 Assembly of H2 Rich Gas Compressor (J10-K-0500A) - 2nd at A320 (Final Alignment)
(Final Alignment)

A320HB582S110 Assembly of H2 Rich Gas Compressor (J10-K-0500B) - 2nd at A320 20 04-Sep-18 26-Sep-18 47 Assembly of H2 Rich Gas Compressor (J10-K-0500B) - 2nd at A320 (Final Alignment)
(Final Alignment)

A320HB513S090-1 Box Up of Columns / Drums at A320 (13 Nos) 26 30-Jun-18 A 29-Sep-18 39 Box Up of Columns / Drums at A320 (13 Nos)

A320HB800S010 Power Energized for AFD at A320 0 30-Sep-18 90 Power Energized for AFD at A320

A320HB582S080 Lube Oil Testi ng & Flush in g for J10 -K-040 0B (J10-U-04 06B) a t A320 20 13-Sep-18 06-Oct-18 0 Lube Oil Testi ng & Flush in g for J10 -K-040 0B (J10-U-04 06B) a t A320 (CRew 1)
(CRew 1)

A320HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A320 61 02-Jan-18 A 07-Oct-18 37 Main Cable & Branch Cabling Te rminati on Works for A320

A320HB582S080-2 Special cleaning for J10-K-0400A/B(J10-U-0406A/B) at A320 (HJ 7 07-Oct-18 14-Oct-18 12 Special cleaning for J10-K-0400A/B(J10-U-0406A/B) at A320 (HJ Sqn9=>n/a)
Sqn9=>n/a)

A320HB650S010 Steam Tracing at A320 69 26-May-18 A 15-Oct-18 1 Steam Tracing at A320

A320HBA20S010 Finish Painting for A/G Piping at A320 75 08-Aug-17 A 23-Oct-18 0 Finish Painting for A/G Piping at A320

A320HB830S010 Lighting Work at A320 82 11-Mar-17 A 30-Oct-18 29 Lighting Work at A320

A320HB912S010 Insulation for Piping at A320 28 30-Jun-18 A 31-Oct-18* 0 Insulation for Piping at A320

A320HB582S130 Assembly of Recycle Compressor - (J10-K-0400A) - 2nd at A320 20 15-Oct-18 06-Nov-18 12 Assembly of Recycle Compressor - (J10-K-0400A) - 2nd at A320 (Final Al
(Final Alignment)

A320HB582S140 Assembly of Recycle Compressor - (J10-K-0400B) - 2nd at A320 20 15-Oct-18 06-Nov-18 12 Assembly of Recycle Compressor - (J10-K-0400B) - 2nd at A320 (Final Al
(Final Alignment)

A320HB792S010 Loop Test at A320 113 30-Dec-17 A 04-Dec-18 0 Loop Test at A320

A330 100 18-Jan-16 A 20-Nov-18 12

A330HB782S010 Branch Cable at A330 18 10-May-17 A 16-Aug-18 68 Branch Cable at A330

A330HB860S010 Communication System Installation at A330 30 20-May-17 A 30-Aug-18 29 Communication System Installation at A330

A330HB623S020 A/G Piping around Equipment at A333 36 24-Jun-16 A 06-Sep-18 19 A/G Piping around Equipment at A333

A330HB621S010 A/G Piping on Pipe Rack at A331 36 18-Jan-16 A 06-Sep-18 19 A/G Piping on Pipe Rack at A331

A330HB623S010 A/G Piping around Equipment at A332 36 22-Oct-16 A 06-Sep-18 19 A/G Piping around Equipment at A332

A330HB680S010 Piping Pressure Test at A330 48 09-Jul-17 A 22-Sep-18 19 Piping Pressure Test at A330

A330HB513S010-1 Box Up of Columns / Drums at A330 (9 Nos) 26 24-Jul-18 A 29-Sep-18 19 Box Up of Columns / Drums at A330 (9 Nos)

A330HB650S010 Steam Tracing at A330 57 02-Jun-18 A 01-Oct-18 30 Steam Tracing at A330

A330HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A330 63 02-Jan-18 A 08-Oct-18 36 Main Cable & Branch Cabling Te rminati on Works for A330

A330HB792S010 Loop Test at A330 75 30-Dec-17 A 23-Oct-18 36 Loop Test at A330

A330HB830S010 Lighting Work at A330 82 25-Feb-17 A 30-Oct-18 29 Lighting Work at A330

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 3 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
A330HBA20S010 Finish Painting for A/G Piping at A330 84 08-Aug-17 A 01-Nov-18 9 Finish Painting for A/G Piping at A330

A330HB912S010 Insulation for Piping at A330 100 29-Aug-17 A 20-Nov-18* 0 Insulation for Piping at A330

A340 112 28-Apr-16 A 04-Dec-18 34

A340HB730S010 Local Instrument Installation at A340 13 03-Aug-17 A 11-Aug-18 60 Local Instrument Installation at A340

A340HB782S010 Branch Cable at A340 21 08-Aug-17 A 20-Aug-18 60 Branch Cable at A340

A340HB623S020 A/G Piping around Equipment at A343 36 28-Apr-16 A 06-Sep-18 11 A/G Piping around Equipment at A343

A340HB623S010 A/G Piping around Equipment at A342 36 01-Oct-16 A 06-Sep-18 11 A/G Piping around Equipment at A342

A340HB582S060 Lube Oil Testi ng & Flush in g for J10 -K-070 2 (J10-U-072 6) a t A340 20 21-Aug-18 12-Sep-18 20 Lube Oil Testi ng & Flush in g for J10 -K-070 2 (J10-U-072 6) a t A340 (Crew 2)
(Crew 2)

A340HB582S060-2 Special cleaning for J10-K-0702 (J10-U-0726) at A340 (HJ 7 13-Sep-18 20-Sep-18 32 Special cleaning for J10-K-0702 (J10-U-0726) at A340 (HJ Sqn5=>n/a)
Sqn5=>n/a)

A340HB680S010 Piping Pressure Test at A340 48 12-Jun-17 A 22-Sep-18 11 Piping Pressure Test at A340

A340HB513S010-1 Box Up of Columns / Drums at A340 (15 Nos) 30 03-Jul-18 A 29-Sep-18 41 Box Up of Columns / Drums at A340 (15 Nos)

A340HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A340 61 02-Jan-18 A 07-Oct-18 37 Main Cable & Branch Cabling Te rminati on Works for A340

A340HB582S40 Assembly of Regeneration Loop Compressor (J10-K-0702) - 2nd at 20 22-Sep-18 14-Oct-18 32 Assembly of Regeneration Loop Compressor (J10-K-0702) - 2nd at A340
A340

A340HB582S20 Lube Oil Testi ng & Flush in g for J10 -K-070 1A/B/C (J10-U -0716A/B/C) 20 25-Sep-18 17-Oct-18 0 Lube Oil Testi ng & Flush in g for J10 -K-070 1A/B/C (J10-U -0716A/B/C) at A340 (Crew1&
at A340 (Crew1&2)

A340HB582S070-2 Special cleaning for J10-K-0703A/B/C (J10-U-0736A/B/C) at A340 8 13-Oct-18 22-Oct-18 0 Special cleaning for J10-K-0703A/B/C (J10-U-0736A/B/C) at A340 (HJ Sqn7=>n/a)
(HJ Sqn7=>n/a)

A340HBA20S010 Finish Painting for A/G Piping at A340 76 06-Aug-17 A 24-Oct-18 11 Finish Painting for A/G Piping at A340

A340HB582S20-2 Special cleaning for J10-K-0701A/B/C (J10-U-0716A/B/C) at A340 8 17-Oct-18 25-Oct-18 48 Special cleaning for J10-K-0701A/B/C (J10-U-0716A/B/C) at A340 (HJ Sqn6=>n/
(HJ Sqn6=>n/a)

A340HB582S070 Lube Oil Testi ng & Flush in g for J10 -K-070 3A/B/C (J10-U -0736A/B/C) 20 07-Oct-18 29-Oct-18 0 Lube Oil Testi ng & Flush in g for J10 -K-070 3A/B/C (J10-U -0736A/B/C) at A340 (
at A340 (Crew 1&2)

A340HB880S010 Electrical Heat Tracing at A340 82 31-Mar-18 A 30-Oct-18 0 Electrical Heat Tracing at A340

A340HB830S010 Lighting Work at A340 82 14-Jan-17 A 30-Oct-18 29 Lighting Work at A340

A340HB582S60 Assembly/Erection of Compressors (J10-K-0703A/B/C) - 2nd at 20 22-Oct-18 13-Nov-18 0 Assembly/Erection of Compressors (J10-K-0703A/B/C) - 2nd at A340
A340 [A34S10]

A340HB912S010 Insulation for Piping at A340 93 22-Aug-17 A 14-Nov-18* 0 Insulation for Piping at A340

A340HB582S50 Assembly/Erection of Compressors (J10-K-0701A/B/C) - 2nd at 20 27-Oct-18 18-Nov-18 48 Assembly/Erection of Compressors (J10-K-0701A/B/C) - 2nd at A3
A340 [A34S20]

A340HB792S010 Loop Test at A340 113 30-Dec-17 A 04-Dec-18 0 Loop Test at A340

A350 100 17-Feb-17 A 20-Nov-18 12

A350HB782S010 Branch Cable at A350 21 20-May-17 A 20-Aug-18 65 Branch Cable at A350

A350HB860S010 Communication System Installation at A350 30 15-May-17 A 30-Aug-18 29 Communication System Installation at A350

A350HB680S010 Piping Pressure Test at A350 48 08-Jun-17 A 20-Sep-18 12 Piping Pressure Test at A350

A350HB513S120-1 Box Up of Columns / Drums at A350 (12 Nos) 24 01-Sep-18 27-Sep-18 40 Box Up of Columns / Drums at A350 (12 Nos)

A350HB582S40 Lube Oil Testi ng & Flush in g for J10 -K-059 0A (J10-U-0596A) at A350 20 08-Sep-18 30-Sep-18 7 Lube Oil Testi ng & Flush in g for J10 -K-059 0A (J10-U-0596A) at A350 (Crew 3)
(Crew 3)

A350HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A350 61 02-Jan-18 A 06-Oct-18 38 Main Cable & Branch Cabling Te rminati on Works for A350

A350HB582S50 Lube Oil Testi ng & Flush in g for J10 -K-059 0B (J10-U-05 96B) a t A350 20 19-Sep-18 11-Oct-18 7 Lube Oil Testi ng & Flush in g for J10 -K-059 0B (J10-U-05 96B) a t A350 (Crew 3)
(Crew 3)

A350HB582S40-2 Special cleaning for J10-K-0590A/B (J10-U-0596A) at A350 (HJ 7 13-Oct-18 20-Oct-18 7 Special cleaning for J10-K-0590A/B (J10-U-0596A) at A350 (HJ Sqn11=>n/a)
Sqn11=>n/a)

A350HB792S010 Loop Test at A350 76 30-Dec-17 A 22-Oct-18 37 Loop Test at A350

A350HBA20S010 Finish Painting for A/G Piping at A350 81 15-Aug-17 A 29-Oct-18 12 Finish Painting for A/G Piping at A350

A350HB830S010 Lighting Work at A350 82 17-Feb-17 A 30-Oct-18 29 Lighting Work at A350

A350HB582S20 Assembly/Erection of Tail Gas C ompressor (J10-K-05 90A/B) - 2nd a t 20 21-Oct-18 12-Nov-18 7 Assembly/Erection of Tail Gas C ompressor (J10-K-05 90A/B) - 2nd a t A
A350

A350HB582S30 Assembly/Erection of Tail Gas C ompressor (J10-K-05 90B) - 2nd at 20 21-Oct-18 12-Nov-18 7 Assembly/Erection of Tail Gas C ompressor (J10-K-05 90B) - 2nd at A35
A350

A350HB912S010 Insulation for Piping at A350 100 01-Aug-17 A 20-Nov-18* 0 Insulation for Piping at A350

A410 82 02-Jan-18 A 30-Oct-18 41

A410HB513S010-1 Box Up of Columns / Drums at A410 (1 No) 3 30-Aug-18 02-Sep-18 64 Box Up of Columns / Drums at A410 (1 No)

A410HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A410 51 02-Jan-18 A 24-Sep-18 48 Main Cable & Branch Cabling Te rminati on Works for A410

A410HB800S010 Power Energized for PIB-010 at A410 0 10-Oct-18 58 Power Energized for PIB-010 at A410

A410HB792S010 Loop Test at A410 69 15-Jan-18 A 14-Oct-18 44 Loop Test at A410

A410HB830S010 Lighting Work at A410 82 27-Jan-18 A 30-Oct-18 29 Lighting Work at A410

A420 87 25-May-17 A 05-Nov-18 25

A420HB800S020 Documentation of Energization Package for SS-010 31 25-May-17 A 01-Sep-18 26 Documentation of Energization Package for SS-010

A420HB800S010 Power Energized for SS-010 at A420 0 15-Sep-18 15 Power Energized for SS-010 at A420

A420HB814S020 Precomm. of SG and MCC (incl. HP Test) for SS-010 at A420 48 12-Sep-17 A 20-Sep-18 15 Precomm. of SG and MCC (incl. HP Test) for SS-010 at A420

A420HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for A420 58 03-Feb-18 A 02-Oct-18 41 Main Cable & Branch Cabling Te rminati on Works for A420

A420HB817S030 Precomm. of PSA/SCADA for SS-010 at A420 69 07-Jun-18 A 15-Oct-18 25 Precomm. of PSA/SCADA for SS-010 at A420

A420HB792S010 Loop Test at A420 82 30-Dec-17 A 05-Nov-18 25 Loop Test at A420

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 4 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
B000 65 28-Feb-18 A 11-Oct-18 62

B000HB829S010 Motor Solo Run at B000 (43 nos) 4 28-Feb-18 A 31-Jul-18 123 Motor Solo Run at B000 (43 nos)

B000HB829S010-1 Motor Solo Run at B000 (2 nos) (For MV/HV Subject for Permanent 6 04-Oct-18 11-Oct-18 62 Motor Solo Run at B000 (2 nos) (For MV/HV Subject for Permanent Power)
Power)

B100 - Main Pipe Rack 82 15-Jun-17 A 30-Oct-18 63

B100HB680S10 Piping Pressure Test at B100 4 15-Jun-17 A 31-Jul-18 46 Piping Pressure Test at B100

B100HB650S10 Steam Tracing at B100 (to be deleted) 5 01-Aug-18 06-Aug-18 124 Steam Tracing at B100 (to be deleted)

B100HB868S10 Communication System Installation at B100 9 09-Sep-17 A 06-Aug-18 92 Communication System Installation at B100

B100HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for B100 10 13-Jan-18 A 15-Aug-18 91 Main Cable & Branch Cabling Te rminati on Works for B100

B100HB792S10 Loop Test at B100 30 30-Dec-17 A 30-Aug-18 98 Loop Test at B100

B100HB880S10 Electrical Heat Tracing at B100 82 15-Aug-17 A 30-Oct-18 63 Electrical Heat Tracing at B100

B210 37 13-Jan-18 A 08-Sep-18 91

B000HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for B210 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B210

B210HB513S010-1 Box Up of Columns / Drums at B210 (4 Nos) 8 20-Aug-18 28-Aug-18 94 Box Up of Columns / Drums at B210 (4 Nos)

B000HB792S10 Loop Test at B210 36 25-Feb-18 A 08-Sep-18 91 Loop Test at B210

B220 82 01-Aug-17 A 30-Oct-18 64

B000HB860S20 Communication System Installation at B220 9 14-Oct-17 A 06-Aug-18 118 Communication System Installation at B220

B000HB781S70-1 Main Cable & Branch Cabling Te rminati on Works for B220 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B220

B000HBA20S20 Finish Painting for A/G Piping at B220 22 01-Aug-17 A 21-Aug-18 98 Finish Painting for A/G Piping at B220

B220HB513S010-1 Box Up of Columns / Drums at B220 (4 Nos) 8 16-Jul-18 A 26-Aug-18 96 Box Up of Columns / Drums at B220 (4 Nos)

B000HB912S20 Insulation for Piping at B220 30 05-Oct-17 A 30-Aug-18 98 Insulation for Piping at B220

B000HB792S20 Loop Test at B220 34 30-Dec-17 A 05-Sep-18 93 Loop Test at B220

B000HB880S20 Electrical Heat Tracing at B220 82 15-Sep-17 A 30-Oct-18 64 Electrical Heat Tracing at B220

B230 35 30-Dec-17 A 05-Sep-18 93

B000HB781S90-1 Main Cable & Branch Cabling Te rminati on Works for B230 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B230

B230HB513S020-1 Box Up of Columns / Drums at B230 (3 Nos) 6 24-Jul-18 A 28-Aug-18 94 Box Up of Columns / Drums at B230 (3 Nos)

B000HB792S30 Loop Test at B230 34 30-Dec-17 A 05-Sep-18 93 Loop Test at B230

B240 35 13-Jan-18 A 05-Sep-18 93

B000HB781S170-1 Main Cable & Branch Cabling Te rminati on Works for B240 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B240

B000HB792S70 Loop Test at B240 34 14-Jan-18 A 05-Sep-18 93 Loop Test at B240

B310 82 15-Sep-17 A 30-Oct-18 57

B000HB781S110-1 Main Cable & Branch Cabling Te rminati on Works for B310 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B310

B310HB513S010-1 Box Up of Columns / Drums at B310 (4 Nos) 20 03-Jun-18 A 19-Aug-18 102 Box Up of Columns / Drums at B310 (4 Nos)

B000HB792S40 Loop Test at B310 34 30-Dec-17 A 05-Sep-18 93 Loop Test at B310

B000HB880S40 Electrical Heat Tracing at B310 82 15-Sep-17 A 30-Oct-18 57 Electrical Heat Tracing at B310

B320 35 30-Dec-17 A 05-Sep-18 93

B000HB781S130-1 Main Cable & Branch Cabling Te rminati on Works for B320 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B320

B320HB513S020-1 Box Up of Columns / Drums at B320 (4 Nos) 8 22-Jul-18 A 29-Aug-18 93 Box Up of Columns / Drums at B320 (4 Nos)

B000HB792S50 Loop Test at B320 34 30-Dec-17 A 05-Sep-18 93 Loop Test at B320

B330 82 20-Aug-17 A 30-Oct-18 60

B000HB781S150-1 Main Cable & Branch Cabling Te rminati on Works for B330 10 13-Jan-18 A 07-Aug-18 105 Main Cable & Branch Cabling Te rminati on Works for B330

B330HB513S020-1 Box Up of Columns / Drums at B330 (4 Nos) 8 20-Aug-18 28-Aug-18 94 Box Up of Columns / Drums at B330 (4 Nos)

B000HB792S60 Loop Test at B330 34 30-Dec-17 A 05-Sep-18 93 Loop Test at B330

B000HB880S60 Electrical Heat Tracing at B330 82 20-Aug-17 A 30-Oct-18 60 Electrical Heat Tracing at B330

B400 - BLDG Area


Ar (SS 014 & PIB 014) 30 11-Oct-17 A 30-Aug-18 97

B400HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for B400 10 20-Jan-18 A 07-Aug-18 104 Main Cable & Branch Cabling Te rminati on Works for B400

B400HB860S010 Communication System Installation at B400 30 11-Oct-17 A 30-Aug-18 97 Communication System Installation at B400

B410 88 28-Apr-18 A 06-Nov-18 58

B410HB716S010-1 Loop Testing at B410 30 28-Apr-18 A 30-Aug-18 97 Loop Testing at B410

B410HB800S010 Power Energized for PIB-014 at B410 0 06-Nov-18 58 Power Energized for PIB-014 at B410

B420 96 20-Aug-16 A 15-Nov-18 50

B420HB4A0S100 HVAC Installation for SS-014 at B420 5 20-Aug-16 A 01-Aug-18 122 HVAC Installation for SS-014 at B420

B420HB827S020 Megger Te st and High Potentia l Test of Cable (LV & MV) for SS-014 19 03-Aug-17 A 18-Aug-18 59 Megger Te st and High Potentia l Test of Cable (LV & MV) for SS-014 at B420
at B420

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 5 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
B420HB800S020 Documentation of Energization Package for SS-014 31 01-Oct-17 A 01-Sep-18 59 Documentation of Energization Package for SS-014

B420HB814S020 Precomm. of SG and MCC (incl. HP Test) for SS-014 at B420 56 11-Nov-17 A 30-Sep-18 34 Precomm. of SG and MCC (incl. HP Test) for SS-014 at B420

B420HB800S010 Power Energized for SS-014 at B420 0 04-Oct-18 30 Power Energized for SS-014 at B420

B420HB817S030 Precomm. of PSA/SCADA for SS-014 at B420 96 07-Jun-18 A 15-Nov-18 50 Precomm. of PSA/SCADA for SS-014 at B420

C000 68 29-Jan-18 A 14-Oct-18 6

C000HB829S010 Motor Solo Run at C000 (24 nos) (For LV Motors) 17 29-Jan-18 A 15-Aug-18 57 Motor Solo Run at C000 (24 nos) (For LV Motors)

C000HB829S010-1 Motor Solo Run at C000 (4 nos) (For MV/HV Subject for Permanent 12 01-Oct-18 14-Oct-18 1 Motor Solo Run at C000 (4 nos) (For MV/HV Subject for Permanent Power)
Power)

C210 - Isomerization
Isomeriza Area East Area 74 15-Jun-17 A 21-Oct-18 1

C210HB582S20-2 Special cleaning for J11-K-0200 (J11-U-0206) at C210 (DEC-SMP) 4 10-Sep-18 15-Sep-18 1 Special cleaning for J11-K-0200 (J11-U-0206) at C210 (DEC-SMP)

C210HB582S20 Lube Oil Testi ng & Flush in g for J11-K-0200A/B (J11-U-0206) at 20 27-Aug-18 18-Sep-18 1 Lube Oil Testi ng & Flush in g for J11-K-0200A/B (J11-U-0206) at C210 (Crew 3)
C210 (Crew 3)

C210HB680S010 Piping Pressure Test at C 210 48 15-Jun-17 A 22-Sep-18 2 Piping Pressure Test at C 210

C210HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for C210 49 02-Jan-18 A 22-Sep-18 14 Main Cable & Branch Cabling Te rminati on Works for C210

C210HB513S130-1 Box Up of Columns / Drums at C210 (12 Nos) 46 21-May-18 A 22-Sep-18 18 Box Up of Columns / Drums at C210 (12 Nos)

C210HB582S10 Assembly/Erection of H2 Make-Up Compressors (J11-K-0200A/B) - 20 15-Sep-18 07-Oct-18 1 Assembly/Erection of H2 Make-Up Compressors (J11-K-0200A/B) - 2nd at C210
2nd at C210

C210HB792S010 Loop Test at C2 10 72 30-Dec-17 A 21-Oct-18 1 Loop Test at C2 10

C220 - Isomerization
Isomeriza Area West Area 75 10-Jun-17 A 22-Oct-18 0

C220HB680S010 Piping Pressure Test at C 220 48 10-Jun-17 A 22-Sep-18 -6 Piping Pressure Test at C 220

C220HB781S0201 Main Cable & Branch Cabling Te rminati on Works for C220 49 02-Jan-18 A 22-Sep-18 13 Main Cable & Branch Cabling Te rminati on Works for C220

C220HB513S020-1 Box Up of Columns / Drums at C220 (6 Nos) 12 30-Jun-18 A 29-Sep-18 12 Box Up of Columns / Drums at C220 (6 Nos)

C220HBA20S010 Finish Painting for A/G Piping at C220 23 14-Aug-17 A 03-Oct-18 -6 Finish Painting for A/G Piping at C220

C220HB912S010 Insulation for Piping at C220 30 22-Aug-17 A 11-Oct-18* -6 Insulation for Piping at C220

C220HB792S010 Loop Test at C2 20 74 30-Dec-17 A 22-Oct-18 0 Loop Test at C2 20

D000 - PX Area 86 05-Mar-18 A 04-Nov-18 30

D000HB829S010 Motor Solo Run at D000 (123 nos) (For LV Motors) 17 05-Mar-18 A 15-Aug-18 99 Motor Solo Run at D000 (123 nos) (For LV Motors)

D000HB829S010-1 Motor Solo Run at D000 (36 nos) (For MV/HV Subject for 26 06-Oct-18 04-Nov-18 30 Motor Solo Run at D000 (36 nos) (For MV/HV Subject for Permanent Powe
Permanent Power)

D100 - Main Pipe Rack 95 04-Oct-16 A 14-Nov-18 22

D100HB782S010 Branch Cable at D100 9 15-May-17 A 06-Aug-18 82 Branch Cable at D100

D100HB868S010 Communication System Installation at D100 30 16-Sep-17 A 30-Aug-18 34 Communication System Installation at D100

D100HB680S010 Piping Pressure Test at D 100 56 22-Jun-17 A 30-Sep-18 -16 Piping Pressure Test at D 100

D100HBA20S010 Finish Painting for A/G Piping at D100 64 10-Aug-17 A 11-Oct-18 22 Finish Painting for A/G Piping at D100

D100HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D100 69 27-Jan-18 A 15-Oct-18 35 Main Cable & Branch Cabling Te rminati on Works for D100

D100HB792S010 Loop Test at D1 00 83 30-Dec-17 A 30-Oct-18 35 Loop Test at D1 00

D100HB880S010 Electrical Heat Tracing at D100 82 17-Jun-18 A 30-Oct-18 0 Electrical Heat Tracing at D100

D100HB832S010 Lighting work at D100 82 04-Oct-16 A 30-Oct-18 34 Lighting work at D100

D100HB650S010 Steam Tracing at D100 (For D110) 83 26-May-18 A 31-Oct-18 15 Steam Tracing at D100 (For D110)

D100HB900S010 Insulation for Piping at D100 94 05-Oct-17 A 14-Nov-18* 0 Insulation for Piping at D100

D210 82 21-Jun-17 A 30-Oct-18 35

D210HB782S010 Branch Cable at D210 17 29-Oct-17 A 15-Aug-18 74 Branch Cable at D210

D210HB582S10 Lube Oil Testi ng & Flush in g for J12 -K-050 0 (J12-U-050 6) a t D210 20 01-Aug-18 23-Aug-18 1 Lube Oil Testi ng & Flush in g for J12 -K-050 0 (J12-U-050 6) a t D210 (Cre w 3)
(Crew 3)

D210HB582S20 Lube Oil Testi ng & Flush in g for J12 -K-061 3 (J12-U-063 6) a t D210 20 15-Aug-18 06-Sep-18 1 Lube Oil Testi ng & Flush in g for J12 -K-061 3 (J12-U-063 6) a t D210 (Cre w 3)
(Crew 3)

D210HB582S20-2 Special cleaning for J12-K-0613 (J12-U-0636) at D210 (SAACO) 4 08-Sep-18 11-Sep-18 46 Special cleaning for J12-K-0613 (J12-U-0636) at D210 (SAACO)

D210HB582S10-2 Special cleaning for J12-K-0500 (J12-U-0506) at D210 (SAACO) 4 12-Sep-18 16-Sep-18 46 Special cleaning for J12-K-0500 (J12-U-0506) at D210 (SAACO)

D210HB680S010 Piping Pressure Test at D 210 56 21-Jun-17 A 30-Sep-18 3 Piping Pressure Test at D 210

D210HB582S040 Assembly Deheptanizer Overhead Compressor(J12-K-0613) - 2nd 20 12-Sep-18 04-Oct-18 50 Assembly Deheptanizer Overhead Compressor(J12-K-0613) - 2nd at D210
at D210

D210HB513S020-1 Box Up of Columns / Drums at D210 (3 Nos) 6 01-Oct-18 07-Oct-18 51 Box Up of Columns / Drums at D210 (3 Nos)

D210HB582S50 Assembly Recycle Compressor (J12-K-0500) - 2nd at D210 20 17-Sep-18 09-Oct-18 46 Assembly Recycle Compressor (J12-K-0500) - 2nd at D210

D210HBA20S010 Finish Painting for A/G Piping at D210 64 11-Jul-17 A 11-Oct-18 3 Finish Painting for A/G Piping at D210

D210HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D210 69 27-Jan-18 A 15-Oct-18 35 Main Cable & Branch Cabling Te rminati on Works for D210

D210HB912S010 Insulation for Piping at D210 75 16-Aug-17 A 22-Oct-18* 1 Insulation for Piping at D210

D210HB792S010 Loop Test at D2 10 83 30-Dec-17 A 30-Oct-18 35 Loop Test at D2 10

D210HB830S010 Lighting Work at D210 82 29-Jun-17 A 30-Oct-18 34 Lighting Work at D210

D220 92 04-Feb-17 A 11-Nov-18 25

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 6 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
D220HB730S010 Local Instrument Installation at D220 18 21-Jun-17 A 16-Aug-18 70 Local Instrument Installation at D220

D220HB782S010 Branch Cable at D220 21 08-Jun-17 A 20-Aug-18 70 Branch Cable at D220

D220HB860S010 Communication System Installation at D220 30 16-Sep-17 A 30-Aug-18 34 Communication System Installation at D220

D220HB680S010 Piping Pressure Test at D 220 56 20-Jun-17 A 30-Sep-18 -16 Piping Pressure Test at D 220

D220HB513S020-1 Box Up of Columns / Drums at D220 (8 Nos) 16 19-Sep-18 07-Oct-18 51 Box Up of Columns / Drums at D220 (8 Nos)

D220HBA20S010 Finish Painting for A/G Piping at D220 64 10-Jul-17 A 11-Oct-18 -7 Finish Painting for A/G Piping at D220

D220HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D220 69 20-Jan-18 A 15-Oct-18 35 Main Cable & Branch Cabling Te rminati on Works for D220

D220HB650S010 Steam Tracing at D220 (To be deleted) 80 28-Jul-18 28-Oct-18 -21 Steam Tracing at D220 (To be deleted)

D220HB792S010 Loop Test at D2 20 83 30-Dec-17 A 30-Oct-18 35 Loop Test at D2 20

D220HB880S010 Electrical Heat Tracing at D220 82 01-Nov-17 A 30-Oct-18 -26 Electrical Heat Tracing at D220

D220HB830S010 Lighting Work at D220 82 04-Feb-17 A 30-Oct-18 34 Lighting Work at D220

D220HB912S010 Insulation for Piping at D220 90 16-Aug-17 A 11-Nov-18* -26 Insulation for Piping at D220

D230 82 19-Feb-17 A 30-Oct-18 35

D230HB782S010 Branch Cable at D230 8 24-Jul-17 A 05-Aug-18 83 Branch Cable at D230

D230HB730S010 Local Instrument Installation at D230 18 21-Jun-17 A 16-Aug-18 83 Local Instrument Installation at D230

D230HB860S010 Communication System Installation at D230 (NO QTY) 30 28-Jul-18 30-Aug-18 34 Communication System Installation at D230 (NO QTY)

D230HB680S010 Piping Pressure Test at D 230 56 29-Jun-17 A 30-Sep-18 2 Piping Pressure Test at D 230

D230HB513S030-1 Box Up of Columns / Drums at D230 (7 Nos) 14 22-Sep-18 07-Oct-18 51 Box Up of Columns / Drums at D230 (7 Nos)

D230HBA20S010 Finish Painting for A/G Piping at D230 64 15-Jul-17 A 11-Oct-18 5 Finish Painting for A/G Piping at D230

D230HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D230 69 22-Feb-18 A 15-Oct-18 35 Main Cable & Branch Cabling Te rminati on Works for D230

D230HB912S010 Insulation for Piping at D230 78 16-Aug-17 A 25-Oct-18* 0 Insulation for Piping at D230

D230HB792S010 Loop Test at D2 30 83 30-Dec-17 A 30-Oct-18 35 Loop Test at D2 30

D230HB830S010 Lighting Work at D230 82 19-Feb-17 A 30-Oct-18 34 Lighting Work at D230

D240 96 16-Nov-16 A 15-Nov-18 21

D240HB782S010 Branch Cable at D240 17 20-Nov-17 A 15-Aug-18 61 Branch Cable at D240

D240HB623S010 A/G Piping around Equipment at D240 44 16-Nov-16 A 16-Sep-18 3 A/G Piping around Equipment at D240

D240HB680S010 Piping Pressure Test at D 240 57 08-Jul-17 A 01-Oct-18 3 Piping Pressure Test at D 240

D240HB513S020-1 Box Up of Columns / Drums at D240 (5 Nos) 10 27-Sep-18 08-Oct-18 50 Box Up of Columns / Drums at D240 (5 Nos)

D240HB650S010 Steam Tracing at D240 69 15-Feb-18 A 15-Oct-18 14 Steam Tracing at D240

D240HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D240 73 22-Feb-18 A 20-Oct-18 31 Main Cable & Branch Cabling Te rminati on Works for D240

D240HBA20S010 Finish Painting for A/G Piping at D240 76 12-May-18 A 23-Oct-18 3 Finish Painting for A/G Piping at D240

D240HB880S010 Electrical Heat Tracing at D240 (No QTY To Be Deleted) 80 28-Jul-18 28-Oct-18 3 Electrical Heat Tracing at D240 (No QTY To Be Deleted)

D240HB830S010 Lighting Work at D240 82 26-Nov-16 A 30-Oct-18 34 Lighting Work at D240

D240HB792S010 Loop Test at D2 40 88 14-Apr-18 A 05-Nov-18 30 Loop Test at D2 40

D240HB912S010 Insulation for Piping at D240 96 21-Aug-17 A 15-Nov-18* 0 Insulation for Piping at D240

D250 90 22-Oct-16 A 08-Nov-18 27

D250HB782S010 Branch Cable at D250 17 15-Jul-17 A 15-Aug-18 69 Branch Cable at D250

D250HB623S010 A/G Piping around Equipment at D252 45 22-Oct-16 A 17-Sep-18 3 A/G Piping around Equipment at D252

D250HB680S010 Piping Pressure Test at D 250 58 07-Aug-17 A 02-Oct-18 3 Piping Pressure Test at D 250

D250HB513S030-1 Box Up of Columns / Drums at D250 (5 Nos) 10 22-Jul-18 A 09-Oct-18 49 Box Up of Columns / Drums at D250 (5 Nos)

D250HB650S010 Steam Tracing at D250 69 28-Jul-18 15-Oct-18 8 Steam Tracing at D250

D250HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D250 74 17-Feb-18 A 21-Oct-18 30 Main Cable & Branch Cabling Te rminati on Works for D250

D250HBA20S010 Finish Painting for A/G Piping at D250 80 26-May-18 A 28-Oct-18 3 Finish Painting for A/G Piping at D250

D250HB830S010 Lighting Work at D250 82 21-Mar-17 A 30-Oct-18 34 Lighting Work at D250

D250HB792S010 Loop Test at D2 50 88 15-Jan-18 A 05-Nov-18 30 Loop Test at D2 50

D250HB912S010 Insulation for Piping at D250 90 11-Sep-17 A 08-Nov-18* 0 Insulation for Piping at D250

D260 95 12-Oct-16 A 14-Nov-18 22

D260HB782S010 Branch Cable at D260 9 16-Jul-17 A 06-Aug-18 82 Branch Cable at D260

D260HBB00S010 Fire Proofing for Steel Structure at D260 15 12-Jul-17 A 13-Aug-18 75 Fire Proofing for Steel Structure at D260

D260HB623S010 A/G Piping around Equipment at D260 45 12-Oct-16 A 17-Sep-18 11 A/G Piping around Equipment at D260

D260HB680S010 Piping Pressure Test at D 260 58 21-Jun-17 A 02-Oct-18 11 Piping Pressure Test at D 260

D260HB513S010-1 Box Up of Columns / Drums at D260 (2 Nos) 4 03-Oct-18 07-Oct-18 51 Box Up of Columns / Drums at D260 (2 Nos)

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 7 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
D260HB650S010 Steam Tracing at D260 69 18-Dec-17 A 15-Oct-18 0 Steam Tracing at D260

D260HB880S010 Electrical Heat Tracing at D260 (No QTY To Be Deleted) 52 19-Aug-18 17-Oct-18 14 Electrical Heat Tracing at D260 (No QTY To Be Deleted)

D260HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D260 74 20-Jan-18 A 21-Oct-18 30 Main Cable & Branch Cabling Te rminati on Works for D260

D260HBA20S010 Finish Painting for A/G Piping at D260 76 06-Aug-17 A 23-Oct-18 12 Finish Painting for A/G Piping at D260

D260HB830S010 Lighting Work at D260 82 18-Mar-17 A 30-Oct-18 34 Lighting Work at D260

D260HB792S010 Loop Test at D2 60 88 14-Jan-18 A 05-Nov-18 30 Loop Test at D2 60

D260HB912S010 Insulation for Piping at D260 78 16-Aug-18 14-Nov-18* 0 Insulation for Piping at D260

D270 87 26-Sep-16 A 05-Nov-18 30

D270HB782S010 Branch Cable at D270 9 16-Jul-17 A 06-Aug-18 82 Branch Cable at D270

D270HB730S010 Local Instrument Installation at D270 13 20-Jun-17 A 11-Aug-18 82 Local Instrument Installation at D270

D270HB623S010 A/G Piping around Equipment at D270 45 26-Sep-16 A 17-Sep-18 1 A/G Piping around Equipment at D270

D270HB680S010 Piping Pressure Test at D 270 58 15-Jun-17 A 02-Oct-18 1 Piping Pressure Test at D 270

D270HB513S010-1 Box Up of Columns / Drums at D270 (2 Nos) 4 03-Oct-18 07-Oct-18 51 Box Up of Columns / Drums at D270 (2 Nos)

D270HB650S010 Steam Tracing at D270 69 23-Jun-18 A 15-Oct-18 0 Steam Tracing at D270

D270HBA20S010 Finish Painting for A/G Piping at D270 72 09-Aug-17 A 18-Oct-18 0 Finish Painting for A/G Piping at D270

D270HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D270 74 20-Jan-18 A 21-Oct-18 30 Main Cable & Branch Cabling Te rminati on Works for D270

D270HB912S010 Insulation for Piping at D270 80 19-Aug-17 A 28-Oct-18* -1 Insulation for Piping at D270

D270HB830S010 Lighting Work at D270 82 02-May-17 A 30-Oct-18 34 Lighting Work at D270

D270HB792S010 Loop Test at D2 70 88 30-Dec-17 A 05-Nov-18 30 Loop Test at D2 70

D280 109 29-Oct-16 A 01-Dec-18 7

D280HB782S010 Branch Cable at D280 17 19-Jul-17 A 15-Aug-18 73 Branch Cable at D280

D280HB623S010 A/G Piping around Equipment at D280 46 29-Oct-16 A 18-Sep-18 0 A/G Piping around Equipment at D280

D280HB680S010 Piping Pressure Test at D 280 59 10-Sep-17 A 03-Oct-18 0 Piping Pressure Test at D 280

D280HB650S010 Steam Tracing at D280 69 28-Jul-18 15-Oct-18 6 Steam Tracing at D280

D280HB880S010 Electrical Heat Tracing at D280 52 20-Aug-18 18-Oct-18 0 Electrical Heat Tracing at D280

D280HBA20S010 Finish Painting for A/G Piping at D280 72 16-Sep-17 A 18-Oct-18 0 Finish Painting for A/G Piping at D280

D280HB781S020 Main Cable & Branch Cabling Te rminati on Works for D280 73 17-Feb-18 A 20-Oct-18 30 Main Cable & Branch Cabling Te rminati on Works for D280

D280HB830S010 Lighting Work at D280 82 07-Oct-17 A 30-Oct-18 34 Lighting Work at D280

D280HB912S010 Insulation for Piping at D280 41 13-Sep-18 30-Oct-18* 0 Insulation for Piping at D280

D280HB792S010 Loop Test at D2 80 110 28-Jul-18 01-Dec-18 7 Loop Test at D2 80

D310 82 22-Jan-17 A 30-Oct-18 35

D310HB782S010 Branch Cable at D310 9 13-May-17 A 06-Aug-18 82 Branch Cable at D310

D310HB680S010 Piping Pressure Test at D 310 56 13-Jul-17 A 30-Sep-18 0 Piping Pressure Test at D 310

D310HB880S010 Electrical Heat Tracing at D310 60 06-Aug-18 14-Oct-18 4 Electrical Heat Tracing at D310

D310HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D310 69 17-Feb-18 A 15-Oct-18 35 Main Cable & Branch Cabling Te rminati on Works for D310

D310HBA20S010 Finish Painting for A/G Piping at D310 72 06-Aug-17 A 18-Oct-18 3 Finish Painting for A/G Piping at D310

D310HB830S010 Lighting Work at D310 82 22-Jan-17 A 30-Oct-18 34 Lighting Work at D310

D310HB792S010 Loop Test at D3 10 83 30-Dec-17 A 30-Oct-18 35 Loop Test at D3 10

D310HB912S010 Insulation for Piping at D310 82 12-Sep-17 A 30-Oct-18* 0 Insulation for Piping at D310

D320 82 11-Mar-17 A 30-Oct-18 64

D320HB782S010 Branch Cable at D320 9 14-May-17 A 06-Aug-18 82 Branch Cable at D320

D320HB911S010-2 Insulation for Equipment at D320 (J12-C-0120, X.R. Column) 18 28-Jul-18 16-Aug-18 128 Insulation for Equipment at D320 (J12-C-0120, X.R. Column)

D320HB680S010 Piping Pressure Test at D 320 56 17-Jul-17 A 30-Sep-18 0 Piping Pressure Test at D 320

D320HB512S010-1 Box Up of Columns / Drums at D320 (1 No) 12 24-Sep-18 07-Oct-18 51 Box Up of Columns / Drums at D320 (1 No)

D320HB650S010 Steam Tracing at D320 (To be deleted) 60 31-Jul-18 08-Oct-18 9 Steam Tracing at D320 (To be deleted)

D320HBA20S010 Finish Painting for A/G Piping at D320 64 25-Jul-17 A 11-Oct-18 0 Finish Painting for A/G Piping at D320

D320HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D320 69 10-Feb-18 A 15-Oct-18 35 Main Cable & Branch Cabling Te rminati on Works for D320

D320HB912S010 Insulation for Piping at D320 80 09-Oct-17 A 28-Oct-18* -1 Insulation for Piping at D320

D320HB830S010 Lighting Work at D320 82 11-Mar-17 A 30-Oct-18 34 Lighting Work at D320

D320HB792S010 Loop Test at D3 20 83 30-Dec-17 A 30-Oct-18 35 Loop Test at D3 20

D330 85 22-Jun-16 A 03-Nov-18 31

D330HB730S010 Local Instrument Installation at D330 18 19-Jun-17 A 16-Aug-18 72 Local Instrument Installation at D330

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 8 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
D330HB782S010 Branch Cable at D330 18 14-May-17 A 16-Aug-18 72 Branch Cable at D330

D330HB623S010 A/G Piping around Equipment at D330 44 22-Jun-16 A 16-Sep-18 3 A/G Piping around Equipment at D330

D330HB650S010 Steam Tracing at D330 19 10-Sep-18 01-Oct-18 12 Steam Tracing at D330

D330HB680S010 Piping Pressure Test at D 330 57 10-Aug-17 A 01-Oct-18 3 Piping Pressure Test at D 330

D330HB513S020-1 Box Up of Columns / Drums at D330 ( 2 Nos) 4 21-Jun-18 A 06-Oct-18 52 Box Up of Columns / Drums at D330 ( 2 Nos)

D330HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D330 71 05-Apr-18 A 17-Oct-18 32 Main Cable & Branch Cabling Te rminati on Works for D330

D330HBA20S010 Finish Painting for A/G Piping at D330 72 19-Aug-17 A 18-Oct-18 4 Finish Painting for A/G Piping at D330

D330HB830S010 Lighting Work at D330 82 03-Aug-17 A 30-Oct-18 34 Lighting Work at D330

D330HB792S010 Loop Test at D3 30 86 30-Dec-17 A 03-Nov-18 31 Loop Test at D3 30

D330HB912S010 Insulation for Piping at D330 85 12-Sep-17 A 03-Nov-18* 1 Insulation for Piping at D330

D340 87 26-Nov-16 A 05-Nov-18 30

D340HB782S010 Branch Cable at D340 17 13-Jul-17 A 15-Aug-18 74 Branch Cable at D340

D340HB730S010 Local Instrument Installation at D340 18 13-Jun-17 A 16-Aug-18 74 Local Instrument Installation at D340

D340HB860S010 Communication System Installation at D340 30 07-Oct-17 A 30-Aug-18 34 Communication System Installation at D340

D340HB623S010 A/G Piping around Equipment at D340 48 26-Nov-16 A 20-Sep-18 0 A/G Piping around Equipment at D340

D340HB650S010 Steam Tracing at D340 22 11-Sep-18 06-Oct-18 0 Steam Tracing at D340

D340HB680S010 Piping Pressure Test at D 340 61 01-Jul-17 A 06-Oct-18 0 Piping Pressure Test at D 340

D340HB513S020-1 Box Up of Columns / Drums at D340 (3 NOs) 6 07-Oct-18 13-Oct-18 46 Box Up of Columns / Drums at D340 (3 NOs)

D340HBA20S010 Finish Painting for A/G Piping at D340 74 06-Aug-17 A 21-Oct-18 3 Finish Painting for A/G Piping at D340

D340HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D340 74 27-Jan-18 A 21-Oct-18 30 Main Cable & Branch Cabling Te rminati on Works for D340

D340HB830S010 Lighting Work at D340 82 20-Jul-17 A 30-Oct-18 34 Lighting Work at D340

D340HB912S010 Insulation for Piping at D340 86 12-Dec-17 A 05-Nov-18* 0 Insulation for Piping at D340

D340HB792S010 Loop Test at D3 40 88 30-Dec-17 A 05-Nov-18 30 Loop Test at D3 40

D350 94 17-Oct-16 A 13-Nov-18 23

D350HB782S010 Branch Cable at D350 17 24-May-17 A 15-Aug-18 74 Branch Cable at D350

D350HB623S010 A/G Piping around Equipment at D350 48 17-Oct-16 A 20-Sep-18 2 A/G Piping around Equipment at D350

D350HB680S010 Piping Pressure Test at D 350 61 01-Jul-17 A 06-Oct-18 2 Piping Pressure Test at D 350

D350HB513S050-1 Box Up of Columns / Drums at D350 (9 Nos) 18 30-Jun-18 A 13-Oct-18 46 Box Up of Columns / Drums at D350 (9 Nos)

D350HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D350 74 10-Feb-18 A 21-Oct-18 30 Main Cable & Branch Cabling Te rminati on Works for D350

D350HBA20S010 Finish Painting for A/G Piping at D350 78 06-Aug-17 A 25-Oct-18 2 Finish Painting for A/G Piping at D350

D350HB880S010 Electrical Heat Tracing at D350 (No QTY To Be Deleted) 60 21-Aug-18 29-Oct-18 2 Electrical Heat Tracing at D350 (No QTY To Be Deleted)

D350HB830S010 Lighting Work at D350 82 05-Aug-17 A 30-Oct-18 34 Lighting Work at D350

D350HB650S010 Steam Tracing at D350 83 07-Apr-18 A 31-Oct-18 0 Steam Tracing at D350

D350HB792S010 Loop Test at D3 50 88 03-Jan-18 A 05-Nov-18 30 Loop Test at D3 50

D350HB912S010 Insulation for Piping at D350 94 15-Dec-17 A 13-Nov-18* -1 Insulation for Piping at D350

D360 114 23-Jun-17 A 06-Dec-18 3

D360HB521S010-1 Internal Work for Adsorbent Towers (J12-C-0201A) at D360-Bottom 4 27-Mar-18 A 31-Jul-18 0 Internal Work for Adsorbent Towers (J12-C-0201A) at D360-Bottom Part
Part

D360HB521S10-1 Internal Work for Adsorbent Towers (J12-C-0201B) at D360-Bottom 4 27-Mar-18 A 31-Jul-18 0 Internal Work for Adsorbent Towers (J12-C-0201B) at D360-Bottom Part
Part

D360HB782S010 Branch Cable at D360 17 11-Jul-17 A 15-Aug-18 74 Branch Cable at D360

D360HB860S010 Communication System Installation at D360 30 12-Oct-17 A 30-Aug-18 34 Communication System Installation at D360

D360HB730S010 Local Instrument Installation at D360 30 23-Jun-17 A 30-Aug-18 74 Local Instrument Installation at D360

D360HBB00S010 Fire Proofing for Steel Structure at D360 35 28-Jun-18 A 05-Sep-18 75 Fire Proofing for Steel Structure at D360

D360HB680S010 Piping Pressure Test at D 360 56 01-Jul-17 A 30-Sep-18 0 Piping Pressure Test at D 360

D360HBA20S010 Finish Painting for A/G Piping at D360 48 15-Aug-18 09-Oct-18 16 Finish Painting for A/G Piping at D360

D360HB781S020-1 Main Cable & Branch Cabling Te rminati on Works for D360 78 03-Feb-18 A 25-Oct-18 26 Main Cable & Branch Cabling Te rminati on Works for D360

D360HB830S010 Lighting Work at D360 82 01-Aug-17 A 30-Oct-18 34 Lighting Work at D360

D360HB650S010 Steam Tracing at D360 83 07-Apr-18 A 31-Oct-18 4 Steam Tracing at D360

D360HB912S010 Insulation for Piping at D360 94 18-Dec-17 A 13-Nov-18* -1 Insulation for Piping at D360

D360HB521S010-2 Internal Work for Adsorbent Towers (J12-C-0201A) at D360-Tray & 94 01-Aug-18 18-Nov-18 0 Internal Work for Adsorbent Towers (J12-C-0201A) at D360-Tray &
Catalyst Works

D360HB521S10-2 Internal Work for Adsorbent Towers (J12-C-0201B) at D360-Tray & 94 01-Aug-18 18-Nov-18 0 Internal Work for Adsorbent Towers (J12-C-0201B) at D360-Tray &
Catalyst Works

D360HB792S010 Loop Test at D3 60 103 30-Dec-17 A 22-Nov-18 15 Loop Test at D3 60

D360HB521S010 Internal Work for Adsorbent Towers (J12-C-0201A) at D360 - LOE 110 27-Mar-18 A 02-Dec-18 0

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 9 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort


Jazan Refinery and Terminal Project - EPC#12 Detailed Work Schedule Rev. 00H Cut Off :27-Jul-18

Activity ID Activity Name Remaining Start Finish Total Float


Duration 2018 2019
Jul Aug Sep Oct Nov Dec Jan Feb Mar
D360HB521S10 Internal Work for Adsorbent Towers (J12-C-0201B) at D360 - LOE 110 27-Mar-18 A 02-Dec-18 0

D360HB521S010-3 Internal Work for Adsorbent Towers (J12-C-0201A) at D360-Top Part 12 19-Nov-18 02-Dec-18 0 Internal Work for Adsorbent Towers (J12-C-0201A) at D36

D360HB521S10-3 Internal Work for Adsorbent Towers (J12-C-0201B) at D360-Top Part 12 19-Nov-18 02-Dec-18 0 Internal Work for Adsorbent Towers (J12-C-0201B) at D36

D360HB513S010-1 Box Up of Columns / Drums at D360 (3 Nos) 18 17-Nov-18 06-Dec-18 0 Box Up of Columns / Drums at D360 (3 Nos)

D370 94 29-Oct-16 A 13-Nov-18 22

D370HB782S010 Branch Cable at D370 17 28-Jun-17 A 15-Aug-18 60 Branch Cable at D370

D370HB782S010-1 Main Cable & Branch Cabling Te rminati on Works for D370 31 10-Feb-18 A 01-Sep-18 59 Main Cable & Branch Cabling Te rminati on Works for D370

D370HB623S010 A/G Piping around Equipment at D370 48 29-Oct-16 A 20-Sep-18 5 A/G Piping around Equipment at D370

D370HB680S010 Piping Pressure Test at D 370 61 15-Jun-17 A 06-Oct-18 5 Piping Pressure Test at D 370

D370HB650S010 Steam Tracing at D370 42 19-Aug-18 06-Oct-18 20 Steam Tracing at D370

D370HB513S020-1 Box Up of Columns / Drums at D370 (5 Nos.) 10 07-Oct-18 17-Oct-18 42 Box Up of Columns / Drums at D370 (5 Nos.)

D370HBA20S010 Finish Painting for A/G Piping at D370 78 16-Jul-17 A 25-Oct-18 5 Finish Painting for A/G Piping at D370

D370HB830S010 Lighting Work at D370 82 17-Apr-17 A 30-Oct-18 34 Lighting Work at D370

D370HB880S010 Electrical Heat Tracing at D370 82 07-Sep-17 A 30-Oct-18 1 Electrical Heat Tracing at D370

D370HB792S010 Loop Test at D3 70 88 14-Apr-18 A 05-Nov-18 29 Loop Test at D3 70

D370HB912S010 Insulation for Piping at D370 94 22-Aug-17 A 13-Nov-18* -1 Insulation for Piping at D370

PRE-COMMISSIONING / COMMISSIONING
PRE-COMMISS 117 08-Apr-18 A 10-Dec-18 11

A000 71 31-Aug-18 20-Nov-18 0

A000J0P00 Leak Te st for Process System_J1 0 71 31-Aug-18 20-Nov-18 0 Leak Te st for Process System_J1 0

A100 - Main Pipe Rack 19 12-Jul-18 A 19-Aug-18 45

A100HB680S010-1 Chemical Cleaning of HPC / MPC / BFW Piping at A000 (Crew 19 12-Jul-18 A 19-Aug-18 45 Chemical Cleaning of HPC / MPC / BFW Piping at A000 (Crew 3=>CRew 2)
3=>CRew 2)

A210 6 16-Aug-18 22-Aug-18 54

A210HB680S010-1 Chemical Cleaning for J10-U-0931 / J10-U-0216A/B at A210 (Crew 6 16-Aug-18 22-Aug-18 54 Chemical Cleaning for J10-U-0931 / J10-U-0216A/B at A210 (Crew 3=>Crew 3)
3=>Crew 3)

A230 6 02-Aug-18 08-Aug-18 54

A230HB680S010-1 Chemical Cleaning for J10-U-0932 at A (Crew 2=>Crew 3) 6 02-Aug-18 08-Aug-18 54 Chemical Cleaning for J10-U-0932 at A (Crew 2=>Crew 3)

A320 6 30-Aug-18 05-Sep-18 38

A320HB680S010-1 Chemical Cleaning Refrigerant Pping at A320 (Crew 3=>Crew 1) 6 30-Aug-18 05-Sep-18 38 Chemical Cleaning Refrigerant Pping at A320 (Crew 3=>Crew 1)

A340 6 09-Aug-18 15-Aug-18 54

A340HB680S010-1 Chemical Cleaning for J10-U-0933 at A (Crew 2 => Crew 3) 6 09-Aug-18 15-Aug-18 54 Chemical Cleaning for J10-U-0933 at A (Crew 2 => Crew 3)

B000 44 25-Aug-18 13-Oct-18 61

B000J1P10 Leak Te st for Process System_J1 4 44 25-Aug-18 13-Oct-18 61 Leak Te st for Process System_J1 4

C000 36 03-Sep-18 14-Oct-18 7

C000J0P10 Leak Te st for Process System_J11 36 03-Sep-18 14-Oct-18 7 Leak Te st for Process System_J11

D000 - PX Area 62 30-Sep-18 10-Dec-18 0

D000J1P00 Leak Te st for Process System_J1 2 62 30-Sep-18 10-Dec-18 0 Leak Te st for Process System_J1 2

D100 - Main Pipe Rack 18 20-Aug-18 09-Sep-18 45

D100HB680S010-1 Chemical Cleaning of HPC / MPC / BFW Piping at D000 (Crew 18 20-Aug-18 09-Sep-18 45 Chemical Cleaning of HPC / MPC / BFW Piping at D000 (Crew 3=>Crew 2)
3=>Crew 2)

D210 6 30-Aug-18 05-Sep-18 81

D210HB680S010-1 Chemical Cleaning of Chilling Package Piping at D210 (Crew 6 30-Aug-18 05-Sep-18 81 Chemical Cleaning of Chilling Package Piping at D210 (Crew 1=>Crew 3)
1=>Crew 3)

D350 6 23-Aug-18 29-Aug-18 54

D350HB680S010-1 Chemical Cleaning for J12-U-0931 at D350 (Crew 1=>Crew 3) 6 23-Aug-18 29-Aug-18 54 Chemical Cleaning for J12-U-0931 at D350 (Crew 1=>Crew 3)

D360 29 08-Apr-18 A 29-Aug-18 38

D360HB680S030-1 Chemical Cleaning at D360 Adsorbent - Loop 5,6 (Crew 1) 13 08-Apr-18 A 11-Aug-18 38 Chemical Cleaning at D360 Adsorbent - Loop 5,6 (Crew 1)

D360HB680S030-2 Chemical Cleaning at D360 Adsorbent Tower Loop 3,4 (Crew 1) 16 12-Aug-18 29-Aug-18 38 Chemical Cleaning at D360 Adsorbent Tower Loop 3,4 (Crew 1)

Milestone Remaining Work R_00H_Jun 18-MS Remaining Level of Effort Page 10 of 10

Actual Work Critical Remaining Work R_00H_Jun 18 Actual Level of Effort