PONDASI BATU KALI Batu Kosong

336.8 m3 125.87 m3
PASIR 0.52 175.136 m3 PASIR 0.432
BATU 1.2 404.16 M3 BATU 1
SEMEN 142 47825.6 956.512 zak

Type 38 Type 38
47.85 20.51
PASIR 0.52 24.882 m3 PASIR 0.432
BATU 1.2 57.42 M3 BATU 1
SEMEN 142 6794.7 135.894 zak
Type 45 Type 45
89.53 29.84
PASIR 0.52 46.5556 m3 PASIR 0.432
BATU 1.2 107.436 M3 BATU 1
SEMEN 142 12713.26 254.2652 zak
Barak Barak
199.42 75.52
PASIR 0.52 103.6984 m3 PASIR 0.432
BATU 1.2 239.304 M3 BATU 1
SEMEN 142 28317.64 566.3528 zak
PASIR URUG
51.79 m3
54.37584 m3 PASIR 1.2 62.148 m3
125.87 M3

Type 38
27.34
8.86032 m3 PASIR 1.2 32.808 m3
20.51 M3

Type 45
9.95
12.89088 m3 PASIR 1.2 11.94 m3
29.84 M3

Barak
14.5
32.62464 m3 PASIR 1.2 17.4 m3
75.52 M3
TOTAL TYPE 38 PONDASI +PASIR URUG
PASIR 57.69 m3
SEMEN 135.894 zak
BATU 77.93 m3

TOTAL TYPE 45 PONDASI +PASIR URUG


PASIR 58.4956 m3
SEMEN 254.2652 zak
BATU 107.436 m3