Beton 2 (NR)
Beton 2 (NR)
0689655
b= 6.2 m = 620 cm
c= 4m= 400 cm
d= 4m= 400 cm
f'c = 27 mpa
fy = 240 mpa
Fungsi Bangunan = 250 Pertokoan
Balok X = 44.28571 h= 50 b= 25
Balok Y = 41.42857 h= 50 b= 25
ln1= 595 cm
ln2= 555 cm
β= 1.0720720721
Menghitung Nilai α 95
α1 = … Be=bw+2hw
15
95 cm
Be=bw+8hf
145 cm 35
17.5
Y= 15312.5 + 60562.5 25
2300
Y= 32.989130435 cm
Ib = 89322.916667 + 209924 + 26718.75 + 128900.7
lb = 454866.39493 cm4
Ip = 163125 cm4
α1 = Ib = 2.788453
Ip
α2 = … Be=bw+2hw 95
95 cm 7.5
15
Be=bw+8hf
145 cm
35
17.5
25
Y= 15312.5 + 60562.5
2300
Y= 32.989130435 cm
Ib = 89322.916667 + 209924 + 26718.75 + 128900.7
lb = 454866.39493 cm4
Ip = 174375 cm4
α2 = Ib = 2.608553
Ip
α3 = … be= bw+hw 60
60 cm 7.5
15
be= bw+4hf
85 cm
35
17.5
25
Y= 15312.5 + 38250
1775
Y= 30.176056338 cm
Ib = 89322.916667 + 140597.1 + 16875 + 136691.6
lb = 383486.64906 cm4
Ip = 81562.5 cm4
α3 = Ib = 4.701752
Ip
α4 = … be= bw+hw 60
60 cm 7.5
15
be= bw+4hf
85 cm
35
17.5
25
Y= 15312.5 + 38250
1775
Y= 30.176056338 cm
Ib = 89322.916667 + 140597.1 + 16875 + 136691.6
lb = 383486.64906 cm4
Ip = 87187.5 cm4
α4 = Ib = 4.398413
Ip
13 cm > 9 cm OK
7.5
50
50
50
50
cm
50 b= 25
50 b= 25
Arah x 25 / 50 cm = 0.25 / 0.5 m
Arah y 25 / 50 cm = 0.25 / 0.5 m
h plat = 15 cm = 0.15 m = 150 mm
Wc = 2400 kg/m3
Berat Pas. Bata = 250 kg/m2
Pembebanan :
Arah X
ln = 595 cm = 5.95 m
H= 350 cm = 3.5 m
Tinjauan 1 L= 5.8 m
BS Balok = 210 kg/m
BS Pelat = 2088 kg/m
BS Dinding = 875 kg/m
q= 3173 kg/m Mo = 14041.51656 kgm
Arah Y
ln = 555 cm = 5.55 m
H= 350 cm = 3.5 m
Tinjauan 2 L= 6.2 m
BS Balok = 210 kg/m
BS Pelat = 2232 kg/m
BS Dinding = 875 kg/m
q= 3317 kg/m Mo = 12771.48656 kgm
Tinjauan 3 L= 5.8 m
BS Balok = 210 kg/m
BS Pelat = 2088 kg/m
BS Dinding = 0 kg/m
q= 2298 kg/m Mo = 10169.36813 kgm
Arah Y
ln = 555 cm = 5.55 m
H= 350 cm = 3.5 m
Tinjauan 4 L= 6.2 m
BS Balok = 210 kg/m
BS Pelat = 2232 kg/m
BS Dinding = 0 kg/m
q= 2442 kg/m Mo = 9402.463125 kgm
Arah Y
ln = 555 cm = 5.55 m
H= 350 cm = 3.5 m
4
5.8 5.8
5.8 3 1 1 3 5.8
2 25/50
5.8 25/50 5.8
5
5.8 5.8
Bid. Momen
Arah X
a cd fg ij
b e h k
MA = -4186.56 kgm
MB = 14914.61 kgm
MC = -19624.5 kgm
MD = -20028.2 kgm
ME = 10784.4 kgm
MF = -20028.2 kgm
MG = -20028.2 kgm
MH = 10784.4 kgm
MI = -20028.2 kgm
MJ = -19624.5 kgm
MK = 14914.61 kgm
ML = -4186.56 kgm
Arah Y
a cd fg ij
b e h k
MA = -3883.09 kgm
MB = 13833.5 kgm
MC = -18202 kgm
MD = -18402.9 kgm
ME = 9909.241 kgm
MF = -18402.9 kgm
MG = -18402.9 kgm
MH = 9909.241 kgm
MI = -18402.9 kgm
MJ = -9464.84 kgm
MK = 7193.277 kgm
ML = 2019.165 kgm
l
26165.98775
l
12619.78425
Dimensi Kolom Arah x 25
Arah y 25
Tinggi Bangunan =
2.9 Berat Pas. Bata =
25/50 h plat =
Wc =
25/50 2.9 W. Finishing =
Fungsi Bangunan =
F'c = 27
3.1 3.1
PLl = 8990 kg
Pu = 47937.92 kg
Direncanakan 10 Lantai
Pu = 479379.2 kg
P A= 177.5479 CM2
α=
A
Direncanakan b = h
A = bh = b2 = 13.32471 = 20
min = 20 cm Diambil = 40 cm
b/h 40 / 40
/ 50 cm = 0.25 / 0.5 m
/ 50 cm = 0.25 / 0.5 m
4m= 400 cm
250 kg/m2
15 cm 150 mm 0.15 m
2400 kg/m3
100 kg/m2
Pertokoan 250 kg/m2
mpa = 2700 kg/cm2