Professional Documents
Culture Documents
Landfill Operations
A. Landfill Equipment
The most common types of heavy landfill equipment and primary tasks
associated with each are waste pushing and placement, waste compaction and
Waste pushing and placement are the initial steps associated with
construction of any landfill cell and require that the piece of equipment have
a blade or broad bucket, and that it maintain a high level of traction under a
landfill equipment used for waste pushing and placement are dozers, track
other pieces of equipment for this task because they also work well for waste
functions: to spread the waste evenly in layers over the landfill, and to
compact waste to reduce its volume and help stabilize the landfill. Proper
landfill compactor to shred, tear and press together various items in the
higher the compaction rate, the more trash the landfill can receive and
store. This will also reduce landslides, cave-ins and minimize the risk of
explosions of landfill gas. This task also involves the use of a blade to trim
off high areas and fill low areas at the surface of the compacted waste.
Specially equipped dozers and compactors are best suited to this task
Table 2.1. Waste Handling Capacities for Different Sizes and Types of
Landfill Equipment
MACHINE WEIGHT Practical Capacity*
MACHINE TYPE
(lbs) (tons/day)
Track Loader <20,000 Up to 20
Track Loader 25,000 Up to 50
Track Loader 33,000 Up to 130
Track Loader 45,000 Up to 175
Dozer 30,000 Up to 100
Dozer 40,000 Up to 125
Dozer 50,000 Up to 175
Dozer 80,000 Up to 250
Dozer 110,000 Up to 400
Compactor 32,000 Up to 100
Compactor 45,000 Up to 250
Compactor 70,000 Up to 400
Compactor 90,000 Up to 600
*Note that waste handling capacity will vary depending on waste type(s), speed of the machine,
push distance, wheel and track design, machine weight, lift thickness, operator skill and
numerous other factors.
3. Waste Covering
Waste covering is the final step of cell construction and can involve a
and compaction. For many landfills, the process of excavating and hauling
cover material to a stockpile near the active fill area or trench is performed on
commonly used for excavating and hauling cover material include dozers,
hoes, loaders, scrapers and trucks. Once the cover material has been
stockpiled near the active area, it can typically be transported, placed and
compacted by the same equipment used for the two earlier steps of cell
to the active disposal area to save time and reduce operating costs.
B. Filling Sequences
identified land. Landfill land needs to be secured and engineered in such way so as
methods practiced for the disposal of solid wastes are shown. (Lokesh, M., 2013)
layer of soil as shown in Figure 1. This method is suitable only for small
Figure 2.1. Excavated Cell or Trench Method (Source: Worrell, W., 2002)
which is not only to difficult to control but will also pollute ground water table.
Used where natural or artificial depressions exist and these are used for
land filling. Depends on the geometry of the site, hydrology and geology of
the site, and access to site. The normal practice is to place such that water does
C. Daily Cover
At the end of each working day, daily cover for landfill, are used to cover
compacted solid waste in a sanitary landfill. The soil material obtained must be
suitable for plants, must not have excess sodium, salts, or lime and should not be
too acid. Additionally, after soil material has been removed, the soil material
remaining in the borrow area must be thick enough over bedrock, a cemented pan,
Agriculture, 2016) Materials used as daily cover include soil, compost, incinerator
ash, foam, and tarps (U.S. Environmental Protection Agency, 2014). The key
1. Minimize windblown-litter
2. Control odours
D. Monitoring
plan for a landfill site. It provides operators with information to assess the effect
of the landfill on the surrounding environment and assists in ensuring that the
waste;
licence;
operating as designed;
waste body;
programs;
to assist in an investigation in the event of a trigger level or
There are three key phases of monitoring at a landfill and these are
Table 2.3. Key Phases of Monitoring At a Landfill (Source: Campbell, R., 2003)
1. Monitoring Requirements
a. Temperature Monitoring
confirm that the fire has been extinguished. In Table 2.4, the relation of
2. Worrell, W. A., Vesilind, P. 2002. Solid Waste Engineering. 2nd Edition. Cengage Learning.
3. Holding Tank Sewage System. Northeast Tri County Health District. 2007
6. Lokesh M. 2013. Landfilling Methods for Urban Waste Disposal. Waste Management.
Agency, Ireland.
9. Greedy, D. 2010. Landfill Operational Guidelines. 2nd Edition. ISWA Working Group for
Landfill.