ﺍﻟﻛﻭﺩ ﺍﻟﻧﺷﺎﻁ ﺍﻟﻣﻭﺍﺭﺩ ﺍﻟﻣﺧﻁﻁﺔ ﺭﺟﻝ ﺳﺎﻋﺔ /ﺍﻟﻭﺣﺩﺓ ﺍﻟﻣﻌﺩﻝ ﺍﻟﻳﻭﻣﻰ ﺍﻟﻭﺣﺩﺓ
10010010 ﺃﻋﻣﺎﻝ ﺍﻟﺣﻔﺭ ﻭﺍﻟﺗﺳﻭﻳﺔ
ﺍﻟﻌﻣﺎﻟﺔ ﻋﺩﺩ 1ﻣﺳﺎﺡ 1 +ﻡ .ﻣﺳﺎﺡ 4 +ﻋﺎﻣﻝ ﻋﺎﺩﻯ
100100101 ﺗﺭﺑﺔ ﺭﻣﻠﻳﺔ /ﻁﻳﻧﻳﺔ ﻡ2 700 0.11
ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﻟﻭﺩﺭ 2 +ﻗﻼﺏ 1 +ﺟﺭﻳﺩﺭ
10010020 ﻁﺑﻘﺔ ﺃﺳﺎﺱ ﺃﻭﻟﻰ /ﺛﺎﻧﻳﺔ
ﺍﻟﻌﻣﺎﻟﺔ ﻁﺑﻘﺔ ﺃﺳﺎﺱ ) ﺳﻣﻙ 25ﺳﻡ ( ﻋﺩﺩ 1ﻣﺳﺎﺡ 1 +ﻡ .ﻣﺳﺎﺡ 4 +ﻋﺎﻣﻝ ﻋﺎﺩﻯ
100100201 ﻡ2 550 0.15
) ﻣﻭﺭﺩﺓ ﻟﻠﻣﻭﻗﻊ ( ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﻟﻭﺩﺭ 1 +ﺟﺭﻳﺩﺭ 1 +ﻫﺭﺍﺱ 1 +ﺳﻳﺎﺭﺓ ﻣﻳﺎﻩ
10010030 ﻁﺑﻘﺔ ﻣﻛﺩﺍﻡ
ﺍﻟﻌﻣﺎﻟﺔ ﻋﺩﺩ 1ﻣﺳﺎﺡ 1 +ﻡ .ﻣﺳﺎﺡ 4 +ﻋﺎﻣﻝ ﻋﺎﺩﻯ
100100301 ﻁﺑﻘﺔ ﻣﻛﺩﺍﻡ ) ﺳﻣﻙ 25ﺳﻡ ( ﻡ2 500 0.14
ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﺟﺭﻳﺩﺭ 1 +ﻟﻭﺩﺭ 1 +ﻫﺭﺍﺱ
10010040 MCO ﻁﺑﻘﺔ
ﺍﻟﻌﻣﺎﻟﺔ ﻋﺩﺩ 2ﻋﺎﻣﻝ
100100401 ﺭﺵ ﻁﺑﻘﺔ MCO ﻡ2 1000 0.02
ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﺳﻳﺎﺭﺓ ﺭﺵ MCO
10010050 ﻁﺑﻘﺔ ﺃﺳﻔﻠﺕ ﺭﺍﺑﻁﺔ
ﻋﺩﺩ 1ﻣﺳﺎﺡ 1 +ﻡ .ﻣﺳﺎﺡ 4 +ﻋﺎﻣﻝ ﺃﺳﻔﻠﺕ 5 +ﻋﺎﻣﻝ
ﺍﻟﻌﻣﺎﻟﺔ
100100501 ﻁﺑﻘﺔ ﺃﺳﻔﻠﺕ ﺳﻣﻙ 6ﺳﻡ ﻣﺣﻁﺔ ﺃﺳﻔﻠﺕ ﻡ2 1000 0.14
ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﻓﻧﺷﺭ 4 +ﻗﻼﺏ 1 +ﻫﺭﺍﺱ
10010060 RC ﻁﺑﻘﺔ
ﺍﻟﻌﻣﺎﻟﺔ ﻋﺩﺩ 2ﻋﺎﻣﻝ
100100601 ﻁﺑﻘﺔ RC ﻡ2 1000 0.02
ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﺳﻳﺎﺭﺓ ﺭﺵ RC
10010070 ﻁﺑﻘﺔ ﺃﺳﻔﻠﺕ ﺳﻁﺣﻳﺔ
ﻋﺩﺩ 1ﻣﺳﺎﺡ 1 +ﻡ .ﻣﺳﺎﺡ 4 +ﻋﺎﻣﻝ ﺃﺳﻔﻠﺕ 5 +ﻋﺎﻣﻝ
ﺍﻟﻌﻣﺎﻟﺔ
100100701 ﻁﺑﻘﺔ ﺃﺳﻔﻠﺕ ﺳﻣﻙ 4ﺳﻡ ﻣﺣﻁﺔ ﺃﺳﻔﻠﺕ ﻡ2 1200 0.12
ﺍﻟﻣﻌﺩﺍﺕ ﻋﺩﺩ 1ﻓﻧﺷﺭ 4 +ﻗﻼﺏ 2 +ﻫﺭﺍﺱ
ﻣﻼﺣﻅﺎﺕ ﻋﺎﻣﺔ
* ﺗﻡ ﺇﺣﺗﺳﺎﺏ ﻋﺩﺩ ﺳﺎﻋﺎﺕ ﺍﻟﻌﻣﻝ ﺍﻟﻳﻭﻣﻳﺔ 8ﺳﺎﻋﺎﺕ /ﻳﻭﻡ .
* ﺃﻋﻣﺎﻝ ﺍﻟﺣﻔﺭ ﻭﺍﻟﺗﺳﻭﻳﺔ ﻋﺎﻟﻳﻪ ﺗﺣﺗﺳﺏ ﻣﻥ ﺍﻟﻣﻧﺳﻭﺏ ﺍﻟﻧﻬﺎﺋﻰ ﺍﻟﻣﺧﻁﻁ ﺗﻧﻔﻳﺫ ﺍﻟﻁﺭﻳﻖ ﻋﻠﻳﻪ ) ﻣﻥ ﻣﻧﺳﻭﺏ ﺍﻟﺻﻔﺭ ﻟﻠﻁﺭﻳﻖ ( .
* ﺗﻡ ﺇﺣﺗﺳﺎﺏ ﺍﻟﻣﻌﺩﺓ = ﺳﺎﺋﻖ ) ﺿﻣﻥ ﻋﺩﺩ ﺳﺎﻋﺎﺕ ﺍﻟﻌﻣﻝ ( .
0.032 1000 m2 ﻋ ﺩﺩ 1ﻏﻼﻳ ﺔ 2+ﻋﺎﻣﻝ 1+ﻣﺳ ﺎﻋﺩ ﺃﻋﻣﺎﻝ ﺍﻟﻁﺭﻕ ﻁﺑﻘﺔ M25
ﻁﺑﻘﺔ ﺃﺳ ﻔﻠﺕ ﺳﻣﻙ 5ﺳﻡ 0.11 1500:3000 ﻋ ﺩﺩ 1ﻓﻧﺷﺭ+ﻫﺭﺍﺱ4+ﻗﻼﺏ+ﻣﺳﺎﺡ+ﻣﺳﺎﻋﺩ ﺃﻋﻣﺎﻝ ﺍﻟﻁﺭﻕ ﻁﺑﻘﺔ ﺭﺍﺑﻁﺔ
0.032 1000 M2 ﻏﻼﻳﺔ 2 +ﻋﺎﻣ ﻝ +ﻣﺳﺎﻋﺩ ﺃﻋﻣﺎﻝ ﺍﻟﻁﺭﻕ ﻁﺑﻘﺔ RC2
ﻁﺑﻘﺔ ﺃﺳ ﻔﻠﺕ ﺳﻣﻙ 4ﺳﻡ 0.1 700 m3 ﻓﻧﺷﺭ+ﻫﺭﺍﺱ 4+ﻗﻼﺏ+ﻣﺳﺎﺡ2+ﻣﺳﺎﻋﺩ ﺃﻋﻣﺎﻝ ﺍﻟﻁﺭﻕ ﻁﺑﻘﺔ ﺳﻁﺧﻳﺔ