Professional Documents
Culture Documents
2nd Scheme Estimates
2nd Scheme Estimates
Sheet No.: 1 of 4
Date: 21/07/2018
No. of Piers : No. of Abuts :
Project Title : Proposed Container Offices
Limits :
Location : Port Harbour, Manila City Exceptions :
Appropiate Act : No. of Length :
Amount Allotment: Road bed Width :
Section : Pavement of Width :
Appropriation : Bridge width :
Character of Terrain : Desirable starting date :
No. of Working days to complete :
Prepared by:
SERKNIGHT S. BENOYA
Technical Staff
General Services Division
BUREAU OF CUSTOMS
GENERAL SERVICES DIVISION
BUILDING AND MAINTENANCE SECTION
OCOM Bldg. Port Area, Manila
C STRUCTURAL WORKS
a. footing column 2.40 Cu. M. 2,645.00 6,348.00
Containers Vans 1.00 pcs 85,000.00 85,000.00
91,348.00 91,348.00
D ARCHITECTURAL WORKS
i. Ceiling 27.97 Sq. m. 250.00 6,992.50
iii. Engineered Wood (Flooring) 27.00 Sq. m. 450.00 12,150.00
v. Carpentry (Wall&Cabinetry) 1.00 lot 20,000.00 20,000.00
vi. Sashworks/door installations 2.00 sets 2,500.00 5,000.00
44,142.50 15,449.88 59,592.38
E PAINTING WORKS
ii. Exterior wall painting 85.47 Sq. m. 45.00 3,846.15
iii. Interior wall painting 43.00 Sq. m. 110.00 4,730.00
8,576.15 3,001.65 11,577.80
F GLASS AND GLAZING
i. Windows 2.00 sets 5,500.00 11,000.00
ii. Doors 2.00 sets 1,200.00 2,400.00
13,400.00 4,690.00 18,090.00
G ROOF FRAMING & ROOFING
Roof GI Sheets, gauge 22 12.00 sheet 320.00 3,840.00
iii. Gutter, Downspout, Eaves and
6.90 Sq. m. 750.00 5,175.00
Ridgeroll
9,015.00 3,155.25 12,170.25
I INSULATION
27.97 Sq. m. 50.00 1,398.50
1,398.50 489.48 1,887.98
J WATERPROOFING
6.00 Sq. m. 350.00 2,100.00
2,100.00 735.00 2,835.00
K PLUMBING/SANITARY WORKS
iii. Rain water disposal system/storm
1.00 Lot 5,000.00 5,000.00
drain
5,000.00 1,750.00 6,750.00
L ELECTRICAL WORKS
1.00 Lot 10,000.00 10,000.00
10,000.00 3,500.00 13,500.00
M MECHANICAL WORKS
i. Exhaust fans 1.00 units 750.00 750.00
i. Fire Protection 27.97 Sq. m. 50.00 1,398.50
2,148.50 751.98 2,900.48
GRAND TOTAL: 223,991.96
Direct Cost
Material Cost 188,208.65
Labor Cost 33,901.23
Mobilization 1,882.09
Prepared by: Total Direct cost 223,991.96
Indirect Cost
SERKNIGHT S. BENOYA OCM (15% of DC) 33,598.79
Technical Assistant Contractors Profit (10% of DC) 22,399.20
General Services Division Total Indirect Cost 55,997.99
Tax (5%) 13,999.50
TOTAL PROJECT
293,989.45