Professional Documents
Culture Documents
Long Intl Construction Claims Analysis Checklist PDF
Long Intl Construction Claims Analysis Checklist PDF
and
Rod C. Carter, CCP, PSP
Copyright © 2017 Long International, Inc.
L ONG INTERNATIONAL
Long International, Inc. • 5265 Skytrail Drive • Littleton, Colorado 80123-1566 USA • Telephone: (303) 972-2443 • Fax: (303) 200-7180 • www.long-intl.com
Construction Claims Analysis Checklist
Richard J. Long, P.E. and Rod C. Carter, CCP, PSP
Table of Contents
The preparation and analysis of claims on engineering, procurement, and construction (EPC)
projects can be a complex undertaking. Multiple engineering, construction, project management,
and construction management experts and legal professionals may be required to either prepare or
defend against claims, depending on the nature of the issues that comprise the claim. The types of
claims and counterclaims that may arise during EPC projects are also diverse, and can include, but
are not limited to, one or more of the following:
Delay claims, both by the contractor for extended overhead costs and by the
owner for liquidated or actual damages
Disruption/Loss of Productivity claims
Acceleration claims
Differing Site Conditions claims
Changes in Scope claims, including Cardinal Change claims
Constructive Changes claims
Defective and Deficient Contract Documents claims
Termination/Suspension claims
Variation in Quantities claims
Gross Negligence/Willful Misconduct claims
Lost Profits claims
Misrepresentation claims
Defective Work claims
Failure to Perform to a Standard of Care claims
Bad Weather claims
Impossibility of Performance claims
Unjust Enrichment claims
Superior Knowledge claims
Breaches of Implied Warranties claims
This article sets forth the basic information and tasks in performing a claims analysis, whether one
is preparing a claim or defending against one. The scope, tasks, and level of detail of the analysis,
however, is dependent on the settlement objectives (change order negotiation, negotiated
settlement of a formal claim, mediation, or expert report for arbitration or litigation), as well as the
monetary risk involved, i.e., the cost of the claims analysis and preparation/defense must be cost
effective compared to the value of the claim. Therefore, not all of the following tasks may be
appropriate, justified, or necessary. Although this list is extensive, it is not meant to be
all-inclusive, and depending on the specific claim issues and the schedule and quantum analyses
utilized, other tasks may be appropriate.
2. Obtain and review the contract terms and conditions, change management
procedure, cost and schedule control procedures, and other contract
documents that may affect the analysis of the claims.
3. Identify the law which governs the contract. Seek legal guidance for any
contractual issues that will govern the analysis and dispute resolution based on
the governing law.
4. Obtain and review the owner’s Request for Proposal, the contractor’s
Proposal, and any documentation related to the development and
understanding of the contract terms and the contractual scope of work.
6. Review any documents setting forth the contractor’s claim(s) and the owner’s
counterclaims. Identify and describe the nature of the claims and problems
incurred or alleged.
8. Prepare issue files that contain information related to each problem and
claim issue.
10. Identify work areas of the project or parts of the facility affected by the claims
and problems.
11. Identify change orders (approved, disputed, or pending) that have been
submitted by the contractor. Identify notice letters related to change orders or
other alleged impacting events.
14. Identify if construction means and methods changed because of the claims
and problems.
15. Identify any hindrances or interferences to the contractor’s work that were
caused by actions/inactions of the owner or his agent(s).
17. Identify any design or specification problems (errors, ambiguities, etc.) that
may have caused or contributed to the claims and problems.
20. Evaluate any problems that may be associated with gross negligence or willful
misconduct. Obtain guidance from legal counsel on these issues.
21. Identify any “specific information on matters of substance” that may have
been withheld by the owner that, if provided, would have affected contractor’s
bid price.
23. If weather-related delay claims are being alleged, obtain all reports relating to
weather conditions from the project record and from the closest weather
station to the project site.
1. Obtain all native electronic files for the baseline schedule, any rebaseline
schedules, and periodic schedule updates.
4. Identify specific requests for time extension sent to the owner and actual time
extensions granted by the owner due to delays caused by approved change
orders, and time extensions that are associated with pending change orders or
other problems, such as force majeure events, suspensions, etc.
7. Determine if the as-built start and finish dates for the schedule activities
are accurate.
8. Identify the relevant milestones and/or time periods that must be analyzed. In
some projects, for example, liquidated damages are assessed based on the
delays to interim project milestones and not just project completion.
Additionally, a contractor’s time-related costs may be highly variable during
the lifespan of a project, e.g., high during the construction phase but much
lower during the engineering phase.
11. If appropriate and necessary, correct the schedules (logic, dates, durations,
etc.) before performing a retrospective delay analysis, depending on the
schedule delay analysis method(s) being performed.
12. For certain schedule analysis methodologies, prepare activity duration and
relationship variance tables to quantify start and duration delays to schedule
activities. These variance tables may need to be calculated for each of the
various time periods being analyzed.
13. Apportion delays to the activities identified in the duration and relationship
variance tables. Determine responsibility for delays using the Claim Issue
analyses (Section 2 above) already performed, and seeking guidance from
legal counsel and/or technical experts if appropriate.
14. Further analyze any large delays identified in the variance tables that are not
explained by the Claim Issue analyses.
15. Identify the planned and actual start dates, milestone and final completion
dates, and activity durations for activities associated with the problems, as
well as activities on the critical and near-critical paths.
16. Determine if the as-planned and as-built critical paths are different for each
period of the analysis.
17. Identify specific critical and near-critical activities that were delayed and/or
impacted by the problems encountered.
18. Determine if the work affected by the problems was (i) on the as-planned
critical path, or (ii) on the statused critical path at the time the
problem occurred.
19. Determine if there were other delays that occurred before or after the
problems that may be related to or were caused by the problems, i.e.,
dependent concurrent delays.
20. Identify any independent concurrent delays specific to the time frame of
each problem.
22. Determine if there are any compensable delays associated with differing site
conditions, suspensions, work being delayed into bad weather periods, or
other claim issues for which time extensions have not been requested
and granted.
23. For certain schedule analysis methodologies, prepare schedule delay fragnets
based on the identification of the various delays (from Claim Issues analysis
described in Section 2 above), and identify the existing schedule activities that
were impacted. A fragnet is a group of schedule activities inserted into a
schedule that model delaying events.
1. Obtain and review the contractor’s bid and bid estimate calculations and
assumptions, including productivity, material quantities, labor rates,
contingency, field and home office overhead amounts, and profit.
2. Determine if the bid was reasonable, or if there could have been an underbid
or bid error.
3. Obtain and review the contractor’s budget and revised budget information,
including quantity, man-hour, and cost data and underlying assumptions,
noting any differences from the bid estimate.
4. Obtain and review the contractor’s actual quantity, man-hour and costs data.
5. Determine the extent to which the contractor coded its additional man-hours
and costs to discrete change-related cost codes, i.e., did the contractor
segregate its additional work and its base scope work?
7. Obtain and evaluate the approved, pending, and disputed change orders on the
project. To the extent possible, determine the material quantities, man-hours,
and costs included in the changes (which may be difficult in respect to
negotiated, lump sum change orders). Determine if the approved change
orders included field and home office overhead costs.
11. Prepare a cost variance analysis, comparing budgeted and actual costs at the
most detailed level of the information available, including consideration for
any approved or pending change orders.
12. In preparing a claim, utilize the variance analyses to: (i) identify and claim
discretely coded additional work; (ii) identify accounts with overruns that are
claimable; (iii) identify accounts with overruns that are not claimable; (iv)
identify escalation costs to labor, materials, or equipment, based upon
comparisons between budgeted and actual rates; (v) quantify the claimed
amounts for certain cost accounts when a Total Cost or Modified Total Cost
Approach is used; and (vi) demonstrate that the claimed costs are reasonable,
by showing the claimed amounts as compared to the variances or losses.
13. In defending against a claim, utilize variance analyses to: (i) identify potential
underbid or bid error; (ii) demonstrate that claims are being improperly
asserted for accounts in which no man-hour or cost overrun was experienced;
(iii) demonstrate that the entirety of the man-hour or cost overrun for a given
account is being claimed improperly because of demonstrable contractor-
responsible problems; and (iv) identify contractor-responsible issues (e.g.,
material quantity growth from its budget) that may be used to demonstrate
incorrect claim amounts.
14. Related to claims for additional work: (i) confirm contemporaneous estimates
included in the change order documentation; (ii) evaluate and confirm
additional costs using invoices and/or labor man-hours and costs from discrete
change-related accounts; or (iii) alternatively, when better data is not
available, estimate the extent of the additional work.
15. Prepare disruption or loss of productivity claim, which is often the largest
component of a contractor’s claim. To the extent possible, compare the
planned working conditions with the less-productive actual working
conditions for discrete and measurable scopes of work, provide the causes of
the changed conditions, and quantify the resulting loss of productivity.
17. If appropriate man-hour and installed quantity data is available over the
duration of the project, and if there are relatively un-impacted periods of
work, perform a measured mile analysis to determine the loss of productivity
man-hours that may be associated with the alleged impacts.
- Overtime
- Stacked trades/congestion
- Weather impacts
- Out-of-sequence work
- Cumulative impact due to multiple change orders
- Other productivity impacts
20. Determine if the contractor expended additional costs for acceleration and if
the owner has paid for any acceleration costs.
21. Determine if the change orders resulting from the alleged problems included
impact or loss of productivity costs.
23. Determine if there any specific home office overhead man-hour and costs that
can be tied directly to the delays. Consider the use of the Eichleay or other
overhead cost allocation formulae to calculate the compensable home office
overhead delay costs.
24. Determine what construction equipment was used for work relating to the
problems. Obtain and analyze the type, duration, and costs associated with
25. Using the man-hour and cost variance analysis, identify any labor, materials,
or installed equipment escalation costs compared to the bid estimate for labor,
materials, or installed equipment due to delays caused by problems.
26. Update the man-hour and cost variance analyses to include approved and
pending change orders, contractor-caused problems, delays, and other claim
issues to determine if the amount being claimed at the cost account level is
reasonable. Ensure that the man-hours and costs associated with any claims
for which the contractor may be entitled fit into the man-hour and cost
variance matrices such that the claimed man-hours and costs do not exceed the
difference between the current contract value and the actual man-hours and
costs when contractor-caused problems are accounted for in the variances.
27. Calculate the reasonable claim value associated with unresolved suspension or
termination claims.
30. Calculate the reasonable value of any claims associated with a failure to
perform to a standard of care claim.
34. Calculate the reasonable value of any breaches of Implied Warranties claims.
35. Calculate the reasonable value of the contractor’s claim and the owner’s
counter claim against the contractor.
36. Prepare cause-effect matrices that connect the root causes of the problems to
intermediate causes and then to the ultimate effects and costs.