Professional Documents
Culture Documents
THIS AGREEMENT made and entered into this _____ day of September
2018 by and between:
and
____________________________________________________________________________
____________________________________________________________________________
______________, hereinafter called the OWNER.
WITNESSETH,
7. In the event the Owner fails to pay the General Contractor his progress
billings, the General Contractor may stop the work and close down the
site until such payment has been made. However, the General
Contractor shall issue a written notice to the Owner three (3) days prior
to work stoppage. Such work stoppage shall constitute an extension to
the completion of the project.
8. In the event the Owner fails to pay the General Contractor his progress
billings for one (1) month or more from the date of the billing, the
General Contractor shall be given outright an additional interest of 5%
monthly to his billing amount as penalty.
3. At least thirty (30) days before the turn over of the project, the OWNER,
through its authorized representative, shall provide the GENERAL
CONTRACTOR with a list (hereinafter referred to as the “PUNCHLIST”)
enumerating all defects and deficiencies in the work of the GENERAL
CONTRACTOR including those done poorly or in contravention of the
contract documents found upon inspection by latter.
4. The OWNER may request for partial turn-over of completed areas and
may occupy/utilize the habitable premises anytime provided the
GENERAL CONTRACTOR agrees on the conditions to be set forth in
writing on such occupation/utilization. No partial turn-over shall be
made without the written conditions agreed by both parties.
5. In case the Punch List contains items involving extensive work and are
not part of any additional or change order works, which could not be
completed on the date of turnover and the GENERAL CONTRACTOR
failed to complete the works on said date, the GENERAL CONTRACTOR
shall be liable to pay the amounts enumerated herein below over and
above its obligation to complete the construction of the PROJECT.
PESOS: ____________________________________________________________
1. The OWNER, may, at any time, order extra work or modify the work, by
way of adding to and/or deducting from the same, as covered by the
contract documents. Such extra work or change may be initially ordered
by the OWNER’s Architect and confirmed subsequently in writing by the
OWNER’s Architect. No extra work or change shall be considered to have
been authorized without the written confirmation signed by the
OWNER’s Architect. However, no such work shall commence without
the written consent and approval of new cost by the Owner and such
delay shall likewise consider as an extension of construction period on
the part of the General Contractor.
2. The costs incurred by the extra work or change order mentioned above,
whether an increase or decrease in the contract amount, shall be
mutually agreed upon by the OWNER and the GENERAL
CONTRACTOR.
3. All extra work or change order shall only be done after the Owner
approved the additional cost and /or deductive cost submitted by the
General Contractor. All extra work and change order shall entail extra
added time to complete, the Owner shall extend the contract period as
presented by the General Contractor.
1. Any unpaid balance including the retention amount and all change
order and extra work claims due to the GENERAL CONTRACTOR shall
be forfeited in favor of the OWNER under the following conditions:
1.1. In the event the GENERAL CONTRACTOR fails to file with the
OWNER all change order and extra work claims related to the
PROJECT within thirty (30) working days from the date of turn-over.
1.2. In the event the GENERAL CONTRACTOR fails to file with the
OWNER the final billing statement within ninety (90) working days
from the date of turn over.
11. Except as to the end results of the project and matters set forth in the
Contract documents, the GENERAL CONTRACTOR shall perform its
task on its own account, under its own responsibility, free from any
further control or direction of the OWNER especially as to the selection,
discipline, control and supervision of the GENERAL CONTRACTOR’s
personnel who are not, and cannot be deemed, employees of the
OWNER.
13. As a condition for the release of the TEN PERCENT (10%) retention
amount, the GENERAL CONTRACTOR shall submit to the OWNER
original copies of the documents enumerated below:
a. Guarantee Bond
b. Certificate of Completion
c. Turn-over Certificate
d. Punchlist Rectification Certificate
e. Certificate of Final Inspection
f. Electrical Load Record
g. Certificate of Warranty
h. As built Plans (1-set) for: Architectural/Civil Works/Electrical
Work, Plumbing Work
i. Meralco power cerficate (by Owner)
j. Maynilad / DMCI water certificate (by Owner)
1. It is hereby understood and agreed that the entire work called for by
this contract shall not be sub-let or sub-contracted. However, certain
specialty works therein may be sub-let or sub-contracted subject to the
following conditions:
2. The GENERAL CONTRACTOR shall pay the filing fees and facilitate, at
his expense, the processing of all government permits and licenses. Any
penalties, surcharges and all other fines or fees imposed by the
government due to the OWNER’s failure and delay to comply with the
requirements of law shall be fully charged to the OWNER.
___________________ ______________________
___________________ _______________________
GENERAL CONTRACTOR OWNER
WITNESSES:
________________________
________________________