eAM Setups
1. Organization setup
An eAM organization must be classified as an Inventory organization. You can classify an eAM as other
product organizations, as well.
Select the EAM Enabled check box to enable Enterprise Asset Management for this organization. You
cannot clear this check box after Enterprise Asset Management items or Enterprise Asset Management
parameters are defined in the current organization
For organizations that are not Enterprise Asset Management enabled, you can populate the EAM
Organization field with an Enterprise Asset Management enabled organization code. The designated eAM
organization maintains equipment items for the designated production organization.
3. Defining eAM parameters
Dr. Inventory
Cr. Maintenance Offset
A department represents a crew within your organization. A crew may include people, machines,
or suppliers. Department will be assigned to each operation of a routing and resources that are
available for that department will be assigned.
Attribute Usage
Charge Type Manual: You must manually charge it to a job
PO Receipt: Auto charge this resource upon receipt of PO
PO Move: Auto charge this resource upon receipt of a PO and move
the assemblies to Queue of the next operation
Supply Subinventory Enter if the resource is a machine. The system uses the supply
subinventory specified for the resource if the routing does not specify
a supply subinventory.
Outside Processing If outside processing enabled, system uses item defined in this box
when it creates requisitions for your OSP resource
Standard Rate Disable standard rate to enter a rate to charge the resource in WIP for
an internal resource, or derive the rate from the PO for an OSP
resource
For OSP resource, the default is the receiving valuation account from
receiving option in Purchasing setup
Deliver:
Dr. WIP OSP account
Cr. Receiving inventory
Sample of Resources
1. Production Manager
2. Field Manager
3. Planner
4. Maintenance Foreman
5. Lead Operator
6. Operator
7. Maintenance Specialist
8. Mechanic
9. Electrical Specialist
10. Instrument Specialist
11. Logistics
12. Safety
13. EI&O
Note: For PR of OSP resource will be generated, the following checklists must be confirmed.
1. Outside processing line type must be enabled and have outside processing flag checked
** Import source for the PR created for OSP resource is ‘WIP’, where import source for PR created for
direct item is ‘EAM’
Define Department (Crews)
Sample of Department
1. E&I
2. Maintenance
3. Operation
4. HSE
5. Logistics
If the primary approver is blank, a notification will be sent to all users having this responsibility.
Change Item attribute name: transactable and stockable to have ‘Status Setting’ = Defaults Value
Note
Before this attribute can be modified, the Project Manufacturing parameter must be recompiled.
To recompile, just query the project manufacturing parameter via Project Manufacturing
Superuser responsibility. Then unmark enable project…. And re-mark it again, then save the
record and exit the form.
9. Create Asset Group
Creating item by copying from template @asset group
Activity Notification Required = indicate whether the asset requiring work is mobile and should
be brought into the shop for repairs. This is for information purpose only.
Note: Multiple work orders with the same activity cannot have ‘Release’ status at the same
time.
11. Associate assets with Activities
If you create an activity association template, the activity that you associate with the current
asset group automatically determines the activity that is associated with the current asset
number.
Attribute Description
Name Template Name
Description Template description
Type Absolute = Normal meter
Change = take the net change and plus or minus the previous value
(cannot be used with preventive maintenance)
UOM Unit of measure
Value change Ascending e.g. Car mileage (meter always goes up)
Descending e.g. fuel guage (meter always goes down)
Blank = Fluctuating (meter can be up and down) e.g. temperature guage
(cannot be used with preventive maintenance)
Used in scheduling The meter is used in preventive maintenance scheduling. If selected,
usage rate and use past reading field are required.
Rate per day Historical rate per day. If enter ‘1’, system will understand that there is no
historical information for PM calculation.
13. Associate meter template with asset group
3) Go to Meter Association, the meter name will be automatically created with naming
convention = TEMPLATE NAME – X (running number)
If the asset is saved, it cannot be deleted. The asset can be inactive if there are no open WO or
WR for the asset and if the asset is not part of an asset hierarchy.
Attribute Description
Owning department Represent the crew responsible for the asset. WR
Notifications will be sent to the Primary approver
of the owning department.
WIP Accounting class Identify the expense account of the WO performed
for the asset.
Maintainable If this box is checked, then you can create WR / WO
for the asset.
Attribute Description
Asset Number Enter the name of asset route
Attribute Description
Seq User defined or auto defaulted as per profile setup
Code Standard operation code, if standard operation is
predefined and used.
Department Department where the operation is performed
Referenced Any changes to standard operations are reflected in the
routing.
Attribute Description
Auto Request Material Indicate that PR/PO are created automatically, for the current
component or Direct Item when the WO is released.
18. Defining Rebuildable Item
Create item using @Rebuildable template. Rebuildable item is an inventory transactable but non-
purchasable item.
19. Define Activities for Rebuildable and associate to the Asset Group
** The instantiate process is a one-time process. After the process is successful, the current
status of the asset number changes to ‘Resides in stores’ and the instantiate option is disabled.
** If the activity template and meter template are defined in prior step, the activity and meter
will be automatic associated with this new asset number after the instantiates process
completed.
Non-stock direct items can represent items that are not stocked in inventory, such as services
that are purchased from a supplier. Non-stock direct items are defined in Item master as an
inventory, purchased, purchasable item but not stockable.
These items are delivered directly to the shop floor for maintenance WO execution.
You can defined non-stock direct item using @non-stocked items template
Profile: PO: Enable Direct Delivery To Shop Floor must be set to ‘YES’ to enable direct item