Activity Unit Worker Dense Medium Light


Site Clearing m2 1/day 50 125 275
Excavation m2 1/day 2.75 3.5 5
Compaction m2 1/day 500
mason culvert laying m3 1/day 1
concrete culvert laying m3 1/day 1
Formwork m2 4/day 18
Reinforcement kg 3/day 640
Concreting m3 5/day 10
Drywall m2 4/day 18
Painting m3 1/day 44
Timber Door ea 1/day 2.5
Wall Tiling m2 2/day 15.6
Floor Tiling m3 2/day 18
Fixing Aircon duct m 2/day 3.2
Fix Electrical Conduit m 2/day 24
Fix Cold water m 2/day 20
Road Basecourse(urban)
Spread & Compact m3 day 240
Trimming m2 hr 250
Road Basecourse(rural)
Spread & Compact m3 day 400
Trimming m2 hr 350
Road Line m hr 20.5
Road Surfaces machine laying m2 hr 145 Asphalt
100 mm in two coats m2 hr 160 Tarmacadem
Road Surfaces machine laying m2 hr 5 asphalt
100 mm in two coats m2 hr 7.7 tarmacadem