You are on page 1of 6

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/250073199

Fidic’s Red Book 1999 edition: a study review

Article  in  Management Procurement and Law · January 2010


DOI: 10.1680/mpal.2010.163.3.129

CITATIONS READS

3 11,451

5 authors, including:

Onur Dursun Sohrab Donyavi


Hitit University University of Reading
2 PUBLICATIONS   3 CITATIONS    5 PUBLICATIONS   9 CITATIONS   

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Sohrab Donyavi on 22 May 2014.

The user has requested enhancement of the downloaded file.


Proceedings of the Institution of
Civil Engineers
Management, Procurement and Law
163
August 2010 Issue MP3
Pages 129–133
doi: 10.1680/mpal.2010.163.3.129
Paper 900056
Received 22/09/2009
Accepted 20/01/2010
Jan-Bertram Hillig Dauda Dan-Asabe Sohrab Donyavi Onur Dursun Anjana Thampuratty
Keywords: Rechtsanwalt, Leinemann & PhD candidate, University of PhD candidate, University of Research Assistant and PhD Architect, Mumbai, India
contracts & law/disputes & Partner, Frankfurt, Germany Reading, UK Reading, UK candidate, University of
arbitration/liability Stuttgart, Germany

Fidic’s Red Book 1999 edition: a study review


J.-B. Hillig PhD, D. Dan-Asabe MSc, S. Donyavi MSc, O. Dursun MSc and A. Thampuratty MSc

The paper describes the main features of the 1999 engineering projects. The last major update of this suite
edition of Fidic’s Red Book, possibly the most commonly stems from 1999. Corbett (2002) referred to the standard
used standard-form construction contract in forms which were published in 1999 as ‘Fidic’s rainbow’
international projects. The paper is addressed to because Fidic refers to them under different colours.
construction professionals who already have an
(a) Red Book 1999: Conditions of Contract for Construction,
understanding of English construction contracts but have
1st edn (Fidic, 1999a).
not yet looked into Fidic contracts. The 1999 Red Book
(b) Yellow Book 1999: Conditions of Contract for Plant and
is for use when the contractor has been given the design
Design-Build, 1st edn (Fidic, 1999b).
by the employer. The contract features general and
(c) Silver Book 1999: Conditions of Contract for EPC/Turnkey
particular conditions, the latter of which have to be
Projects, 1st edn (Fidic, 1999c).
drafted by the parties before the contract is entered
(d ) Green Book 1999: Short Form of Contract, 1st edn (Fidic,
into. A typical feature of the 1999 Red Book is the role of
1999d).
the engineer. Whether he has to act for the employer or
whether he has to make a fair determination depends on Since 1999 Fidic has published the following other contracts.
the matter in question. There are two striking
(a) Model Representative Agreement, test edn, 2004 (Fidic,
differences from the contract JCT SBC 2005 regarding
2004).
claims of the contractor. First, only the 1999 Red Book
(b) White Book 2006: Client/Consultant Model Services
contains strict time bars. Second, the clauses which
Agreement, 4th edn (Fidic, 2006a).
contain events that justify claims are spread out over the
(c) Harmonised Red Book 2006: Conditions of Contract for
whole contract and not contained in comprehensive lists
Construction (Multilateral Development Bank
of events. New features are clause 13.2 on value
Harmonised), 1st edn (Fidic, 2006b).
engineering and clause 20 on the impartial dispute
(d ) Blue–Green Book 2006: Form of Contract for Dredging
adjudication board.
and Reclamation Works, 1st edn (Fidic, 2006c).
(e) Gold Book 2008: Conditions of Contract for Design, Build
1. INTRODUCTION: THE STUDY GROUP
and Operate Projects, 1st edn (Fidic, 2008a).
This is a report on the findings of the study group on
( f ) Standard Prequalification Form, 3rd edn, 2008 (Fidic,
international construction law at the school of construction
2008b).
management and engineering, University of Reading. The
study group was set up in 2008 to bring together people with The main contracts of 1999 all contain 20 clauses and 17 of
an interest in international construction law. The group these clauses have common clause titles (Corbett, 2002: p. 1).
studied the clauses of the Fidic 1999 Red Book (Fidic, 1999a) Fidic contracts have been translated into about 15 languages
and their practical implications, and compared the contract which indicates their widespread relevance and use. No other
with others. The report is an introduction to the main standard-form construction contract has been translated into
features of the 1999 Red Book for construction professionals so many languages.
who already have an understanding of English construction
contracts but have not yet looked into Fidic contracts. 3. FIDIC’S RED BOOK 1999
Different topics were examined by pinpointing the relevant The 1999 Red Book is the flagship of all Fidic contracts. Like
clauses in the 1999 Red Book. the other contracts, it is recommended for use ‘where tenders
are invited on an international basis’ (Foreword to the
2. FIDIC AND ITS SUITE OF CONTRACTS contract). Although the contract is officially called the
The acronym Fidic stands for the French name of the Conditions of Contract for Construction and Fidic refers to it
International Federation of Consulting Engineers: Fédération as the ‘Construction Contract’, it is popularly better known as
Internationale des Ingénieurs-Conseils. This organisation has the ‘new Red Book’ or the ‘1999 Red Book’. The contract
its headquarters in Geneva, Switzerland. Its members are should not be called the ‘Red Book’ because that name is
national associations of consulting engineers. Fidic is best associated with Fidic’s Conditions of Contract for Works of
known for publishing a suite of contracts for international Civil Engineering Construction, 4th edition of 1987

Management, Procurement and Law 163 Issue MP3 Fidic’s Red Book 1999 edition: a study review Hillig et al. 129
(Fidic, 1987). Even though the 1987 contract was not the ground surface, making the quantities very difficult to
supplemented by the 1999 Red Book, the latter can in many predict. Other re-measurement contracts than Fidic’s Red
ways be seen as the successor of the 1987 Red Book. The Book 1999 are, for example, the seventh edition of the ICE
subtitle of the 1999 Red Book points out that the contract conditions (ICE 7; ICE, 2007) and the Standard Building
was drafted ‘for building and engineering works designed by Contract (SBC) of the Joint Contracts Tribunal (JCT) in its
the Employer’. It is thus a contract for the procurement version ‘with approximate quantities’ (JCT, 2009a). By
method of general contracting. The most interesting feature contrast, the most common form of JCT SBC is its version
of the 1999 Red Book, according to Murdoch and Hughes ‘with quantities’ (JCT, 2009b) (referred to hereafter as JCT
(2008: p. 113), is its division into general conditions and SBC 05), which is a lump sum contract, as is the 1999 Yellow
particular conditions. The contract’s foreword makes clear Book of Fidic. The 1999 Red Book can easily be transformed
that these two parts together form the ‘conditions of contract’ into a lump sum contract, and the guidance for the
that govern the rights and obligations of the parties. The preparation of the particular conditions, against clause 14,
general conditions contain clauses of general applicability, details the necessary steps for this transformation. In lump
and they are complemented by the appendix to tender, to be sum contracts the contractor takes both the risk that the
found at the end of the contract, in which the parties are to agreed price per unit is too low and the risk that the initially
specify the contract specific data, such as the period of time estimated quantity of works was an underestimation.
for completion, the governing law, or the amount of the
liquidated damages. By contrast, the particular conditions 5. RETENTION MONEY
allow the parties to change the general conditions. They need Another issue, related to payment, is the retention money
to be drafted for each project. Fidic has included a guidance which the employer is allowed to withhold until the project
for the preparation of the particular conditions into the 1999 has been completed. Clauses 14.3 and 14.9 of the 1999 Red
Red Book which describes circumstances in which it may be Book provide several rules regarding the retention money.
appropriate to change the general conditions. This guidance Interestingly, there is no default provision laid down in the
also contains examples of wording for the particular 1999 Red Book regarding the percentage. Instead, the parties
conditions. Drafters of the particular conditions are further have to enter a percentage into the appendix to tender. This is
assisted by a Microsoft Word model document of the a difference to JCT SBC 05 where a 3% default is specified
particular conditions, containing a set of columns in which and ICE 7 where a 5% default is specified. The first half of the
the particular conditions can be inserted. This model is part retention money must be paid out when the taking-over
of the electronic version of the 1999 Red Book. Finally, an certificate is issued (clause 14.9; regarding that certificate see
important item of background information is that the Section 6 of this paper). If the works are divided into sections
underlying legal concepts of the 1999 Red Book are based on or parts, and if the engineer issues a taking-over certificate
English law. This is so because the contracts are published in for a section or part, a proportion of the retention money is to
English and because the first edition of the Red Book, be released. That proportion is 40% of the estimated contract
published in 1957, was based on the fourth version of the value of the section or part divided by the estimated final
Conditions of Contract of the English Institution of Civil contract price (clause 14.9; see also Bunni, 2005: p. 579). This
Engineers of 1954 (ICE, 1954). 40% rule is a particularity of the 1999 Red Book. Under other
contracts, the proportion is 50% of the value of the completed
4. PAYMENT: THE 1999 RED BOOK IS A section; see, for example, clause 4.20 of JCT SBC 05.
‘RE-MEASUREMENT CONTRACT’
The topic of payment is dealt with in clause 14. This clause 6. CERTIFICATES BY THE ENGINEER
has 15 sub-clauses. In addition, clause 1.1.4 provides The engineer has various roles under the 1999 Red Book. He
definitions of payment-related terms. One thing to be learnt is the employer’s agent, certifier, designer, supervisor and
from the definitions is that the ‘accepted contract amount’ decision maker. Clause 3.1(a) of the 1999 Red Book stipulates
refers to the sum stated in the ‘letter of acceptance’ (clause that the engineer acts for the employer. However, according
1.1.4.1) – that is, the contract price as agreed at the to clause 3.5 the engineer has to make a ‘fair determination’
beginning – whereas the ‘contract price’ is the sum which the (if he cannot find an agreement with both parties) in cases in
employer will eventually pay (clause 1.1.4.2). These two which clause 3.5 is referred to in the relevant clause of the
amounts will usually differ because the initially agreed price 1999 Red Book (for example, a clause on claims or on a
(the accepted contract amount) will be adjusted (either certificate). In these cases, the engineer has a quasi-judicial
increased or decreased) to determine the ‘contract price’. The (impartial) role similar to that of the contract administrator
adjustments take place according to the valuations of the under JCT SBC 2005. Whereas this concept is typical for
works actually done (see clause 14.1). This feature makes the English standard-form construction contracts, it is alien to
1999 Red Book a so-called ‘re-measurement contract’. In this the practice in other jurisdictions. For example, the German
category of contract the works actually undertaken are contract VOB/B (Vergabe- und Vertragsordnung für
valued, and the valuation takes place on the basis of the bill Bauleistungen) 2006 edition (DVA, 2006) does not mention a
of quantities. The typical risk allocation implied by contract administrator (or architect/engineer) and under that
re-measurement contracts is that while the contractor takes contract it is for the employer to decide about the completion
the risk that the agreed price per unit is too low (i.e. lower of the works: clause 12 of VOB/B 2006 says that the
than the actual price), the employer takes the risk that the employer declares the acceptance (‘Abnahme’) of the works
initially estimated quantity of work turns out to be an which is a broad equivalent to the practical completion
underestimation. Re-measurement contracts are typically certificate under JCT SBC 2005. As already pointed out, the
used for civil engineering works when large parts are below neutral role of the engineer under Fidic’s 1999 Red Book has

130 Management, Procurement and Law 163 Issue MP3 Fidic’s Red Book 1999 edition: a study review Hillig et al.
a rather limited scope of application: clause 3.5 states that 7. DELAY DAMAGES
the engineer only has to act fairly if clause 3.5 is referred to What is usually called ‘liquidated damages’ in English contract
in the relevant clause of the 1999 Red Book. These instances law is referred to as ‘delay damages’ in the 1999 Red Book (see
primarily refer to claims of the contractor for time or money. clause 8.7). There are always two questions regarding delay
By contrast, clause 10 about the taking-over certificate does damages, namely ‘what is their amount?’ and ‘how is the period
not mention clause 3.5. Thus, it seems that the engineer is of delay being assessed?’ Regarding the first question, clause
allowed to make an unfair determination. This issue has also 8.7 provides that the amount has to be specified by the parties
been described by Ndekugri et al. (2007: p. 796) who in the appendix to tender. Interestingly, the amount is supposed
conclude that it would not be wise of the engineer to make to be specified as a percentage of the ‘contract price’ (which is
an unfair determination to the detriment of the contractor, the final price of the works) per day, and not, as in other
and to be open about it, because the contractor would then standard-from contracts (such as JCT contracts), as a particular
certainly apply to the (neutral) dispute adjudication board sum of money per day. Another particularity of the 1999 Red
(clause 20.2 of the 1999 Red Book) to review the decision. Book is that the parties should specify a ‘ceiling’ in the
Another feature of the 1999 Red Book is the option to agree appendix to tender which the delay damages cannot exceed, for
in the contract that the engineer must not exercise any example ‘10% of the final contract price’. The second question
powers without the employer’s approval (see guidance for the ‘how is the period of delay being assessed?’ is also answered by
preparation of the particular conditions, which is part of the clause 8.7: the delay is the period between the ‘time for
1999 Red Book, under clause 3). If that option is agreed, the completion’ and the issuance of the ‘taking-over certificate’.
engineer is never in a neutral role. Regarding this certificate see the previous section: the
calculation of the ‘time for completion’ requires two steps. First,
The study group further looked especially at the taking-over a look into the appendix of tender shows the number of days in
certificate (clause 10). With this certificate the engineer which the works have to be completed, as specified by the
confirms that the works have been completed in accordance parties, for example 100 days. Second, the moment when this
with the contract. This is a crucial step in the contract period starts is called the ‘commencement date’. According to
administration process. Two details are worth mentioning. clauses 1.1.3.2 and 8.1 of the 1999 Red Book it is the engineer’s
First, clause 10.1 provides a fiction which benefits the task to specify the commencement date. He does so by a notice
contractor: if the engineer does not deal for 28 days with an to the contractor. The notice must be given ‘not less than 7
application of the contractor for the taking-over certificate, days’ before the commencement date and the commencement
the certificate is deemed to have been issued. Second, clause date has to take place within the 42 days after the contractor
10.1(a) provides that defects in the works do not prevent the receives the letter of acceptance (clause 8.1). Following these
certificate from being issued if they ‘will not substantially two steps, the ‘time for completion’ can be assessed, and if the
affect the use of the works . . . for their intended purpose’. In ‘taking-over certificate’ was issued later, the delay has to be
other words, in the case of minor defects the engineer should compensated by the award of ‘delay damages’.
issue the taking-over certificate, and the contractor has to
rectify the defects afterwards. This definition of the level of 8. CLAIMS FOR LOSS AND EXPENSE AND CLAIMS
required completeness is an appropriate provision because FOR EXTENSION OF TIME
defects which can be rectified later do not justify the The clauses regarding claims by contractors are arguably the
withholding of the certificate, with all its consequences. This most cited clauses in any construction contract: contractors
handling of defects in Fidic’s Red Book 1999 edition addresses typically claim for compensation of loss and expense and for
one of the most contentious matters in construction contracts: an extension of time. An extension of time, if granted, prevents
traditionally, the relevant certificate becomes due when the the contractor from becoming liable for ‘delay damages’. Clause
works are ‘substantially complete’, and under this concept it is 20.1 of the 1999 Red Book considers both entitlements of
highly debated whether minor defects prevent ‘substantial contractors, namely those regarding loss and expense and
completion’ from occurring. Regarding the views of the extension of time. The clause stipulates a strict notice period:
courts, see Murdoch and Hughes (2008: p. 192). This problem the contractor must give notice to the engineer no later than 28
was present in the predecessor of the 1999 Red Book and it days after he became aware of, or should have become aware
still subsists in ICE contracts (see ICE 7 clause 48.1) and JCT of, the event that forms the basis of the claim. This time-bar
contracts (see JCT SBC 2005 clause 2.30.1) because there is no clause places a large risk on the contractor because the
definition of substantial or practical completion. This employer will be discharged from all liabilities in connection
shortcoming was highlighted by Latham (1994: p. 99) who with the claim if the notice is given too late. Time-bar clauses
stated: ‘It is surprising that there is no definition in the such as clause 20.1 do not feature in the contract JCT SBC 05.
standard contract documents of what constitutes ‘practical A list of the events which allow an extension of time is
completion’. This matter should be addressed by the JCT’. presented in clause 8.4. Among other events, a ‘variation’ and
Similarly, the lack of a definition of practical completion in ‘exceptionally adverse climatic conditions’ are mentioned there.
JCT contracts was qualified by Davison (2006) as ‘one of JCT’s However, clause 8.4 is not comprehensive in the sense that all
traditional oddities’. events are covered there, for clause 8.4(b) makes reference to
other specific clauses in the 1999 Red Book where events are
Other certificates of the 1999 Red Book issued by the mentioned that justify an extension of time. Even less clearly
engineer are the performance certificate (clause 11.9) which laid out are the events that allow a claim for loss and expense:
corresponds to the certificate of making good under clause there is no clause in the 1999 Red Book which contains a list of
2.39 of JCT SBC 2005, the interim payment certificates these events. However, the study group determined a common
(clause 14.6) and the final payment certificate (clause 14.13). body of writing style for the contractor’s entitlements for both

Management, Procurement and Law 163 Issue MP3 Fidic’s Red Book 1999 edition: a study review Hillig et al. 131
sorts of claims: the relevant clauses can easily be picked out reduction of the construction or maintenance costs of the
from the layout of the contract because they are indented. Their building. This is referred to as ‘value engineering’ in the 1999
wording is usually as follows (see clauses 2.1, 4.7, 10.3, etc.) Red Book. It is an incentive for the contractor because he
shares 50% of the financial benefit which his suggestions
‘(a) an extension of time for any such delay . . .
bring to the employers. According to the clause, the benefit
(b) payment of any such cost . . .’.
equals the difference between the cost savings on the one
A full list of the relevant events can be compiled accordingly. hand and the reduction (if any) of the value which the
In conclusion, in the 1999 Red Book the events that justify project has for the employer on the other. Corbett (2002: p. 4)
claims are contained in clauses which are spread out over the provides the example of a cheaper turbine which leads to
whole contract; the applicable clauses can be found where higher maintenance costs. Here, the net benefit may be less
the relevant subjects are. This approach differs strikingly than the savings in capita cost.
from the contract JCT SBC 2005 where comprehensive lists of
events exist: relevant events for claims for extension of time 11. OTHER FEATURES OF THE 1999 RED BOOK
are contained in clause 2.29, and relevant matters for claims Other interesting and important features of the contract are,
for loss and expense are contained in clause 4.24. The JCT among others: the entitlement of the contractor to request
approach appears to be preferable for users who want to evidence of the employer’s financial arrangements to pay the
ascertain whether they have a claim against the other party. contractor (clause 2.4); the requirement of monthly progress
reports by the contractor (clause 4.21); the possibility to
9. DISPUTE ADJUDICATION BOARD extend the 365 days defects notification period (during which
Previous versions of Fidic’s Red Book stipulated that any the contractor has to remedy defects) by up to 2 years if a
dispute had first to be referred to the engineer before it could defect or damage prevents the use of the works for their
be referred to arbitration. This is different in the 1999 Red intended purpose (clause 11.3); the employer’s right to
Book. The engineer’s decision has been replaced by the terminate the contract for convenience subject to a 28-day
decision of an impartial dispute adjudication board (DAB). notice period (clause 15.5); the contractor’s right to suspend
The relevant provisions can be found in clauses 20.2 to 20.4 the works in case of late payment or late certification
of the contract, and additional rules on the DAB are laid (clause 16); the limitation of liability according to which both
down in the appendix entitled ‘general conditions of dispute parties are not liable to the other party for consequential
adjudication agreement’, the annex ‘procedural rules’ (both damages such as damages for loss of use of any works or
documents can be found after the general conditions), the loss of profit (clause 17.6); and the entitlement of the
appendix to tender and the dispute adjudication agreement contractor to claim for loss and expense and additional time
(both documents are in the section ‘forms’ of the 1999 Red in case of force majeure, the definition of which is well laid
Book). The DAB consists of one or three members, dependent out in the contract (clause 19).
on the parties’ determination in the appendix to tender. One
of the innovative features of the DAB is that its members 12. CONCLUSION
visit the site on a regular basis unless the parties decide for This study examined the main features of the 1999 Red Book.
an ad hoc DAB when the dispute arrives. Such site visits While many concepts of the contract are similar to the
have the purpose to enable the DAB members to become and concepts of the standard-form contracts commonly used in
remain acquainted with the progress of the works and of any the English jurisdiction, other concepts of Fidic are different.
actual or potential problems or claims (see annex procedural This is especially true regarding the strict notice periods for
rules 1 and 2). This feature can provide the members of the the contractor’s claims and the DAB that visits the site
DAB with first-hand information unavailable to judges or regularly from the beginning of a project. Another finding of
arbitrators who are called upon when the dispute arises. the study group was the experience that the process of
Corbett (2002: p. 3) praises the new DAB as a feature of ‘best familiarisation with a new standard-form of contract will
practice’ and he expects substantially reduced durations of inevitably take time, but that this time investment is
disputes. worthwhile because it deepens the understanding of how
construction contracts work.
The decision of the DAB is binding for both parties (clause
20.4). If any party is dissatisfied with the decision, it must REFERENCES
issue a notice of its dissatisfaction to the other party within Bunni NG (2005) The FIDIC Forms of Contract: The Fourth
28 days (clause 20.4). The parties can then attempt to solve Edition of the Red Book, 1992. The 1996 Supplement.
the dispute by amicable settlement (clause 20.5) or refer it to The 1999 Red Book. The 1999 Yellow Book. The 1999
arbitration (clause 20.6). If arbitration is chosen, clause 20.6 Silver Book, 3rd edn. Blackwell, Oxford, UK.
refers to the rules of arbitration of the International Chamber Corbett E (2002) Delivering Infrastructure: International Best
of Commerce (ICC) which are often adopted for international Practice – FIDIC’s 1999 Rainbow: Best Practice? Society
contracts. A schematic illustration for the typical sequence of of Construction Law, London, Paper D023. See http://
dispute resolution and time periods under the 1999 Red Book www.scl.org.uk/node/751 (accessed 06/07/2010).
can be obtained at the early pages of the contract. Davison J (2006) JCT 2005 – What’s New?, 1st edn. RICS
Books, Coventry, UK.
10. VALUE ENGINEERING DVA (Deutschen Vergabe- und Vertragsausschuss für
Clause 13.2 incentivises the contractor to suggest changes to Bauleistungen) (2006) Vergabe- und Vertragsordnung für
the works which, if adopted, would benefit the employer. For Bauleistungen (VOB), Teil B: Allgemeine
example, such changes can lead to a quicker completion or a Vertragsbedingungen für die Ausführung von

132 Management, Procurement and Law 163 Issue MP3 Fidic’s Red Book 1999 edition: a study review Hillig et al.
Bauleistungen (VOB/B) (Procurement and Construction Fidic (2008a) Conditions of Contract for Design, Build and
Contract Procedures, Part B: General Conditions of Operate Projects, 1st edn (2008 Gold Book). Fidic, Geneva,
Contract for the Execution of Works). DVA, Berlin, Switzerland.
Germany (in German). Fidic (2008b) Standard Prequalification Form, 3rd edn. Fidic,
Fidic (International Federation of Consulting Engineers) (1987) Geneva, Switzerland.
Conditions of Contract for Works of Civil Engineering ICE (Institution of Civil Engineers) (1954) Conditions of
Construction, 4th edn. Fidic, Geneva, Switzerland. Contract, 4th edn. ICE, London.
Fidic (1999a) Conditions of Contract for Construction, 1st edn ICE (2007) ICE Conditions of Contract Measurement Version,
(1999 Red Book). Fidic, Geneva, Switzerland. 7th edn. Institution of Civil Engineers, Association of
Fidic (1999b) Conditions of Contract for Plant and Design- Consulting Engineers and Civil Engineering Contractors
Build Projects, 1st edn (1999 Yellow Book). Fidic, Geneva, Association, London.
Switzerland. JCT (Joint Contracts Tribunal) (2009a) Standard Building
Fidic (1999c) Conditions of Contract for EPC/Turnkey Projects, Contract with Approximate Quantities, Revision 2 2009.
1st edn (1999 Silver Book). Fidic, Geneva, Switzerland. Sweet and Maxwell, Andover.
Fidic (1999d) Short Form of Contract, 1st edn (1999 Green JCT (2009b) Standard Building Contract with Quantities,
Book). Fidic, Geneva, Switzerland. Revision 2 2009. Sweet and Maxwell, Andover.
Fidic (2004) Model Representative Agreement, Test edn. Fidic, Latham M (1994) Constructing the Team. Joint Review of
Geneva, Switzerland. Procurement and Contractual Arrangements in the United
Fidic (2006a) Client/Consultant Model Services Agreement, 4th Kingdom Construction Industry (Latham Report). Her
edn. Fidic, Geneva, Switzerland. Majesty’s Stationery Office, London, UK.
Fidic (2006b) Conditions of Contract for Construction, Murdoch J and Hughes W (2008) Construction Contracts: Law
Multilateral Development Bank Harmonised edn. Fidic, and Management, 4th edn. Taylor and Francis, London,
Geneva, Switzerland. UK.
Fidic (2006c) Form of Contract for Dredging and Reclamation Ndekugri I, Smith N and Hughes W (2007) The engineer under
Works, 1st edn (2006 Blue-Green Book). Fidic, Geneva, FIDIC’s conditions for construction. Construction
Switzerland. Management and Economics 25(7): 791–799.

What do you think?


To discuss this paper, please email up to 500 words to the editor at journals@ice.org.uk. Your contribution will be forwarded to the
author(s) for a reply and, if considered appropriate by the editorial panel, will be published as a discussion in a future issue of the
journal.
Proceedings journals rely entirely on contributions sent in by civil engineering professionals, academics and students. Papers should be
2000–5000 words long (briefing papers should be 1000–2000 words long), with adequate illustrations and references. You can submit
your paper online via www.icevirtuallibrary.com/content/journals, where you will also find detailed author guidelines.

Management, Procurement and Law 163 Issue MP3 Fidic’s Red Book 1999 edition: a study review Hillig et al. 133

View publication stats

You might also like