You are on page 1of 1

DPR (Daily Progress Report)- Electrical

Project UG+G+2P+9F Typ+RF MIXED USE RESIDENTAL BUILD (102)


Client MR. AHMED AL ZAROONI
Consultant KAIZEN ARCHITECTS & ENGINEERING Date 8/10/2018
Main Contractor FLAMINGO CITY BUILDING CONTRACTING LLC
Sub-Contractor NABA-AL-WADI TECHNICAL WORKS LLC

% of Actual % of
SNO Activity Description Area/Location QTY Area of Concern Area of Concern Remarks
Progress Date Progress

1 DB&ONU fixing on 3rd floor 3rd floor 90%

2 DB&ONU Wall conduiting 3rd floor 32%

3 GI- Box fixing on 3rd floor 3rd floor 40%

4 PVC-Wall conduiting on 3rd floor 3rd floor 28%

Substation lighting&power cable pulling


5 DB fixing
Ground floor 100%

DAILY PROGRESS REPORT (DPR) IT MUST BE SUBMITTED DAILY TO MEP MANAGER BEFORE 5:00 PM
List of Equipments/Tools Manpower Details
Sno. Tools/Equipments Used Quantity Location Sl No. Designation Nos
1 Eng. 1 Prepared by Checked by

2 Supervisor/Forman 1
3 Technician 3
4 Helper 14 Elect ENG. Anwar MEP MANAGER

You might also like