You are on page 1of 3

Project Site Development Works

Location Caltex Mamplasan Station Extended Lot

BALANCE OF WORKS (AS OF JANUARY 26)


TOTAL BALANCE COMPLETED ACC. THIS WEEK
Pavement 4,107.62 299.76 7% 3,946.06 96% +3%
Curb and Gutter 874.60 67.25 8% 807.35 92% +7%
Sidewalk 1,557.00 540.10 35% 1,016.90 65% +25%
BALANCE OF WORKS (AS OF JANUARY 12)
TOTAL BALANCE COMPLETED ACC. THIS WEEK
Pavement 4,174.62 299.76 7% 3,835.06 92% 0%
Curb and Gutter 870.40 130.25 15% 740.15 85% +30%
Sidewalk 1,531.69 885.79 58% 645.90 42% +0%

NOTE: Quantities exclude additional works


curb and gutter
this date balance
4107.62 7.62 6
4.53 11.6
4.5 10.25
1 8.2
0.6 2
0.6 7.5
15.6 17
9.5 1.8
60.4 0.6
7.5 0.6
50 4.2
4 4.2
14 4.2
0.6 1.2
0.6 1.2
4 9.5
12.5 15.6
4 4.8
0.6 4.8
0.6 2
550.40 202.75 740.15 13
130.25
total curb 870.4

You might also like