You are on page 1of 27

Shaft Generators

Power Take Off from the Main Engine

Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Contents:
1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

2. Definitions and Designations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

3. Categories of Shaft Generators . . . . . . . . . . . . . . . . . . . . . . . . . . 5

3.1 PTO/GCR (Power Take Off / Gear Constant Ratio) . . . . . . . . . . . 5

3.2 PTO/RCF (Power Take Off / Renk Constant Frequency) . . . . . . . 5

3.3 PTO/CFE (Power Take Off / Constant Frequency Electrical) . . . . 6

4. Physical Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

4.1 Front end installation (BW I) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

4.2 Front end installation (BW II) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

4.3 Side mounted installation (BW III) . . . . . . . . . . . . . . . . . . . . . . . . 11

4.4 Aft end installation (BW IV) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

4.5 Front end installation (DMG/CFE) . . . . . . . . . . . . . . . . . . . . . . . . 14

4.6 Aft end installation (SMG/CFE). . . . . . . . . . . . . . . . . . . . . . . . . . . 15

5. Layout of Engine with Shaft Generator . . . . . . . . . . . . . . . . . . . . 16

6. Torsional Vibration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

6.1 Engines with small shaft generators . . . . . . . . . . . . . . . . . . . . . . 18

6.2 Engines with large shaft generators . . . . . . . . . . . . . . . . . . . . . . . 18

7. Engine Governing System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

8. Pros and Cons (shaft generators versus gensets) . . . . . . . . . . 19

8.1 Advantages – shaft generators . . . . . . . . . . . . . . . . . . . . . . . . . . 19

8.2 Disadvantages – shaft generators . . . . . . . . . . . . . . . . . . . . . . . . 19

9. Economic Comparison . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

10. Typical Applications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

11. Special Applications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

11.1 Shuttle tankers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

11.2 Auxiliary propulsion system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

12. Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

1
2
Shaft Generators
Power Take Off from the Main Engine

Preface 1. Introduction drive systems, and they will not be dis-


cussed in this paper.

The purpose of this paper is to provide During the 1980s the use of shaft gen- In the following, the term "shaft genera-
detailed information about the various erators in conjunction with two-stroke tor" is employed for any arrangement
aspects related to the application of diesel engines rapidly became a popu- where a Power Take Off from the main
shaft generators on the MAN B&W lar method of producing electric power engine or the shaftline is used to drive
MC series of engines. for the various electricity consumers on an alternator, i.e for the purpose of pro-
board ships. ducing electricity using the main engine
Shortly after introducing the first MC as the prime mover.
engines in 1982, MAN B&W Diesel At that time most gensets were unable
started investigating the possibilities of to operate on heavy fuel oil and, even
using shaft generators on the engines, if they were, the fuel oil prices were
and several standardised shaft genera- much higher than today, so because of
tor types were developed. the differences in efficiency of the two-
troke engine and the medium-speed
In this paper the individual types of genset engine, the use of a shaft gen-
shaft generators are defined and their erator often resulted in significant fuel
physical configuration is described to- cost savings.
gether with the interface with the diesel
engine. Nowadays, a wide range of gensets,
able to operate efficiently on heavy fuel
Given the nature of this paper, it can be oil and, at the same time, offering a
used either to obtain a complete de- high degree of reliability, are available,
scription of the relevant aspects or it and it is tempting to ask whether the
can be used for reference. installation of a shaft generator is really
economical?

This paper highlights a number of pa-


rameters which may influence the final
selection of the electricity production
plant. Beyond the fuel oil costs, it is im-
portant to consider a number of other
parameters, some of them impossible
to quantify, if we are to obtain a clear
picture of the pros and cons of the
shaft generator concept.

References show that a number of


shipowners still consider a shaft gener-
ator to be an attractive investment, e.g.
on container vessels, product tankers
and shuttle tankers, and a number of
different types and various physical
configurations of shaft generators are
available. The paper describes these
types together with their interface with
the two-stroke diesel engine, and ex-
amples are given of typical as well as
special applications.

As an alternative to producing electri-


city, a Power Take Off can be used, for
example, to drive a hydraulic pump di-
rectly. However, only a marginal num-
ber of PTO systems are made as direct

3
2. Definitions and Designations Alternative types and layouts Total efficiency
Design Seating
of shaft generators (%)
On engine
Basically, MAN B&W Diesel distinguish 1 BW I/GCR 92
(vertical generator)
between three main categories of shaft
generators:
2 BW II/GCR On tanktop 92
PTO/GCR

1) PTO/GCR (Power Take Off/Gear


Constant Ratio): 3 BW III/GCR On engine 92
Consists of flexible coupling, step-
up gear, torsionally rigid coupling
and alternator. 4 BW IV/GCR On tanktop 92

2) PTO/RCF (Power Take Off/Renk On engine


Constant Frequency): 5a 5b BW I/RCF 88-91
(vertical generator)
Consists of flexible coupling, step-
up gear, torsionally rigid couplings, On tanktop
PTO/RCF

6a 6b BW II/RCF (vertical generator) 88-91


RCF-gear and alternator.

3) PTO/CFE (Power Take Off/Con- 7a 7b BW III/RCF On engine 88-91


stant Frequency Electrical):
Consists of flexible coupling, step-up
gear, torsionally rigid coupling, al- 8a 8b BW IV/RCF On tanktop 88-91
ternator and electrical control equip-
ment or, alternatively, a slow-running 9a 9b On engine 81-85
BW I/CFE
alternator with electrical control (vertical generator)
equipment.
10a 10b BW II/CFE On tanktop 81-85
The PTO/RCF and the PTO/CFE incor-
porate different kinds of frequency con-
PTO/CFE

11a 11b BW III/CFE On engine 81-85


trol systems which make it possible to
produce electric power with constant
electrical frequency at varying engine 12a 12b BW IV/CFE On tanktop 81-85
speed. The PTO/GCR has no fre-
quency control system.
13a 13b DMG/CFE On engine 84-88
Shaft generators of all three categories
can be installed either at the front end 14a 14b SMG/CFE On tanktop 84-88
of the engine, at the side of the engine
or aft of the engine. Figure 1 shows, in
principle, the various possibilities for
the installation of a shaft generator. Fig. 1: Types of PTO

The designations BW I ... BW IV are of an S50MC-C engine is thus desig-


used to distinguish between the vari- nated:
ous physical configurations of the shaft
generator system. BW III S50-C / GCR 700 - 60

In MAN B&W Diesel terms, a 700 kW In the following chapters, the three
(60 Hz) shaft generator of the GCR types of PTO (PTO/GCR, PTO/RCF,
type intended for installation at the side PTO/CFE) and the various possibilities
for the configuration of the PTO (BW I
... BW IV) are described.

4
3. Categories of Shaft supplying electric power for all other 3.2 PTO/RCF (Power Take Off /
Generators power consumers. Renk Constant Frequency)

3.1 PTO/GCR (Power Take Off / The total efficiency of the PTO/GCR is The PTO/RCF includes an RCF speed
Gear Constant Ratio) around 92%. controlled planetary gearbox devel-
oped by Renk, and the system is only
The PTO/GCR is the simplest shaft Except for the PTO BW I/GCR and the available from Renk. Figure 2 illustrates
generator, as no speed control or fre- PTO BW III/GCR, which are built di- the design principles of the RCF gear-
quency control systems are incorpo- rectly onto the main engine, and is only box.
rated. In the vast majority of cases, the produced by Renk in Germany, several
PTO/GCR is used to produce electric manufacturers are able to supply the The RCF gearbox is an epicyclic gear
power with a constant electrical fre- PTO/GCR system. Prices vary greatly with a hydrostatic superposition drive.
quency during the voyage. Since the with the physical configuration of the The superposition drive comprises a
frequency produced by the alternator system and the different suppliers. The hydrostatic motor controlled by an
is proportional to the speed of the en- investment cost of a PTO/GCR is much electronic control unit and driven by a
gine, the engine must be operated at smaller than the cost of a PTO/RCF or built-on pump.
constant speed. This is only possible a PTO/CFE. On the other hand, the in-
if a controllable pitch propeller is in- vestment cost of the controllable pitch The hydrostatic system drives the an-
stalled. When a fixed pitch propeller is propeller required in combination with a nulus of the epicyclic gear in either di-
used, the speed of the propeller, and PTO/GCR is higher than the cost of a rection of rotation, based on the
thus of the engine, varies with the fixed pitch propeller. detected output speed, and thus con-
required speed of the ship and the re- tinuously varies the gear ratio over an
sistance acting on the ship. Finally, the operation of the engine at engine speed variation of 30%. In the
constant speed means reduced pro- standard layout the constant output
Alternatively, the PTO/GCR can be peller efficiency at reduced propulsion speed range of the gearbox is set be-
used for power production with floating load compared with a controllable pitch tween 100% and 70% of the engine
frequency, e.g. between 50 and 60 Hz, propeller running in combinator mode speed at specified MCR.
which means that the speed of the (reduced speed at reduced propulsion
main engine is allowed to vary between load) or a fixed pitch propeller. The
83% and 100% of the speed at speci- thermal efficiency of the main engine is
fied MCR (Maximum Continuous Rat- also slightly lower in constant speed
ing). This also means that certain mode than in combinator mode.
power consumers sensitive to fre-
quency variations must be provided To panel
with power supply via a frequency con-
verter or from a genset. The concept of Hydrostatic
long-term running with floating electri- control
cal frequency is only used in rare
cases. Operator control panel
Hydrostatic (in switchboard)
motor
The PTO/GCR is unable to run in paral-
Output shaft
lel with the auxiliary engines for long
periods, because of the small engine
speed variations of the main engine
which occur even in the constant Hydrostatic pump
speed mode of the controllable pitch
propeller plant. Consequently, the
PTO/GCR is often used to supply elec-
tric power to all power consumers dur- Multi-disc clutch
ing the voyage, with the gensets out of
operation. During manoeuvring, which
involves reducing the main engine Input shaft
speed, the PTO/GCR can be used as a Controller
separate power source for the bow
thruster, which can often be run with Terminal
floating frequency, with the gensets
Fig. 2: PTO/RCF, developed by Renk

5
An electronic control system ensures Mains, constant frequency
that the control signals to the main
electrical switchboard are identical to
those of the gensets, and the
PTO/RCF is able to operate alone or in Synchronous
parallel with the gensets throughout the Excitation condenser
complete constant output speed range converter G
of the gearbox. The PTO/RCF is there-
fore suitable for installation on ships
with a fixed pitch propeller.

Internal control circuits and interlocking Diesel engine Smoothing


functions between the epicyclic gear Static reactor
and the electronic control box provide DMG converter
automatic control of the functions ne-
cessary for the satisfactory operation
Fig.3: PTO DMG/CFE
and protection of the RCF gear.

If any monitored value exceeds the


normal operation limits, a warning or an
alarm is given depending on the origin,
severity and the extent of deviation
3.3 PTO/CFE (Power Take Off / integrated into the intermediate shaft
from the permissible values. The cause
Constant Frequency Electrical) (SMG/CFE, Shaft Mounted Generator).
of a warning or an alarm is shown on a
The slow-running generators are much
digital display.
The PTO/CFE is, like the PTO/RCF, larger than the generators running at
able to produce electricity with con- high speed, but in return the flexible
A multi-disc clutch, integrated into the
stant electrical frequency over a wide coupling and the step-up gear are
RCF-gearbox input shaft, permits the
engine speed range. In the case of the omitted.
engaging and disengaging of the
PTO/CFE using a step-up gear, the al-
epicyclic gear, and thus the alternator,
ternator may have a built-in electronic Again, additional electrical control
from the main engine during operation.
converter, which ensures that correc- equipment must be installed to provide
tions are made for the varying engine thyristor control of the frequency. The
Depending on the actual engine speed
speed, and hence the varying alterna- DMG/CFE and the SMG/CFE are nor-
relative to the speed at specified MCR,
tor speed. Alternatively, and more mally able to operate in parallel with the
the total efficiency varies between 88%
usually, the electric power is produced gensets at the full rated electric power,
and 91%.
with varying frequency and is after- when the speed of the main engine is
wards converted by thyristor control between 75% and 100% of the engine
to electric power with a constant fre- speed at specified MCR. Between 40%
quency. and 75% of the SMCR speed, the elec-
tric output of the PTO/CFE is reduced
Over the years, different types of proportionately to the engine speed.
PTO/CFE based on step-up gears Figure 3 shows the control principle for
have been introduced, and a limited the DMG/CFE.
number of units have been built.
However, to our knowledge, this type The SMG/CFE (Shaft Mounted Genera-
of shaft generator is not used for new- tor) is much more frequently used than
buildings at the moment. We therefore the DMG/CFE (Direct Mounted Gener-
disregard the PTO/CFE based on a ator). One reason may be that the
step-up gear in this paper. SMG/CFE is not subject to any limita-
tions from the installation on the main
The PTO/CFE can, alternatively, be engine.
made as a slow-running alternator
coupled directly to the front end of the The total efficiency of the slow running
engine (DMG/CFE, Direct Mounted PTO/CFE types varies between 84%
Generator) or installed with the rotor and 88%.

6
4. Physical Configuration
4.1 Front end installation (BW I)

In the BW I system, the step-up gear unit


is bolted directly to the engine front end
face and comprises a bevel gear, which
allows the alternator to be placed verti-
cally on top of the gear unit. See Figure
4. This compact design gear unit is only
available from Renk.

A Geislinger elastic damping coupling is


included in the delivery. The elastic ele-
ments in the Geislinger coupling are
packages of steel springs, and the
damping is provided by oil, which is
squeezed from one oil chamber to an-
other by the steel springs, when they
deflect during operation. The oil also
provides the necessary lubrication and
cooling of the coupling. The Geislinger
coupling is bolted to the front end of the
crankshaft, and the input shaft of the
gear unit is connected to the Geislinger
coupling by a toothed coupling made as
an integral part of the Geislinger coup-
ling. Thanks to this design, the gear unit
is isolated from axial movements of the
crankshaft and protected against tor-
sional excitations.

Additionally, the toothed coupling allows


Fig. 4: PTO BW I S70/RCF 850-60 (Renk)
simple separation of the complete gear
unit from the Geislinger coupling, and
thus the crankshaft, by shifting the shaft
which carries the main gear wheel for-
A multi-disc clutch is built into the RCF gear requires a 5 µm filtration of
ward in the axial direction. This proce-
gearbox input shaft and ensures that the oil, the complete gear unit has a
dure for disconnection is only to be used
the epicyclic RCF gear (if included) separate lubricating oil system includ-
in the special event that it is required to
and the alternator, can be engaged ing the oil supply to the Geislinger
completely disconnect the gear unit from
or disengaged during operation of coupling.
the main engine.
the main engine.
Around the Geislinger coupling, between
An electrically driven built-on lubricat-
the crankcase space and the gear unit,
ing oil stand-by pump supplements a
space is available for a tuning wheel,
gear driven pump when the engine is
a moment compensator or a torsional
started and in the event of malfunc-
vibration damper, if required.
tioning of the gear driven pump.
The gear unit, often referred to as a
The PTO/RCF can be operated on
“crankshaft gear”, is bolted to the bed-
the same type of oil as is used for the
plate and framebox of the engine, and
main engine lubricating oil system.
the weight of the gear wheels is, via
However, in the case of the PTO
bearings installed in the gearbox, trans-
BW I/RCF the RCF gear is integrated
ferred to the engine structure. Conse-
into the step-up / bevel gear unit and
quently, the crankshaft is only loaded by
because the hydrostatic drive of the
the weight of the Geislinger coupling.

7
For the PTO BW I/RCF, the shipyard
must provide cooling water for the

PTO BW IV/GCR
PTO BW III/GCR
PTO BW IV/RCF
built-on lubricating oil cooler, electric

PTO BW III/RCF

PTO BW II/GCR
PTO BW II/RCF

PTO BW I/GCR
PTO DMG/CFE

PTO SMG/CFE
PTO BW I/RCF
power supply to the built-on lubricating
oil stand-by pump and cabling be-
tween the alternator and the switch-
board. We further recommend that the
shipyard installs an external lubricating
oil filling system, including a dosage
Cooling water supply to lub. oil
tank made in accordance with the x x x x x x
specified volume of oil used for one cooler
gearbox oil change. See Figure 5. Cooling water supply to alternator
(x) (x)
- if water cooled type is applied
The PTO BW I/GCR is lubricated and
cooled by using the main engine lubri- Lub. oil dosage tank (option) (x) (x) (x) (x)
cating oil system. This means that the
cooling water supply and the external Electric power supply to lub. oil
x x x x x x x x
lubricating oil filling system can be dis- stand-by pump
pensed with. In this case, the capaci-
ties of the main engine’s lubricating oil Cabling between alternator and
x x x x x x x x
system with related coolers must be in- switchboard
creased in accordance with the data
External wiring of control system x x x x
given by the supplier of the shaft gen-
erator. The shipyard has to arrange the Electric cabling x x
external wiring of the control system.
The PTO BW I/GCR has not yet been Seating for gearbox x x x x
produced.
Seating for support bearing (x) (x)
The following preparations for the in-
Seating for alternator x x
stallation of the PTO system must be
made on the engine. See also Figure 6. Seating for synchronous condenser
x x
unit
• three machined blocks welded on to
the front end face for alignment of Seating for static converter cubicles x x
the gear unit
Seating for stator housing x
• machined washers to be placed be-
tween the gearbox and the framebox
to compensate for the small differ- Fig. 5: Shipyard installations for PTO
ence in length between the bedplate
and the framebox

• rubber gasket to be placed between


the gearbox and the framebox

• electronic axial vibration measuring


system

• free flange end on lubricating oil inlet


pipe (only for PTO BW I/GCR)

• oil return flange welded on to bed-


plate (only for PTO BW I/GCR).

8
4.2 Front end installation (BW II)

PTO BW IV/GCR
PTO BW III/GCR
PTO BW IV/RCF
The PTO BW II is placed in front of the

PTO BW III/RCF

PTO BW II/GCR
PTO BW II/RCF

PTO BW I/GCR
PTO DMG/CFE

PTO SMG/CFE
PTO BW I/RCF
engine but, in contrast to the PTO
BW I, the gear unit is seated on a sep-
arate foundation on the tanktop.

Various gearbox manufacturers are


able to supply the PTO BW II/GCR,
whereas only Renk is able to supply Machined blocks welded on to
x x x x x
the PTO BW II/RCF. engine front end face

Machined washers to be placed


The installation length in front of the en- x x x x
between gearbox and framebox
gine, and thus the engine room length
requirement, naturally exceeds the Rubber gasket to be placed between
length of the other shaft generator ar- x x x x
gearbox and framebox
rangements. However, there is some
scope for limiting the space require- Steel shim to be placed between
x
ment, depending on the configuration gearbox and framebox
chosen.
Electronic axial vibration measuring
x x x x x x x
system

Free flange end on lubricating oil inlet


x x x
pipe

Oil return flange welded to bedplate x x x

Brackets mounted on side of


x x
bedplate

Intermediate shaft between crank-


x x
shaft front end and flexible coupling

Front end cover in two halves, with


x x
oil sealing arrangement

Fig. 6: Engine preparations for PTO

9
Figure 7 shows a space optimised con- Alternator Torsionally Step-up
cept where the alternator is placed ho- rigid gear
coupling
rizontally between the step-up gearbox
and the front end of the engine and
thus utilises the space which is anyway
taken up by the flexible coupling.

A further reduction of the building-in


length can be obtained by the use of
a bevel gear in the step-up gearbox
and a vertically placed alternator, see
Figure 8.

A rubber type elastic damping coupling


is installed at the gearbox input shaft
outside the engine. The engine drives
the shaft generator via an intermediate
shaft, which is bolted to the front end
of the crankshaft and passes through
the engine front end cover, which is Main engine Support Flexible coupling
made in two halves with an oil sealing side bearing
arrangement.

Fig.7: PTO BW II/GCR (A. Friedr. Flender AG)

Alternator

Flexible
coupling

Step-up
gear

Fig.8: PTO BW II/GCR (Renk)

10
Often a small support bearing has to 4.3 Side mounted installation The gear unit, often referred to as a
be installed between the front end of (BW III) “crankshaft gear”, is bolted to the bed-
the engine and the flexible coupling. plate and framebox of the engine, and
Whether a support bearing is required The investment cost of the PTO BW III the weight of the gear wheels is, via
can be determined from MAN B&W is typically higher than for the other bearings installed in the gearbox, trans-
Diesel’s specification of the permissible gear based shaft generators. However, ferred to the engine structure. Conse-
shear force and bending moment on we have adopted it as our standard, as quently, the crankshaft is only loaded
the front end of the crankshaft. it is the most compact system avail- by the weight of the Geislinger coup-
able, which means more space for ling.
The PTO BW II has its own lubricating cargo transportation, and a further ad-
oil system, and an electrically driven vantage is that it is easy to install at the The step-up gear of the PTO BW III/
built-on lubricating oil stand-by pump shipyard. GCR is lubricated and cooled using the
supplements a gear driven pump at main engine lubricating oil system, so it
start of the engine and in the event of The gearbox is available as standard requires no cooling water supply. The
malfunctioning of the gear driven for the 42-98MC engines. Standard capacities of the main engine’s lubri-
pump. sizes of alternators are 700, 1200, cating oil system with related coolers
1800 and 2600 kW, but others are are to be increased accordingly.
The gearbox and the support bearing available on request.
are seated on the tanktop, and the A multi-disc clutch is built into the gear-
shipyard has to make suitable founda- In the BW III system, the step-up gear box output shaft and ensures that the
tions. The shipyard must also provide unit is bolted directly to the engine front alternator can be engaged or disen-
cooling water for the built-on lubricat- end face, and is designed to allow the gaged during operation of the main
ing oil cooler, electric power supply to alternator to be placed horizontally at engine. The required operating oil pres-
the built-on lubricating oil stand-by the side of the engine. See Figure 9, sure for the multi-disc clutch is sup-
pump and cabling between the alterna- which shows the PTO BW III/GCR. plied by a gear driven pump. On engine
tor and the switchboard, as well as This compact design gear unit is only start-up and in the event of malfunc-
external wiring of the control system available from Renk. tioning of the gear driven pump, an
(except for the PTO BW II/RCF). electrically driven built-on lubricating oil
A Geislinger elastic damping coupling stand-by pump supplements the gear
For the PTO BW II/RCF we recom- is included in the delivery. The driven pump.
mend that the shipyard installs an ex- Geislinger coupling is described in
ternal lubricating oil filling system, Section 4.1.
including a dosage tank made in ac-
cordance with the specified volume of
oil used for one gearbox oil change.

The following preparations for the in-


stallation of the PTO system must be Combined
made on the engine: Geislinger
and toothed
coupling
• intermediate shaft between the en-
gine and the flexible coupling Crankshaft
gear
• front end cover in two halves with oil Alternator
sealing arrangement

• electronic axial vibration measuring


system.

Brackets

Bedframe Toothed coupling Multi-disc clutch

Fig. 9: PTO BW III/GCR (Renk)

11
Operator
control
panel

Combined
Geislinger
Alternator and toothed
coupling
Controller
Crankshaft gear

Bedframe Brackets

RCF unit
incl. multi-
disc clutch
Toothed coupling

Fig. 10: PTO BW III/RCF (Renk)

The step-up gear (crankshaft gear) of lubricating oil cooler built on to the RCF • machined washers to be placed
the PTO BW III/RCF is, similar to the gear, electric power supply to the lubri- between the gearbox and the frame-
crankshaft gear of the PTO BW III/GCR, cating oil stand-by pump built on to the box to compensate for the small dif-
lubricated and cooled by using the RCF gear and cabling between the alter- ference in length between the
main engine lubricating oil system. nator and the switchboard. We further bedplate and the framebox
Figure 10 shows the PTO BW III/RCF. recommend that the shipyard installs an
external lubricating oil filling system, in- • rubber gasket to be placed between
The RCF gear, placed at the side of the cluding a dosage tank made in accor- the gearbox and the framebox
engine, can be operated on the same dance with the specified volume of oil
type of oil as the main engine lubricat- used for one RCF-gear oil change. • electronic axial vibration measuring
ing oil system. However, the hydro- system
static drive of the RCF gear requires a The PTO BW III/GCR only requires
5 µm filtration of the oil, and the RCF electric power supply to the built-on • free flange end on lubricating oil inlet
gear, consequently, has its own lubri- lubricating oil stand-by pump and ca- pipe
cating oil system. bling between the alternator and the
switchboard as well as external wiring • oil return flange welded on to bed-
A multi-disc clutch is built into the RCF of the control system. plate
gearbox, and an electrically driven lu-
bricating oil stand-by pump, built on to The following preparations for the in- • brackets mounted on starboard side
the RCF gear, supplements a gear stallation of the PTO BW III/GCR sys- of bedplate to support the RCF gear
driven pump on engine start-up and in tem or the PTO BW III/RCF system (if installed) and the alternator.
the event of malfunctioning of the gear must be made on the engine:
driven pump.
• three machined blocks welded on to
For the PTO BW III/RCF the shipyard the front end face for alignment of
must provide cooling water for the the gear unit

12
4.4 Aft end installation (BW IV) termediate shaft flange at the engine foundations, both for the gearbox and
aft end and the hollow shaft of the tun- the alternator. The shipyard must also
The PTO BW IV is placed aft of the en- nel gearbox. Some of the steel flanges provide cooling water for the built-on
gine and is made as a tunnel gear with used for the coupling are made in lubricating oil cooler, electric power
a hollow shaft, which allows the inter- halves to allow them to be assembled supply for the built-on lubricating oil
mediate shaft, including the flange, to around the shaft. stand-by pump and cabling between
pass through, see Figure 11. the alternator and the switchboard, as
The flexible coupling only transfers the well as external wiring of the control
A number of gearbox manufacturers torque corresponding to the power of system (except for the PTO BW IV/
are able to supply the PTO BW IV/GCR, the shaft generator, since the interme- RCF).
whereas only Renk is able to supply diate shaft for the propeller is bolted di-
the PTO BW IV/RCF, although it has rectly to the thrust shaft of the engine. No preparations for the installation of
not yet been produced. the PTO system are needed on the
The PTO BW IV has a separate lubri- engine, but the intermediate shaft
The PTO BW IV can often be installed cating oil system, and an electrically flange must be provided with additional
within the space already available driven built-on lubricating oil stand-by bolt holes for the flexible coupling.
around the shaftline aft of the engine, pump supplements a gear driven pump
without increasing the total building-in on engine start-up and in the event of
length. any malfunctioning of the gear driven
pump.
A hollow, segmented elastic damping
coupling based on rubber elements is The gearbox is seated on the tanktop,
built around the shaft between the in- and the shipyard has to make suitable

Vulkan Rato
flexible coupling

Alternator
Toothed
coupling

Tunnel gear

Fig. 11: PTO BW IV/GCR, Tunnel gear

13
Static frequency converter system

Synchronous
condenser Distribution cubicle
Converter cubicle To
switchboard
Excitation cubicle
Control cubicle

Cooler

Oil seal cover Support


Rotor bearing

Stator housing

Fig. 12: PTO DMG/CFE

4.5 Front end installation front end support bearing to reduce the Since the frequency converter system
(DMG/CFE) load on the crankshaft. uses a DC intermediate link, it can
supply no reactive power to the main
The PTO DMG/CFE is a large slow- The electrical frequency generated de- switchboard. A synchronous con-
running alternator with its rotor pends on the speed of the main engine denser is used to supply this reactive
mounted directly on the crankshaft and and the number of poles. Since the power. The synchronous condenser
its stator housing bolted to the front size of the alternator, and thus the consists of an ordinary synchronous
end face of the engine. The PTO number of poles, is limited by the alternator.
DMG/CFE does not include a gearbox, ship’s hull, it is not possible, with the
and no flexible coupling is required. low speed of the two-stroke engine, for The DMG/CFE is normally able to oper-
See Figure 12. The alternator is sepa- the alternator itself to produce electric- ate in parallel with the gensets at the
rated from the crankcase by a plate ity with a frequency of 50 Hz or 60 Hz. full rated electric power, when the
and a labyrinth seal. It is therefore necessary to use a static speed of the main engine is between
frequency converter system between 75% and 100% of the engine speed at
If the torsional characteristics of the the alternator and the main switch- specified MCR. Between 40% and
shaft system require the application of board. 75% of the SMCR speed, the electric
an additional inertia mass on the crank- output of the DMG/CFE is reduced
shaft fore end, a tuning wheel can be The static frequency converter system, proportionately to the engine speed.
installed, as illustrated in Figure 13. see Figure 12, consists of a static part,
A front end mounted moment compen- i.e. thyristors and control equipment, The shipyard must provide seating for
sator or a torsional vibration damper and a rotary electric machine (synchro- the synchronous condenser unit and
may be installed in a similar way. nous condenser). the static converter cubicles, as well as
cooling water, if a water cooled alterna-
If the limits for shear force and bending The three-phase alternating current is tor is used, and electric cabling.
moment acting on the fore end flange rectified and conducted to a thyristor
of the crankshaft are exceeded, the inverter producing a three-phase alter-
stator housing must be made with a nating current with constant frequency.

14
4.6 Aft end installation (SMG/CFE)
Stator housing Stator housing
Stuffing box Stuffing box The PTO SMG/CFE has the same
Air Air
Crankshaft Crankshaft working principle as the PTO
cooler cooler
DMG/CFE, but instead of being located
on the front end of the engine, the
alternator is installed aft of the engine,
with the rotor integrated on the inter-
Support mediate shaft. See Figure 14. This con-
bearing cept is much more frequently used
than the PTO DMG/CFE, and has the
Pole
advantages of a somewhat lower price
wheel
and a more straightforward design with
no physical interface with the main en-
gine.

In addition to the shipyard installations


Pole wheel Main Tuning wheel Main mentioned in Section 4.5 for the PTO
bearing No. 1 bearing No. 1 DMG/CFE, the shipyard must provide
the foundation for the stator housing in
Standard engine, with direct Standard engine, with direct the case of the PTO SMG/CFE.
mounted generator (DMG/CFE) mounted generator and tuning wheel
The engine needs no preparation for
the installation of this PTO system.
Fig. 13: PTO DMG/CFE

The following preparations for the in-


stallation of the PTO system must be
made on the engine:

• three machined blocks welded on to


the front end face for alignment of
the stator housing

• steel shim to be placed between the


stator housing and the framebox to
compensate for the small difference
in length between the bedplate and
the framebox

• electronic axial vibration measuring


system.

References show that at present the


PTO DMG/CFE is very rarely used.

Fig. 14: PTO SMG/CFE 1300-60 (AEG)

15
5. Layout of Engine with basis of the propeller design point (PD) In most cases, the SMCR of an engine
Shaft Generator by incorporating the following factors, with a shaft generator is found by add-
please refer to Figure 15: ing the maximum power consumed by
the shaft generator to the specified
Beyond the physical preparations of • light running factor (normally 3-7% of propulsion MCR point (MP).
the engine for the installation of a shaft the engine speed at PD is deducted) See Figure 16.
generator, the layout of the engine in
terms of power and speed is also af- • sea margin (traditionally 15% of the Consequently, the engine with a shaft
fected by the decision to install a shaft power at PD is added – following the generator is specified with the maxi-
generator. heavy running propeller curve and mum continuous rating (M) and the op-
giving the service propulsion point timising point (O) located on a propeller
As an example the following describes SP = S) curve placed to the left of the propeller
how the installation of a shaft generator curve (through MP) for heavy running
on an engine intended to drive a fixed • engine margin (typically 10% of the propulsion without a shaft generator.
pitch propeller influences the layout of power at MP = M = SMCR is added
the engine: to the power at SP = S – following
the heavy running propeller curve).
The specified maximum continuous
rating (SMCR) of an engine without a
shaft generator can be found on the

Power
2 Heavy propeller curve – fouled hull
and heavy weather
6 Light propeller curve – clean hull
and calm weather
MP
Engine MP: Specified propulsion MCR point
margin SP: Service propulsion point
(10% of MP) SP
PD´ PD: Propeller design point
Sea PD´: Alternative propeller design point
margin
(15% of PD) PD LR: Light running factor
HR: Heavy running

LR(4%)
2 6 HR

Engine speed

Fig. 15: Ship propulsion running points and engine layout

16
The above means that the installation
of a shaft generator may involve that an
engine with one more cylinder must be
selected to ensure that the SMCR
point is placed inside the top of the lay-
out diagram. However, this, of course,
entails extra costs and additional space
requirements for the main engine.

To avoid selecting a main engine with


one more cylinder, another solution is
to restrict the load on the shaft genera-
tor when the engine is operated close
to the SMCR.

More information about the layout of


engines with and without shaft genera-
tors, as well as various examples, can
be found in our paper P.254-96.03:
Basic Principles of Ship Propulsion.

M: Specified MCR of engine


S: Continuous service rating of engine
Power A=M
7 O: Optimising point of engine
O SG
S A: Reference point of load diagram

SG MP MP: Specified propulsion MCR point


SP: Service propulsion point
SP SG: Shaft generator power consumption
r
to
ra
ne

2 6 Definition of point A of load diagram


1
ge

Line 1: Propeller curve through optimising point (O)


aft
Sh

Line 7: Constant power line through specified MCR (M)


Light propeller curve – clean Point A: Intersection between lines 1 and 7
hull and calm weather
Propulsion curve
for heavy running
Engine service curve
for heavy running
Engine speed

Fig. 16: Engine layout with shaft generator (normal case)

17
6. Torsional Vibration As a rule of thumb, the lowest natural The DMG/CFE and the SMG/CFE do
frequency of the shaft generator not incorporate a gear or a flexible
6.1 Engines with small shaft branch should not be less than 120%, coupling but, because of the inertia of
generators or more than 80%, of the frequency the rotor, they may naturally influence
corresponding to the main engine the torsional layout of the shafting.
The gear based shaft generator sys- speed at specified MCR. This means
tems (PTO BW I ... BW IV) all incorpo- that either undercritical or overcritical
rate a flexible coupling to protect the vibration conditions for 1st order exci- 6.2 Engines with large shaft
gears against hammering caused by tation are obtained, with a satisfactory generators
torsional excitation from the engine. safety margin.
Certain types of ships, such as shuttle
Normally, when the power output of If a clutch for the alternator is incorpo- tankers with high electricity consump-
the shaft generator is less than 10 per rated in the PTO/GCR, the tuning of tion, may use one or more large shaft
cent of the main engine power, the vi- the PTO system is normally made as generators for the electricity produc-
bration modes of the shaft generator follows: tion. The propulsion arrangement of a
system will not influence the vibration shuttle tanker with a large shaft gener-
modes of the propulsion shaft system. • Alternator engaged: ator normally comprises a controllable
This means that the main propulsion Overcritical running (1st order critical pitch propeller and a shaft clutch. See
shaft system can be designed and de- speed at 55 - 80% x SMCR speed) Section 11.1.
termined regardless of whether a shaft
generator is to be installed later on. • Alternator disengaged The torsional vibrations of such an in-
Undercritical running (1st order criti- stallation are very complex, and require
The PTO/GCR is normally designed to cal speed above 120% x SMCR careful investigation of all possible op-
operate at 100% of the speed at spe- speed, higher orders to be consid- eration modes during the design stage.
cified MCR, and is therefore tuned so ered).
that the critical speed of significant In general, the elastic coupling, or cou-
T/V-orders is placed outside the range The ideal way of tuning the PTO/RCF, plings, should be sufficiently flexible to
80 - 120% of the speed at specified which is normally designed to operate ensure a natural frequency in the shaft
MCR. between 70% and 105% of the engine generator system below 75% of the
speed at specified MCR, is to have a frequency which corresponds to the
Normally, the flexible couplings for the flexible coupling which leads to a natu- main engine speed to be used for op-
PTO/GCR types are selected on the ral frequency, around 50 - 60% of the eration of the shaft generator.
basis of the misfiring conditions, and frequency which corresponds to the
the normal service conditions will, con- speed at specified MCR. Alternatively, the shaft generator sys-
sequently, usually be harmless to the tem can be designed to have a natural
flexible coupling and the gear. Should the natural frequency be higher, frequency of approximately 150% of
because of a more rigid coupling, the the frequency which corresponds to
In cases of misfiring, the 1st order exci- alternator must be declutched in the the main engine operating speed.
tation, which normally has a frequency event of misfiring. The PTO/RCF is al-
close to the natural frequency of the ways made with a clutch built into the The above will give main critical reso-
1-node vibration mode (the lowest nat- RCF gear, and operation during misfir- nances in the shaft generator system
ural frequency) occurring in the shaft ing is often prohibited. In this case, the (4th, 5th and 6th order) at very low
generator branch, increases substan- magnitude of the alternator’s inertia speed or even below the minimum
tially, irrespective of the number of cyl- must, when the alternator is declutch- speed. Furthermore, the 1st and 2nd
inders of the engine. This explains why ed, permit the natural frequency of the order excitation, which becomes domi-
it is essential to tune the natural fre- shaft generator branch which remains nant in case of misfiring, will have reso-
quency of the 1-node vibration mode coupled to the engine, to ‘jump’ to a nance outside the shaft generator
in accordance with the engine speed. sensibly higher frequency than the fre- operating speed. Such tuning of the
quency which corresponds to 105% of natural frequencies will normally require
The position of the natural frequency the speed at specified MCR. In order to very elastic couplings.
for the 1-node vibration mode in the obtain this, it may be necessary to tune
shaft generator branch mainly depends the inertia of the alternator by fitting an
on the flexible coupling’s torsional flexi- additional mass (tuning wheel) at the al-
bility and the inertia of the alternator. ternator side of the clutch.

18
7. Engine Governing System 8. Pros and Cons (shaft checks of proper functioning and
generators versus gensets) regular replacement of the lubricat-
ing oil and the oil filter, if the shaft
Basically, the following three types of generator has a separate lubricating
governors can be used to control In the following, a number of advan- oil system
modern two-stroke diesel engines: tages and disadvantages related to the
use of shaft generators are discussed: • Low spare parts cost
• conventional electronic governor The high reliability of shaft genera-
with one speed pick-up and stan- tors, together with the low spare
dard software 8.1 Advantages – shaft generators parts consumption for planned
maintenance, result in low spare
• advanced electronic governor with • Small space requirement parts costs
two or more speed pick-ups and The shaft generator is installed close
special software to the engine or the shaft line, and • Long lifetime
often takes up no further space than A shaft generator is generally not ex-
• mechanical-hydraulic governor (for is already set aside for the engine posed to much wear, but of course
small bore engines only). installation. In particular, the PTO components such as bearings, me-
BW III (engine side mounted) and the chanically driven oil pumps, friction
The mechanical-hydraulic governor PTO BW IV (tunnel gear) require little clutches, etc. need to be replaced or
can be used for simple installations in- space for the installation. The reconditioned after many years in
volving the 26-46MC engines, where it SMG/CFE and the DMG/CFE need operation
may provide sufficient governing abili- extra space elsewhere in the engine
ties at an attractive cost. However, an room for the synchronous con- • Low noise
electronic governor is also often used denser and the control cubicles The noise level of a shaft generator
for the 26-46MC engines. All 50-98MC is considerably lower than the noise
engines require an electronic governor. • Low investment cost (PTO/GCR) level of a genset.
The investment cost depends on the
The installation of a shaft generator type and make of the shaft genera-
with an electric output power of less tor. Depending on the origin of the 8.2 Disadvantages – shaft
than 15% of the main engine’s power shaft generator, the PTO/GCR can generators
at specified MCR does not normally be purchased at a relatively low
require special considerations in the price, whereas the frequency con- • No power production in harbour
selection of governor. However, if a trolled types (PTO/RCF and Whether a shaft generator is in-
PTO/GCR is installed together with a PTO/CFE) are relatively expensive stalled or not, the electric power
controllable pitch propeller, it may consumption in harbour will gene-
prove advantageous to use an elec- • Low installation cost rally have to be covered by a genset.
tronic governor even on the smallest The shaft generator requires no sep- However, in special cases where a
engine types to obtain the most stable arate (or only a simple) foundation, clutch is installed in the shaft line, as
engine speed conditions and, hence, no exhaust gas system and only a on shuttle tankers with high electric-
the most stable frequency in the gen- few connections to the auxiliary ity consumption for cargo pumping,
erated electricity. equipment. Furthermore, the time it is possible to use the main engine
spent installing a shaft generator is and the shaft generator for electric
For large shaft generators, the combi- normally short power production in harbour
nation of a low natural frequency and a
high moment of inertia in the alternator • Reliability • Higher load on main engine
may require special facilities in the en- Shaft generators are normally con- The load on the main engine, and
gine governor (i.e. the advanced gover- sidered highly reliable, as is the main thus the specific fuel oil consumption
nor) if instabilities in the system are to engine which drives the shaft gener- and the cylinder oil consumption, in-
be avoided. For plants where the out- ator crease when a shaft generator is
put power of the shaft generator ex- used
ceeds 15% of the main engine’s • Low man-hour cost for mainte-
power, or a clutch or a flexible coupling nance
is installed in the shaft line, we there- The planned maintenance of a shaft
fore recommend investigating whether generator during the first years of
an advanced electronic governor is operation only involves regular
needed.

19
• Reduced propeller and engine effi- 9. Economic Comparison
ciency at low propulsion power for
PTO/GCR
If the PTO/GCR is used for power On the basis of the following data we have compared the operating costs, with
production with a fixed frequency, and without a shaft generator, of a typical feeder container vessel.
which is usually the case, the engine
with a controllable pitch propeller The following alternatives have been compared:
must be operated at constant speed
even at reduced load. The efficiency
Alternative 1: 1 x 7S50MC-C + PTO BW IV GCR/1200 +
of the controllable pitch propeller and
the engine would be higher if the en- 2 x 7L16/24H
gine was operated according to a Alternative 2: 1 x 7S50MC-C + 3 x 7L16/24H
combinator curve, where the speed
was reduced at reduced load We have used the following ratings of the main engines:
Alternative 1: SMCR = 11,060 kW at 127 rpm
• No long-time parallel running ability
for PTO/GCR CP-Propeller running at constant speed
The PTO/GCR cannot run in parallel Alternative 2: SMCR = 9,760 kW at 127 rpm
with the gensets except during load CP-Propeller running at combinator curve
take-over. This means that the power
distribution between the electric
power producers is not as flexible as Propulsion load profile, Alternative 2:
with a pure genset installation
• 90% load for 15% of time at sea
• More complex shaft arrangement
The installation of a shaft generator • 80% load for 40% of time at sea
complicates the shaft arrangement.
Gears and flexible couplings need not • 70% load for 35% of time at sea
be installed for a two-stroke diesel
engine used for propulsion if a shaft • 50% load for 10% of time at sea
generator is not installed.
In order to compare two vessels operating at exactly the same speed, the pro-
pulsion loads for Alternative 1 have been increased to compensate for the re-
duced propeller efficiency at part load, caused by the propeller operating at
constant speed.

Time at sea: 250 days/year


Time in harbour: 115 days/year
Electric load at sea: 900 kW
Electric load in harbour: 500 kW

We have compared the two alternatives with respect to fuel oil costs and lubri-
cating oil costs and found the following result:

Annual additional fuel and lube oil costs for


Alternative 1= 8,630 USD/year

Details of the calculations are shown in Figures 17 and 18.

20
Additionally, we have analysed the maintenance costs for the two alternatives and
estimate that the average annual maintenance costs for a long operating period
are as follows:

Alternative 1:
Main engine, 7S50MC-C: 98,200 USD/year
Shaft generator, PTO BW IV S50-C/GCR 1200: 500 USD/year
Gensets, 2 x 7L16/24H: 4,700 USD/year
Total annual maintenance costs: 103,400 USD/year

Alternative 2:
Main engine, 7S50MC-C: 98,200 USD/year
Gensets, 3 x 7L16/24H: 25,200 USD/year
Total annual maintenance costs: 123,400 USD/year

Annual saving in maintenance costs for Alternative 1: 20,000 USD/year

The maintenance costs include The installation costs may be expected


man-hours for overhaul with an hourly to favour the shaft generator.
wage of 30 USD, and spare part costs
in accordance with normal overhaul Other aspects also need to be consid-
intervals. The maintenance costs also ered, e.g. in some cases a shaft gener-
allow for 30% extra man-hours for ator cannot be installed unless the
unscheduled overhauls. engine is specified with one additional
cylinder. The extra costs for the engine
To sum up the fuel and lube oil costs and its auxiliary equipment related to
together with the expected mainte- an additional cylinder, together with the
nance costs, economic impact of an increased en-
gine room length, have not been evalu-
. However, ated.
the saving only represents around
1.0% of the total annual operating To conclude, many factors influence
costs. the final economic result, and the final
conclusion as to whether the installa-
Assuming a 30,000 USD extra invest- tion of a shaft generator is attractive or
ment cost for the shaft generator com- not can only be made by the owner.
pared with one extra 7L16/24H genset,
the calculation shows a payback time
for Alternative 1 (with shaft generator)
of three years, using the Net Present
Value method with a 3% rate of infla-
tion and a 6% rate of interest.

However, the investment costs for the


shaft generator and the genset may dif-
fer significantly depending on the origin
of the shaft generator and the genset.

21
Machinery arrangement Load pattern
7S50MC-C with PTO Load case 1 2 3 4 5
SMCR (kW) 11,060 Hours 900 2,400 2,100 600 2,760
Efficiency PTO (%) 92 Propulsion power (kW) 8,780 7,833 6,916 5,142 0
2 x 7L16/24H gensets PTO mech. power (kW) 975 975 975 975 0
Main engine power (kW) 9,755 8,808 7,891 6,117 0
Basic data MEP (bar) 16.8 15.1 13.6 10.5 0
Total days at sea 250 SFOC (g/kWh) 168.7 168.3 168.6 170.9 0
Total days in harbour 115 Genset power (kWel) 0 0 0 0 500
HFO price (USD/ton) 110
System oil price (USD/ton) 1,000 Fuel oil consumption
Cylinder oil price (USD/ton) 1,000 Load case 1 2 3 4 5 Total Cost (USD)
Hours 900 2,400 2,100 600 2,760
Main engine power (kW) 9,755 8,808 7,891 6,117 0
SFOC (g/kWh) 168.7 168.3 168.6 170.9 0
Genset power (kWel) 0 0 0 0 500
SFOC (g/kWhel) 0 0 0 0 202
HFO (tons/year) 1,573 3,779 2,968 666 296 9,282 1,021,020
(SFOC: ref. LCV = 42,700 kJ/kg)
(HFO: ref. LCV = 40,200 kJ/kg)

System oil consumption


Load case 1 2 3 4 5 Total Cost (USD)
Hours 900 2,400 2,100 600 2,760
Main engine (kg/24h) 35 35 35 35 0
Genset (kg/24h) 0 0 0 0 12
System oil (tons/year) 1.3 3.5 3.1 0.9 1.4 10.2 10,200

Cylinder oil consumption (based on 1.49 g/kWh at nominal MCR and


reduced proportional to MEP at part load)
Load case 1 2 3 4 5 Total Cost (USD)
Hours 900 2,400 2,100 600 2,760
MEP (bar) 16.8 15.1 13.6 10.5 0
Cylinder oil (tons/year) 13.1 31.4 24.8 5.5 0.0 74.8 74,800

Total cost per year (USD) excl. maintenance cost 1,106,020

Fig. 17: 7S50MC-C with PTO

22
Machinery arrangement Load pattern
7S50MC-C without PTO Load case 1 2 3 4 5
SMCR (kW) 9,760 Hours 900 2,400 2,100 600 2,760
Efficiency PTO (%) – Propulsion power (kW) 8,784 7,808 6,832 4,880 0
3 x 7L16/24H gensets PTO mech. power (kW) 0 0 0 0 0
Main engine power (kW) 8,784 7,808 6,832 4,880 0

Basic data MEP (bar) 16.2 14.8 13.2 9.9 0


Total days at sea 250 SFOC (g/kWh) 166.0 164.3 164.7 168.2 0
Total days in harbour 115 Genset power (kWel) 900 900 900 900 500
HFO price (USD/ton) 110
System oil price (USD/ton) 1,000 Fuel oil consumption
Cylinder oil price (USD/ton) 1,000 Load case 1 2 3 4 5 Total Cost (USD)
Hours 900 2,400 2,100 600 2,760
Main engine power (kW) 8,784 7,808 6,832 4,880 0
SFOC (g/kWh) 166.0 164.3 164.7 168.2 0
Genset power (kWel) 900 900 900 900 500
SFOC (g/kWhel) 205 205 205 205 202
HFO (tons/year) 1,570 3,741 2,921 641 296 9,169 1,008,590
(SFOC: ref. LCV = 42,700 kJ/kg)
(HFO: ref. LCV = 40,200 kJ/kg)

System oil consumption


Load case 1 2 3 4 5 Total Cost (USD)
Hours 900 2,400 2,100 600 2,760
Main engine (kg/24h) 35 35 35 35 0
Genset (kg/24h) 24 24 24 24 12
System oil (tons/year) 2.2 5.9 5.2 1.5 1.4 16.2 16,200

Cylinder oil consumption (based on 1.49 g/kWh at nominal MCR and


reduced proportional to MEP at part load)
Load case 1 2 3 4 5 Total Cost (USD)
Hours 900 2,400 2,100 600 2,760
MEP (bar) 16.2 14.8 13.2 9.9 0
Cylinder oil (tons/year) 12.6 30.8 24.0 5.2 0.0 72.6 72,600

Total cost per year (USD) excl. maintenance cost 1,097,390

Fig. 18: 7S50MC-C without PTO

23
10. Typical Applications 11. Special Applications The large side thruster power installed
on the vessels calls for equipment that
11.1 Shuttle tankers can provide sufficient electricity pro-
At present, the following shaft genera- duction. This means that large diesel
tors are most frequently installed: Shuttle tankers, which load their cargo generators or large shaft generators
from storage facilities at the field or di- need to be installed on all shuttle tank-
PTO BW II/GCR rectly from the production platform, are ers intended for dynamic positioning
widely used to serve offshore oil fields operation. In order to minimise the total
PTO BW III/GCR from which pipeline connections are installed power of the auxiliary power
not practicable. producers, cargo pumps driven by
PTO BW IV/GCR electric motors are normally installed.
High performance manoeuvring equip- The cargo pumps are primarily used to
PTO SMG/CFE ment is made necessary by the operat- unload the cargo in port but may also
ing profile which, during loading of the be used in the field to distribute oil
The PTO BW II/RCF and the PTO BW ship, includes long periods of accurate among the segregated cargo tanks.
III/RCF are also installed from time to dynamic positioning at the field, by us- The maximum power consumption of
time. ing bow and stern thrusters as well as the cargo pumps is typically around
the main propeller. The time required 4-5,000 kW.
Typically, the PTO BW II/GCR and the for loading the oil depends on the load-
PTO BW IV/GCR are used on container ing facilities and may vary from one to One propulsion system which meets
vessels or chemical tankers with ten days in each round trip. the above-mentioned requirements is
26-50MC main engines (and CPP). The the diesel-mechanical system with two
electrical output power is normally Shuttle tankers with 3 x 1750 kW bow low speed main engines and shaft gen-
between 500 and 1200 kW. The PTO thrusters and 2 x 1750 kW stern erators. Figure 19 shows an example
BW III/GCR is mostly used for the thrusters to match the above require- of such an arrangement, where the
same ship types with 50-60MC main ments are in operation. shaft generators are placed in the
engines (and CPP), and the shaft gen- shaftlines.
erator normally has an electrical output
power between 700 and 1800 kW.

The PTO SMG/CFE is often installed on


large container vessels with 70-98MC
main engines (and FPP) and a large
number of reefer plugs. For large con-
tainer vessels, the shaft generator will
often be specified with an electric ca-
pacity of around 2,000-3,500 kW.

The PTO BW III/RCF has been used DG Electric


with all engines in the range from 42 ME motors
to 90MC and can also be installed
together with the 98MC engines. For
small ships with the smallest MC en-
gines (26-35MC) with FPP, the PTO ME
BW II/RCF with a power of around
250-700 kW is occasionally used. DG

SG
ME

ME: Main engine


SG: Shaft generator Disconnectable Cargo
DG: Diesel generator thrust bearing pumps

Fig. 19: Shuttle tanker engine room arrangement with shaft generators

24
Clutches are installed in the shaftlines Such a study normally results in the main engines, the other engine is at
aft of the shaft generators, and are setting of minimum requirements for standstill and accessible for overhaul).
used to disconnect the propeller from the inertia of the alternator as well as
the main engine while in port, so that requirements for the control of the A frequency converter laid out for the
the main engine can be used for elec- main engine, such as an advanced ship’s power consumption is required
tric power production without turning electronic governor and an additional where the shaft generators are to be
the propeller. overspeed shut-down system control- used for power supply for the general
ling a fuel cut-off device. As an addi- electrical consumption of the ship in all
When a clutch is positioned in the tional safety feature it is recommended load conditions (harbour, steaming and
shaftline, an external thrust bearing is that the flexible couplings are made dynamic positioning) and where, in some
required, so that both forward and with a torsional limit device, so that in of these load conditions, the engine
aftward thrust are transmitted to the the event of breakage of the flexible el- speed is not kept at a constant level.
tanktop, aft of the clutch. The clutch ements, steel parts will transmit the
and the thrust bearing are normally torque until the safety system has shut Alternatively, one diesel generator can
made as a unit. down the engine. be used to supply the electric power
for the general electricity consumption
When a clutch is to be placed in the In harbour, the speed, and thus the ef- when the engine speed is reduced.
shaftline, a study of the engine acceler- ficiency, of the cargo pumps can be
ation behaviour must be performed, il- controlled by varying the speed of the In all cases, transformers are needed
lustrating the outcome of an immediate engine that drives the shaft generator to provide voltage regulation between
loss of electrical load on the shaft gen- and thus varying the electrical fre- the alternators and the ship service
erator with the propeller disconnected. quency (in a propulsion plant with two switchboard.

Fig. 20: 8600 kW PTO arrangement for shuttle tanker, being tested at the Renk works

25
11.2 Auxiliary propulsion system The CB-Clutch is operated by hydraulic The requirements of some classification
oil pressure which is supplied by the societies differ depending on whether
From time to time, an auxiliary propul- power pack used to control the the auxiliary propulsion system is to be
sion system (Power Take Off / Power CP-propeller. used as a take home system (in the
Take In) is requested, especially in con- event of failure of the main engine at
nection with projects involving gas and A thrust bearing, which transfers the sea) or as an alternative propulsion
chemical tankers with main engines in auxiliary propulsion propeller thrust to system (take away from quay or alter-
the range of S35-S42MC and equipped the engine thrust bearing when the native propulsion at low vessel speed).
with a CP-propeller. clutch is disengaged, is built into the
CB-Clutch. When the clutch is en- The auxiliary propulsion system offered
The auxiliary propulsion system must gaged, the thrust is transferred stati- by MAN B&W Diesel fulfils the require-
be capable of driving the CP-propeller cally to the engine thrust bearing ments of both alternatives, provided
by using the shaft generator as an through the thrust bearing built into the that sufficient electrical power for auxil-
electric motor while the main engine is clutch. iary propulsion of the vessel can be
stopped and disengaged. The electric produced by the gensets.
power is produced by a number of To obtain high propeller efficiency in
gensets. the auxiliary propulsion mode, and thus The system can quickly establish auxil-
also to minimise the auxiliary power re- iary propulsion from the engine control
MAN B&W Diesel can offer a solution quired, a two-speed tunnel gear, which room and/or bridge, even with unman-
where the CP-propeller is driven by the provides lower propeller speed in the ned engine room.
alternator via a two-speed tunnel gear auxiliary propulsion mode, is used.
box. The main engine is disengaged by Re-establishing of normal operation re-
a clutch (CB-Clutch) made as an inte- The two-speed tunnel gear box is quires attendance in the engine room
gral part of the shafting. The clutch is made with a friction clutch which al- and can be done within a few minutes.
installed between the tunnel gear box lows the propeller to be clutched in at
and the main engine, and conical bolts full alternator/motor speed where the
are used to connect and disconnect full torque is available. The alterna-
the main engine and the shafting. See tor/motor is started in the de-clutched
Figure 21. condition with a start transformer.

Generator/motor
Two-speed Main engine
tunnel gearbox

Oil distribution
ring
Hydraulic
coupling Conical Bolt-
Clutch

Intermediate
bearing

Hydraulic Flexible
coupling coupling

Fig. 21: Auxiliary propulsion system

26
12. Summary heavy fuel oil, improved reliability and On the other hand, when surplus ca-
prolonged mean time between over- pacity is available from the main en-
A wide range of shaft generators are hauls. gine, a shaft generator is still a viable
available for installation in combination solution.
with the two-stroke engines in MAN
B&W Diesel’s comprehensive engine
programme. PTO/GCR Engine type Units
(Renk, A. Friedr. Flender AG, (BW IV/GCR)
The shaft generators are available with Newbrook)
42MC 6
or without frequency control systems.
Some of them use step-up gears, 50MC 4
some of them do not. 60MC 17
80MC 2 29
The installation of a shaft generator af-
(BW III/GCR)
fects the layout of the engine relative to
the propeller, and the shaft generator 42MC 2
must be included in the torsional vibra- 50MC 9
tion calculations. Shaft generators with
60MC 28
normal electric capacity (less than 15%
of the SMCR power) typically do not in- 70MC 0 39
fluence the requirements of the engine (BW II/GCR)
governing system. However, especially 26MC 16
with shaft generators with no frequency
control system, the stability of the en- 35MC 25
gine speed needs to be considered. 42MC 4
50MC 1 46
Shaft generators can be used in spe-
Total 114
cial applications, including shuttle
tanker propulsion arrangements where PTO/RCF Engine type Units
the engine can be disconnected from (Renk)
the propeller and used to drive a large (BW III/RCF)
alternator supplying electric power for 42MC 5
the cargo pumps. 50MC 25
60MC 44
In rare cases, an auxiliary propulsion
system is requested, in which the shaft 70MC 24
generator is used as an electric motor 80MC 14 112
to drive the propeller, with the main en- (BW II/RCF)
gine disconnected (the electric power
is produced by a number of gensets), 26MC 5
and MAN B&W Diesel is able to offer a 35MC 9
tailor-made concept, including the 42MC 1
CP-propeller.
80MC 2 17
References show that most MAN B&W (BW I/RCF)
two-stroke engines are at present in- 70MC 2 2
stalled without a shaft generator. This
Total 131
reflects the fact that many shipowners
and shipyards rather than using a shaft PTO/CFE Engine type Units
generator, prefer the simple engine (Renk) (BW III/CFE)
room arrangement with a directly cou-
pled two-stroke engine for propulsion, 60MC 6
and a number of gensets for electricity 70MC 9 15
production purposes. This may be be- Total 15
cause, in recent years, gensets have
improved their cost effectiveness
thanks to low prices, operation on Reference List (Renk, A. Friedr. Flender AG, Newbrook), as at 1999.06.16

27

You might also like